F. Buddie Contracting, Inc. v. Seawright

595 F. Supp. 422, 1984 U.S. Dist. LEXIS 24348
CourtDistrict Court, N.D. Ohio
DecidedAugust 15, 1984
DocketC80-2344
StatusPublished
Cited by23 cases

This text of 595 F. Supp. 422 (F. Buddie Contracting, Inc. v. Seawright) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. Buddie Contracting, Inc. v. Seawright, 595 F. Supp. 422, 1984 U.S. Dist. LEXIS 24348 (N.D. Ohio 1984).

Opinion

MEMORANDUM OPINION

DOWD, District Judge.

Before the Court is the motion for summary judgment of defendant, Peabody Galion, Inc., (Peabody). For the reasons stated below, the motion for summary judgment is denied.

I. FACTUAL BACKGROUND

This case arose out of the award of a contract to build a solid waste transfer station (transfer station) for the City of Cleveland (City) in May 1975. The City retained Seminole Management Consultants, Inc., (Seminole) to prepare the specifications for the transfer station and to assist the City in reviewing bids for the project. Seminole’s president, Lawrence Plants (Plants), was principally responsible for this work. F. Buddie Contracting, Inc. (Buddie), the plaintiff in this action, was one of the bidders on the project. Peabody, through one of its local distributors, William Seawright (Seawright), also bid on the project.

A number of companies bid for the transfer station contract. In relevant part, those bids were

Buddie Contracting, Inc. $1,247,700.00
Stephens Paint & Corp. 1,472,000.00.
Peabody-Galion 1,578,766.00

A review of the bids, however, indicates that the bidders found the specifications ambiguous and bid on slightly different projects. The City then turned to its consultant, Seminole, to review the bids and to make a recommendation for the award of the contract. Seminole recommended that the City award the contract to Peabody as the lowest responsible bidder and that the City disqualify Buddie’s bid as defective. Acting on Seminole’s recommendation, the City then awarded the contract to Peabody on June 20, 1975.

On July 9, 1975, Buddie filed a taxpayer’s action in Cuyahoga County Common Pleas Court (Buddie I) alleging a violation of the state laws regulating the award of public contracts. Buddie sought an injunction barring execution of the contract and readvertisement of the bids. Within two weeks, the trial judge heard the case on plaintiff’s application for a preliminary injunction.

On August 6, 1975, the trial judge entered judgment in favor of the defendants in the Buddie I action. In his opinion, the trial judge indicated that he had, apparently on his own motion, consolidated the trial on the merits with the application for preliminary injunction pursuant to Ohio Civil Rule 65(B)(2). In relevant part, the trial judge’s opinion stated that he found no evidence of improper conduct or collusion involving any public official or bidder. He further found that Seminole was justified in suggesting rejection of Buddie’s bid because of defects in the bid. In conclusion, the trial judge, recognizing the limited role of courts in reviewing awards of public contracts, upheld the selection of Peabody as the successful bidder.

Buddie appealed the decision of the Bud-die I court to the Eighth District Court of Appeals. That Court affirmed the trial judge’s decision in an opinion filed on December 2, 1976. Construction of the transfer station proceeded throughout this period and the transfer station is now complete.

Subsequent to the close of the Buddie I action, press revelations and a subsequent prosecution disclosed an unlawful relationship between Seminole and Peabody. Seminole’s president, Plants was discovered to be a close business associate of defendant, Seawright, the president of a Peabody distributor. On December 21, 1978, the Cuyahoga County Grand Jury indicted Sea-wright, Seminole, and Plants on criminal charges arising out of their involvement in the award of the contract for the transfer station. Ultimately, Seawright pled guilty *426 to one count of attempt and complicity to have an unlawful interest in a public contract. Seminole pled guilty to one count of having an unlawful interest in a public contract and Plants pled guilty to attempt to have an unlawful interest in a public contract. The remaining counts of the indictment were dismissed as part of the plea bargain.

