The University of Notre Dame (USA) in England v. TJAC Waterloo, LLC

49 F.4th 13
CourtCourt of Appeals for the First Circuit
DecidedSeptember 13, 2022
Docket21-1558P
StatusPublished
Cited by2 cases

This text of 49 F.4th 13 (The University of Notre Dame (USA) in England v. TJAC Waterloo, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The University of Notre Dame (USA) in England v. TJAC Waterloo, LLC, 49 F.4th 13 (1st Cir. 2022).

Opinion

United States Court of Appeals For the First Circuit

No. 21-1558

THE UNIVERSITY OF NOTRE DAME (USA) IN ENGLAND,

Plaintiff, Appellee,

v.

TJAC WATERLOO, LLC; ZVI CONSTRUCTION CO., LLC,

Defendants, Appellants.

APPEAL FROM THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MASSACHUSETTS

[Hon. Allison D. Burroughs, U.S. District Judge]

Before

Barron, Chief Judge, Lipez and Gelpí, Circuit Judges.

Richard E. Briansky, with whom Amy B. Hackett and Peckar & Abramson, P.C. were on brief, for appellants. John A. Tarantino, with whom Nicole J. Benjamin and Adler Pollock & Sheehan, P.C. were on brief, for appellee.

September 13, 2022 GELPÍ, Circuit Judge. This is an appeal from the

district court's confirmation of a foreign arbitral tribunal's

assessment of damages in a contractual dispute relating to

construction defects. The underlying arbitration concerns joint

liability claims made by appellee The University of Notre Dame

(USA) in England ("Notre Dame") against appellants TJAC Waterloo,

LLC ("TJAC") and ZVI Construction Co., LLC ("ZVI"), respectively

the seller and renovator of a dormitory that Notre Dame had agreed

to purchase. In a previous decision, we affirmed the district

court's confirmation of the arbitrator's liability judgment

against TJAC and ZVI. See Univ. of Notre Dame (USA) in Eng. v.

TJAC Waterloo, LLC (Notre Dame I), 861 F.3d 287, 296 (1st Cir.

2017). Now, TJAC and ZVI challenge the district court's

confirmation of certain damages awarded to Notre Dame, arguing

that Notre Dame's petition for judicial confirmation of these

awards is time-barred. Because appellants' contentions in this

building-defect dispute rest on shaky foundations, we affirm.

- 2 - I. Background1

Upon purchasing from TJAC the building that ZVI had

renovated, Notre Dame became aware of numerous defects. The

ensuing dispute was submitted to arbitration, and the parties

agreed to bifurcate the proceedings, first trying the liability

elements of Notre Dame's breach-of-contract claim, and

subsequently litigating issues of "quantum" (i.e., damages) for

any breach found during the liability phase. Id. at 290.

In Notre Dame I, we addressed the finality of the

arbitrator's judgment of joint liability against TJAC and ZVI

following the conclusion of the first phase of the arbitration.

861 F.3d at 289. TJAC and ZVI argued that the district court erred

in confirming the arbitrator's liability award because that

judgment -- only pertaining to the first stage of the bifurcated

proceedings -- lacked the requisite finality for judicial

confirmation under the United Nations Convention on the

Recognition and Enforcement of Foreign Arbitral Awards, June 10,

1958, 21 U.S.T. 2517, 330 U.N.T.S. 38 (the "New York Convention").2

1 As this is the second time a dispute relating to the underlying arbitration has made its way to this court, see Notre Dame I, 861 F.3d at 287, we assume the reader's familiarity with our earlier opinion, and rehearse here only the facts and travel necessary to contextualize the instant appeal. 2 The New York Convention is implemented in domestic law by chapter two of the Federal Arbitration Act ("FAA"). See 9 U.S.C. §§ 201-08.

- 3 - Notre Dame I, 861 F.3d at 291. We disagreed, holding that the

same standard of finality applicable under domestic law applies to

proceedings pursuant to the New York Convention and reiterating

our previous determination that "a bifurcated liability judgment

may qualify as final when the arbitrating parties have formally

agreed to litigate liability and damages in separate, independent

stages." Id. at 291-92 (citing Hart Surgical, Inc. v. Ultracision,

Inc., 244 F.3d 231, 235-36 (1st Cir. 2001)). On de novo review,

see Cytyc Corp. v. DEKA Prods. Ltd. P'ship, 439 F.3d 27, 32 (1st

Cir. 2006), we affirmed the district court's finding that the

arbitrator's liability judgment was indeed final and thus

susceptible to judicial confirmation. Notre Dame I, 861 F.3d at

293.

While the parties litigated judicial confirmation of the

liability awards (issued by the arbitrator as Awards No. 1 and No.

2), the arbitration continued to the quantum phase of the

proceedings. Between 2016 and 2020, the arbitrator issued a series

of damages awards concerning various costs that stemmed from the

breach established at the liability stage:

• Award No. 3 ("An Expert Determination on Quantum") -- Dated

September 20, 2016; regarding the preliminary "Cost of Works"

to remediate the deficiencies in the building under contract;

no amount was awarded.

- 4 - • Award No. 4 ("An Expert Determination on Quantum") -- Dated

April 11, 2017; regarding the final cost of works; the amount

awarded was £1,781,048.44.

• Award No. 5 ("Decisions") -- Dated July 27, 2017; regarding

certain additional and ancillary costs of work items not

covered by Award No. 4; the amount awarded was £957,450.00.

• Award No. 6 ("Expert Determination Award No. 6

(Amended)") -- Dated December 5, 2018; regarding interest due

on Awards No. 4 and 5; the amount awarded was £328,001.37 +

£269.52 per day (beginning on November 30, 2018).

• Award No. 7 ("Expert Determination Award No. 7 -- Decisions

as to VAT") -- Dated March 31, 2020; concerning costs relating

to the value-added tax (VAT) previously paid by Notre Dame as

well as remaining outstanding items (e.g., expert fees and

interest); the amount awarded was £547,699.00 + £5,040.00 +

£65,723.00 (interest through August 1, 2018) + £60.02 per day

(beginning on August 2, 2018).

On May 15, 2020, Notre Dame moved for the district court

to confirm these awards and enter summary judgment in its favor.

TJAC and ZVI opposed the motion, arguing that Award No. 4 was, for

purposes of judicial confirmation, final upon issuance and that

Notre Dame's request for confirmation of Award No. 4 was thus time-

barred. Because the FAA provides that a party to an arbitration

may apply for judicial confirmation "[w]ithin three years after an

- 5 - arbitral award falling under the [New York] Convention is made,"

see 9 U.S.C. § 207, and Award No. 4 was issued on April 11, 2017,

TJAC and ZVI posited that the statute of limitations for

confirmation of the award expired on April 11, 2020. Similarly,

TJAC and ZVI argued that Award No. 6 was partially ineligible for

judicial confirmation insofar as it granted interest on the

(putatively unconfirmable) Award No. 4.

The district court disagreed, holding that Award No. 4

was not a final award eligible for judicial confirmation upon

issuance. Instead, the court held that the three-year statute of

limitations for judicial confirmation only began to run upon the

issuance of Award No. 7 on March 31, 2020, as it was only at this

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
49 F.4th 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-university-of-notre-dame-usa-in-england-v-tjac-waterloo-llc-ca1-2022.