Falcon Steel Co. v. Weber Engineering Co.

517 A.2d 281, 1986 Del. Ch. LEXIS 464
CourtCourt of Chancery of Delaware
DecidedSeptember 23, 1986
DocketCiv. A. 8376
StatusPublished
Cited by18 cases

This text of 517 A.2d 281 (Falcon Steel Co. v. Weber Engineering Co.) is published on Counsel Stack Legal Research, covering Court of Chancery of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Falcon Steel Co. v. Weber Engineering Co., 517 A.2d 281, 1986 Del. Ch. LEXIS 464 (Del. Ct. App. 1986).

Opinion

OPINION

JACOBS, Vice-Chancellor.

The plaintiff, Falcon Steel Company (“Falcon”) is the prime contractor for steel fabrication and erection for the construction of a corporate office building for Bec-ton Dickinson and Company (“Becton”) in New Jersey. In 1984 Falcon subcontracted to the defendant Weber Engineering Company (“Weber”) the steel erection portion of its contract with Becton. The Falcon/Weber subcontract called for Falcon to fabricate the steel in Delaware and to deliver it to Weber for erection at the construction site in New Jersey.

As a result of additional work that Weber was required to perform, Weber incurred alleged losses, damages and additional costs which form the basis of a claim by Weber against Falcon totalling $633,-180. On January 6, 1986 Weber filed a demand for arbitration of its claims with the American Arbitration Association pursuant to the arbitration clause of its subcontract with Falcon. Falcon refused to arbitrate and, in response, it brought this action to enjoin the arbitration. Weber answered and counterclaimed for an order requiring Falcon to comply with its contractual agreement to arbitrate Weber’s claim. Simultaneously, Weber moved for judgment on the pleadings. This is the decision of the Court, following briefing and argument, on Weber’s motion for judgment on the pleadings. 1

I.

Weber’s motion is founded upon the language of the arbitration clause of its subcontract with Falcon (“the subcontract”) which provides:

All claims, disputes or other matters in question arising out of or relating to this contract or the breach thereof shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. This agreement to arbitrate shall be specifically enforceable under the United States Arbitration Act. Title IX of the United States Code. The award rendered by the arbitrator shall be final and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.

Weber contends, and Falcon does not dispute, that its claims are covered by the broad language of the subcontract arbitration clause. No challenge is leveled against the validity of the arbitration clause itself. That being the case, Weber argues that Falcon is obligated to arbitrate Weber’s claims as a matter of both Federal *284 and Delaware law, specifically, by virtue of Section 2 of the Federal Arbitration Act (9 U.S.C. § 2) 2 and Section 5701 of the Uniform Arbitration Act (10 Del.C. § 5701).

Section 2 of the Federal Act provides: A written provision in any maritime transaction or a contract evidencing a transaction involving commerce to settle by arbitration a controversy thereafter arising out of such contract or transaction, or the refusal to perform the whole or any part thereof, or an agreement in writing to submit to arbitration an existing controversy arising out of such a contract, transaction, or refusal, shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract. (9 U.S.C. § 2)
10 Del. C. § 5701 provides:
A written agreement to submit to arbitration any controversy existing at or arising after the effective date of the agreement is valid, enforceable and irrevocable, save upon such grounds as exist at law or in equity for the revocation of any contract, without regard to the justi-ciable character of the controversy, and confers jurisdiction on the Chancery Court of the State to enforce it and to enter judgment on an award. In determining any matter arising under this chapter, the Court shall not consider whether the claim with respect to which arbitration is sought is tenable, or otherwise pass upon the merits of the dispute. This chapter also applies to arbitration agreements between employers and employees or between their respective representatives, except as otherwise provided in § 5725 hereunder.