Frank John Gerdnic, vice president of marketing for Peabody’s solid waste division, received a grant of immunity in exchange for his testimony in this case. His sworn statement, attached to the brief in opposition to the motion for summary judgment, indicates that Peabody had knowledge of Seawright’s unlawful conduct and took no action to disassociate itself from Seawright.

II. PROCEDURAL HISTORY

After the entry of the guilty pleas, Buddie instituted this federal court action alleging violations of the antitrust laws. In brief, Buddie alleges that the defendants conspired to secure the award of the contract for Peabody, even though Peabody was not the lowest responsible bidder. It claims that this conspiracy violated both § 1 of the Sherman Act, 15 U.S.C. § 1, and Ohio’s Valentine Act, Ohio Rev.Code § 1331.01 et seq.

Peabody now moves for summary judgment arguing that (1) Buddie’s cause of action is barred by the statute of limitations; (2) Buddie lacks standing to sue for damages under the antitrust laws; and (3) Buddie’s allegations fail to state a violation of the antitrust laws. Even if Buddie’s legal theories and factual submission survive these legal challenges, Peabody further contends that collateral estoppel prevents Buddie from establishing facts required to make out its cause of action.

Before turning to these specific challenges, the Court notes the unique standard which applies to the review of summary judgment motions in an antitrust case. Historically, the courts have been extremely reluctant to dispose of antitrust litigation on summary judgment motions. See Poller v. Columbia Broadcasting System, Inc. 368 U.S. 464, 473, 82 S.Ct. 486, 491, 7 L.Ed.2d 458 (1962). While that standard has been somewhat relaxed, see First National Bank of Arizona v. Cities Service Co., 391 U.S. 253, 284-90, 88 S.Ct. 1575, 1590-93, 20 L.Ed.2d 569 (1968), summary judgment is still disfavored, particularly where factual issues remain subject to dispute. See Smith v. Northern Michigan Hospitals, Inc., 703 F.2d 942 (6th Cir.1983). While it is debatable whether this attitude toward summary judgment applies to motions presenting principally legal issues, the Court approaches the motion mindful of the particular hazards associated with granting summary judgment in antitrust litigation.

III. STATUTE OF LIMITATIONS

A four year statute of limitations applies to federal antitrust claims. 1 The contract award which gives rise to this lawsuit was made on June 20, 1975 — over five years followed until the filing of the complaint in this case on December 19, 1980. Absent some tolling provision, therefore, Buddie’s claim will be barred by the statute of limitations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tremont Public Advisors, LLC v. Connecticut Resources Recovery Authority
333 Conn. 672 (Supreme Court of Connecticut, 2019)
State ex rel. Jeffers v. Athens Cty. Commrs.
2016 Ohio 8119 (Ohio Court of Appeals, 2016)
Doron Precision Systems, Inc. v. FAAC, INC.
423 F. Supp. 2d 173 (S.D. New York, 2006)
Amec E & C Services, Inc. v. Nu-West Industries, Inc.
395 F. Supp. 2d 957 (D. Idaho, 2005)
Titan America, LLC v. Riverton Investment Corp.
569 S.E.2d 57 (Supreme Court of Virginia, 2002)
J & J Construction Co. v. Bricklayers & Allied Craftsmen, Local 1
631 N.W.2d 42 (Michigan Court of Appeals, 2001)
Lockheed Information Management Systems Co. v. Maximus, Inc.
524 S.E.2d 420 (Supreme Court of Virginia, 2000)
Stearns Airport Equipment Co. v. FMC Corp.
170 F.3d 518 (Fifth Circuit, 1999)
Colsa Corp. v. Martin Marietta Services, Inc.
133 F.3d 853 (Eleventh Circuit, 1998)
Colsa Corp. v. Martin Marietta
Eleventh Circuit, 1998
Tower Air, Inc. v. Federal Express Corp.
956 F. Supp. 270 (E.D. New York, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
595 F. Supp. 422, 1984 U.S. Dist. LEXIS 24348, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-buddie-contracting-inc-v-seawright-ohnd-1984.