Republic of the Philippines v. Westinghouse Electric Corp.

782 F. Supp. 972, 1992 U.S. Dist. LEXIS 1186, 1992 WL 17826
CourtDistrict Court, D. New Jersey
DecidedFebruary 4, 1992
DocketCiv. 88-5150
StatusPublished
Cited by4 cases

This text of 782 F. Supp. 972 (Republic of the Philippines v. Westinghouse Electric Corp.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Republic of the Philippines v. Westinghouse Electric Corp., 782 F. Supp. 972, 1992 U.S. Dist. LEXIS 1186, 1992 WL 17826 (D.N.J. 1992).

Opinion

OPINION

DEBEVOISE, District Judge.

The Republic of the Philippines (the “Republic”) and the National Power Corporation (“NPC”) instituted this action against Westinghouse Electric Corporation and Westinghouse International Projects Com *974 pany (collectively, “Westinghouse”) and Burns & Roe Enterprises, Inc. (“Burns & Roe”), asserting multiple tort and contract claims. The case arises out of the construction of the 600-megawatt Philippine Nuclear Power Plant (“PNPP”) in Bagac, Bataan during a ten year period commencing in 1976.

I concluded that with the exception of Count 3 and part of Count 8 all counts against Westinghouse should be stayed and referred to arbitration, that Count 2 against Burns & Roe should be stayed and referred to arbitration and that with the exception of Count 3 and part of Count 8 all the remaining counts against Burns & Roe should be stayed pending the completion of arbitration. Count 3, which alleges that Westinghouse and Burns & Roe breached their fiduciary duties to the Philippine people by bribing former Philippine President Ferdinand Marcos in connection with the PNPP contracts, and the portion of Count 8 which alleged a conspiracy to bribe President Marcos, were permitted to proceed in this Court. See Republic of the Philippines v. Westinghouse, et al., 714 F.Supp. 1362 (D.N.J.1989) (the “Stay Opinion”).

Those two proceedings went forward in parallel. . In this Court the Count 3 and Count 8 conspiracy claims were litigated through discovery and many motions to the point of trial. In Geneva, three arbitrators pursued their task.

On December 19, 1991, the Arbitrational Tribunal (the “Tribunal”) rendered a “Preliminary Award on Issues of Jurisdiction and Contract Validity” (the “Arbitration Award” or the “Award”). See Clary Affidavit at Exhibit A. The Award addresses the questions of arbitral jurisdiction and the validity of the prime contract between Westinghouse and the NPC for construction of the PNPP and the consulting contract between Burns & Roe and the NPC for engineering and consulting services. It concluded that the contracts (and the arbitration clauses in them) are valid and that they confer arbitral jurisdiction over the NPC. See infra “The Award.”

Based on the Award, and more particularly on the Tribunal’s findings on the existence of bribery by Westinghouse and Burns & Roe, the defendants have moved for summary judgment, on the theory of collateral estoppel, with respect to Counts 3 (tortious interference with fiduciary duty) and 8 (conspiracy to interfere with fiduciary duty) of this lawsuit. A trial is tentatively scheduled to begin during the third week of February, 1992.

A preliminary comment is in order with respect to what is not the subject matter of the defendants’ summary judgment motions. Westinghouse has argued that the issue presented is whether a court may give collateral estoppel effect to an arbitration proceeding. See Transcript of Hearing, January 24, 1992, at 4, 19 (“Transcript”). 1 All parties have cited my prior decision in Glictronix Corp. v. American Tel. & Tel. Co., 603 F.Supp. 552 (D.N.J.1984) in support of their various contentions. 2 Because nothing in Glictronix *975 would preclude the application of collateral estoppel to an arbitration proceeding, I believe Westinghouse has mischaracterized the issue before the Court. See Transcript at 4 (collateral estoppel effect of an arbitration proceeding). Rather, the issue presented is whether, under the circumstances, the Tribunal’s decision should bind the Republic on a collateral estoppel theory. See Transcript at 13-14.

I am ruling that the Republic is not bound, and, therefore, am denying the defendants’ motions. I do so for three reasons: (i) there is insufficient identity between the issues decided by the Tribunal and Counts 3 and 8; (ii) the Tribunal applied a more onerous standard of proof than a jury to the extent the contract validity and arbitral jurisdiction bribery issue and Counts 3 and 8 bribery issue overlap; and, (iii) the Republic is in any event not bound by the Tribunal’s ruling because it is not a party to the arbitration. I am rejecting the Republic’s contentions that collateral estoppel is barred by the discovery of new evidence subsequent to the Third Circuit’s ruling of December 19, 1991, 951 F.2d 1414, in the form of the documentation provided to the Department of Justice or by the failure of the Tribunal to consider certain evidence of record. See Westinghouse v. Republic of the Philippines, 951 F.2d 1414 (3d Cir.1991). I also find it unnecessary to consider the other elements of collateral estoppel. See Temple University v. White, 941 F.2d 201, 212 (3d Cir.1991) cert. denied — U.S. -, 112 S.Ct. 873, 116 L.Ed.2d 778 (1992) (setting forth the elements of collateral estoppel); Lane v. Sullivan, 900 F.2d 1247, 1250 (8th Cir.) cert. denied — U.S. -, 111 S.Ct. 134, 112 L.Ed.2d 101 (1990).

THE AWARD

I will first review the relevant portions of the Arbitration Award. The Tribunal set forth, and answered in the negative, the six issues covered by the Award as follows: i) was the arbitration clause relied upon by Burns & Roe obtained in such a manner as to render it invalid; ii) if (i) is answered in the negative, is the Republic bound by the said arbitration clause; iii) was the arbitration clause relied upon by Westinghouse obtained in such a manner as to render it invalid; iv) if (iii) is answered in the negative, is the Republic bound by such arbitration clause; v) was the engineering and consulting services contract between NPC and Bums & Roe dated April 23, 1974 obtained in such a manner as to render it invalid, and; vi) was the contract dated February 9, 1976 between NPC and Westinghouse Electric S.A. for Philippine Nuclear Power Plant (“PNPP”) Unit 1 obtained in such a manner as to render it invalid. Award at 5.

The Award reviewed the basic facts giving rise to the disputes between the parties. They are essentially the same facts set forth in my Opinion of September 20, 1991, and various of my other opinions, which I incorporate by reference. See generally Republic of the Philippines v. Westinghouse, 139 F.R.D. 50 (D.N.J.1991) (the “Damages Opinion”); Republic of the Philippines v. Westinghouse, 774 F.Supp. 1438 (D.N.J.1991) (the “Summary Judgment Opinion”); the Stay Opinion, 714 F.Supp. at 1362. The Award then addressed several preliminary issues and determined the applicable law. Award at 16-30.

1. Standard of Proof

The Tribunal discussed the various formulations of the “preponderance of the evidence” and “clear and convincing evidence” standards and concluded that the standard to be applied in weighing the evidence was the “preponderance of the evidence standard” as generally understood in the Philippines, New Jersey and Pennsylvania. Award at 30-34.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gannon v. American Home Products
999 A.2d 522 (New Jersey Superior Court App Division, 2010)
Gruntal & Co., Inc. v. Steinberg
854 F. Supp. 324 (D. New Jersey, 1994)
Westinghouse Elec. Corp. by Levit v. Franklin
789 F. Supp. 1313 (D. New Jersey, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
782 F. Supp. 972, 1992 U.S. Dist. LEXIS 1186, 1992 WL 17826, Counsel Stack Legal Research, https://law.counselstack.com/opinion/republic-of-the-philippines-v-westinghouse-electric-corp-njd-1992.