Colsa Corp. v. Martin Marietta Services, Inc.

133 F.3d 853, 1998 U.S. App. LEXIS 939, 1998 WL 23140
CourtCourt of Appeals for the Eleventh Circuit
DecidedJanuary 23, 1998
Docket97-6206
StatusPublished
Cited by3 cases

This text of 133 F.3d 853 (Colsa Corp. v. Martin Marietta Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colsa Corp. v. Martin Marietta Services, Inc., 133 F.3d 853, 1998 U.S. App. LEXIS 939, 1998 WL 23140 (11th Cir. 1998).

Opinion

PER CURIAM:

Plaintiff Colsa Corporation (“Colsa”) appeals the district court’s grant of summary judgment for Martin Marietta (“Martin Marietta”) on Colsa’s antitrust claims. We AFFIRM.

/. BACKGROUND

At issue in this case is a government contract to provide “operation and maintenance” services to the United States Navy in support of the Atlantic Fleet Weapons Training Facility located in Roosevelt Roads, Puerto Rico [hereinafter the Contract]. For many years, Martin Marietta, or one of its predecessors in interest, 1 had been awarded the Contract. In March 1990, Martin Marietta and Colsa entered a “Teaming Agreement,” which provided that Colsa would assist Martin Marietta to obtain the Contract and support Martin Marietta by providing software services under the Contract. This support was contingent, however, on Martin Marietta being awarded the Contract.

On April 15, 1991, Martin Marietta was awarded the Contract for a base period of six months, with four one-year options exercisable by the government. On May 15, 1991, Martin Marietta entered into a fixed price subcontract with Colsa whereby Colsa agreed to provide a limited number of personnel to support Martin Marietta in performing the Contract.

The government exercised subsequent options on the first of October 1991, 1992, and 1993. On each occasion, Martin Marietta entered into a subcontract with Colsa; Colsa served as the subcontractor for Martin Marietta until June 1994. The Contract was scheduled to be re-solicited and awarded in 1995.

In February 1994, Colsa entered into a teaming agreement with Raytheon, a competitor of Martin Marietta, concerning the next procurement of the Contract. Martin Marietta learned about Colsa’s new agreement with a competitor and began to consider *855 Colsa to be a competitive threat. In May-1994, Martin Marietta provided Colsa with notice that it was terminating the subcontract with Colsa, effective June 12, 1994 (pri- or to the end of the third option period). 2 That the termination of the subcontract was not related to performance problems by Col-sa is undisputed. Martin Marietta did not enter into a subcontract for the fourth option period (beginning in October 1994). The government announced the rebidding of the Contract in October 1994. In October 1996, the new Contract was awarded to ITT.

On June 7, 1994, Colsa filed this action against Martin Marietta for violations of Section 2 of the Sherman Act due to anti-competitive conduct in the termination of the subcontract. Colsa specifically contends that Martin Marietta sought to create or to maintain a monopoly through illegal competitive conduct. The district court granted summary judgment in favor of Martin Marietta on the antitrust claim because Colsa failed to show that Martin Marietta had market power in the relevant market, a prerequisite to a monopolization claim. 3 Colsa appeals.

II. DISCUSSION 4

The issue on appeal is whether the district court erred by granting summary judgment for Martin Marietta after concluding that Colsa failed to define properly the relevant market. Summary judgment orders are reviewed de novo. Scala v. City of Winter Park, 116 F.3d 1396, 1398 (11th Cir.1997). Summary judgment is appropriate if, after viewing all the evidence in favor of the non-moving party, there is no genuine issue on any material fact. Fed.R.Civ.P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986); Adickes v. S.H. Kress & Co., 398 U.S. 144, 157, 90 S.Ct. 1598, 1608, 26 L.Ed.2d 142 (1970).

The district court determined that Colsa improperly defined the relevant market and granted summary judgment for Martin Marietta based on that conclusion. While we agree that summary judgment was appropriate, we do so on a different basis. 5 As stated, Colsa’s argument does not show how Martin Marietta’s conduct was anticompeti-tive so as to support an antitrust claim.

The Contract at issue in this case has two aspects: (1) service of the Contract and (2) *856 procurement of the Contract. Colsa expressly states that the alleged antitrust violation is Martin Marietta’s “termination of [Colsa’s] subcontract in June 1994.” Colsa asserts that this was predatory conduct intended to “eliminate Colsa] as a competitor in violation of Section 2 of the Sherman Act.” In addition, Colsa contends that the only relevant time is the one that covers the termination of the subcontract and specifically rejects the district court’s analysis of the case from the standpoint of the Contract procurement. 6

In other words, Colsa appears only to argue that Martin Marietta, by terminating Colsa’s subcontract for services, engaged in anticompétitive conduct during the service of the Contract. 7 We fail to see how this conduct can be characterized as anticompetitive. Colsa cannot claim that Martin Marietta monopolized — or attempted to monopolize — its own contract by terminating a subcontract. All contracts involve, in some sense, a monopoly over the performance of the contract, which is necessarily controlled by the parties to the contract. It is not anticompetitive for Martin Marietta (a party to the Contract) to exclude Colsa (a non-party to the Contract) from performing services under the Contract. Any rights that Colsa may have against Martin Marietta sound in contract instead of antitrust law. 8

For these reasons, we find that the district court did not err by granting summary judgment for Martin Marietta. Colsa has failed to allege anticompetitive conduct upon which an antitrust claim could be predicated.

AFFIRMED.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
133 F.3d 853, 1998 U.S. App. LEXIS 939, 1998 WL 23140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colsa-corp-v-martin-marietta-services-inc-ca11-1998.