Given the clear statutory language and policy of the federal and state law, which is to encourage arbitration and the enforcement of agreements to arbitrate, 3 and given the breadth of the subcontract arbitration clause to which the parties agreed in this particular instance, it would appear manifest that Weber’s claims are covered by the subcontract arbitration clause and that Falcon is obligated to arbitrate its dispute over those claims. See Pettinaro Construction Co., Inc. v. Harry C. Partridge, Jr. & Sons Inc., supra, 408 A.2d at 963 (enforcing comparable arbitration provision covering “all claims, disputes and other matters in question arising out of or relating to this contract”).

Falcon argues, however, that there is more to the question of arbitrability than meets the eye, and that, properly interpreted, the Weber/Falcon subcontract arbitration clause does not apply to most of Weber’s claims. Falcon contends that most of Weber’s claims are not arbitrable, by virtue of the arbitration clause in the Falcon/Bec-ton prime contract (“the prime contract) which (Falcon argues) is incorporated by reference into the subcontract. Falcon also argues that Weber’s conduct constitutes a waiver of certain of its claims.

In support of its incorporation-by-reference contention, Falcon reasons, somewhat intricately, as follows: the parties incorporated the prime contract (including its arbitration clause) by reference into their subcontract, as evidenced by Subparts 22-24 of Paragraph 2 of the subcontract {See pp. 285-286, infra). Unlike the subcontract arbitration clause which is practically all-inclusive in its scope, the prime contract requires arbitration only for those claims amounting to $50,00.0 or less, and makes claims above that amount subject to litigation.

In further support of its incorporation by reference argument, Falcon relies upon the *285 “conflicts” clause (1117) of the subcontract, which provides that:

In case of conflict between the provisions of the [prime contract]_and the provisions of this [subcontract]_, the provisions of this shall prevail in any matter between the contractor [Falcon] and the subcontractor [Weber].

Based upon the above-quoted language, Falcon argues that since the arbitration provisions of the prime contract and the subcontract are “inconsistent”, the subcontract arbitration clause can only be applicable to . matter[s] between the contractor and the subcontractor”. Falcon argues that any other “matters”, that is, any claims involving the subcontractor (Weber) and the owner (Becton), would be governed by the prime contract arbitration clause, under which all claims over $50,000 are not arbitrable. Applying that premise to Weber’s claims, Falcon concludes that most of Weber’s claims would not be arbitrable, because they exceed $50,000 and because they involve Becton in one or more respects. 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Purvi Gandi-Kapoor v. Hone Capital LLC
Court of Chancery of Delaware, 2023
Jeehye Jung v. El Tinieblo International, Inc.
Court of Chancery of Delaware, 2022
Hurley v. EB Safe LLC
N.D. Texas, 2019
Pavel Menn v. Conmed Corp. and Endodynamix, Inc.
Court of Chancery of Delaware, 2019
Umbach v. Carrington Investment Partners (US), LP
851 F.3d 147 (Second Circuit, 2017)
H&S Ventures, Inc. v. RM Techtronics, LLC
Superior Court of Delaware, 2017
Align Strategic Partners LLC v. Moesser
Court of Chancery of Delaware, 2016
American Insurance Co. v. Siena Construction Corp.
23 Mass. L. Rptr. 232 (Massachusetts Superior Court, 2007)
Habets v. Waste Management, Inc.
363 F.3d 378 (Fifth Circuit, 2004)
Citisteel USA, Inc. v. General Electric Co.
78 F. App'x 832 (Third Circuit, 2003)
DMS Properties-First, Inc. v. P.W. Scott Associates, Inc.
748 A.2d 389 (Supreme Court of Delaware, 2000)
SBC Interactive, Inc. v. Corporate Media Partners
714 A.2d 758 (Supreme Court of Delaware, 1998)
New Castle County v. U.S. Fire Insurance
728 F. Supp. 318 (D. Delaware, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
517 A.2d 281, 1986 Del. Ch. LEXIS 464, Counsel Stack Legal Research, https://law.counselstack.com/opinion/falcon-steel-co-v-weber-engineering-co-delch-1986.