Evans Construction Co. v. State

44 Ill. Ct. Cl. 112
CourtCourt of Claims of Illinois
DecidedAugust 12, 1991
DocketNo. 86-CC-0017
StatusPublished

This text of 44 Ill. Ct. Cl. 112 (Evans Construction Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Evans Construction Co. v. State, 44 Ill. Ct. Cl. 112 (Ill. Super. Ct. 1991).

Opinion

ORDER

Montana, C.J.

I.

INTRODUCTION

Claimant, Evans Construction Company, brought this action on behalf of its subcontractor and itself seeking compensation for work performed in connection with the rehabilitation of an underground State parking lot. The record is quite extensive and the Court commends the parties for efforts in presenting this complex case in such a clear and concise manner.

A.

GENERAL BACKGROUND

On April 12, 1983, Evans Construction Company (“Evans”) and the Capital Development Board for the State of Illinois (“CDB”) entered into a unit price contract for the rehabilitation of a two-level underground Old State Capitol Parking Garage at Springfield, Illinois. The user of the facility is the Illinois State Historical Society. This ■ project officially started in September 1980 when Hanson Engineers, Inc. (“Hanson”), of Springfield was selected as the architectural/ engineering firm. Hanson was involved in the original design of this structure and had performed additional rehabilitation work at the Old State Capitol and the garage in prior years. Funds were released in December of 1981 and bid documents were frozen at the 100% stage in March 1982. Almost one year later (January 1983) construction funds were released and bid documents issued. Bids were received on April 6, 1983; Evans was the lowest of five bidders with a bid of $704,000.00.

B.

THE COMPLAINT — 10 COUNTS COUNT I (RETAINAGE)

Count I deals with the sum of money yet retained by CDB, $75,941.60, and admitted to be owed to Evans (paragraph 66 of additional stipulation of fact). This sum also compensates Claimant for the sums requested under Count II.

COUNT II

(ACCOUNT STATED)

Count II is an action on an account stated theory, based on a CDB form commonly referred to as a RFP, Request for Proposal. This form is Exhibit B affixed to the complaint and referenced in Count II. In part it states:

“2. REQUEST for change by : CDB
CDB contemplates making certain changes, additions and deletions to the work to be performed under the subject Contract. Unless otherwise indicated in the description of the change, accompanying drawings and specifications all work required shall conform to the contract documents. The Contractor is requested to submit within 14 calendar days from the date herein a proposal and a detailed breakdown for this change. The proposal shall be submitted in accordance with CDB’s format and the general conditions.
3. REASON for change:
Adjustment to contract based on measured quantities.
4. DESCRIPTION of change including reference to drawings and specifications revised, new drawings and specifications issued.
(See Attached Sheet)”

The attached sheet referenced above was a May 8, 1984, summary of quantities which listed 10 items. It would appear that this RFP was a final attempt by the parties to resolve their differences short of this litigation. The summary of quantities is worth noting because it serves as a summary of all matters involved in this suit. It is set out as follows: [See page 116 following.]

Count II was in effect an acceptance by Claimant of CDB’s prices and quantities as to items 3,4,6,7,9 and 10 for a net award to Claimant of $1,147.00 after permitting certain other adjustments agreed to by Claimant (paragraph 5 of Count II of the complaint).

The parties’ inability to come to terms on items 1 and 2, “partial and full depth patching, level L-l,” of the two-level underground garage is the sound versus unsound concrete question comprising Counts VI and X of the complaint, and spoken to below.

COUNT III

(EPOXY CRACK INJECTION)

Item 5 of the RFP and the summary of quantities illustrates the parties’ agreement on the quantity of coverage on the epoxy crack injection, 6,791 lineal feet, column second from the right entitled “Net Change Order Quantities.” Claimant, however, refused to abide CDB’s suggested unit price of $14.65, which would have resulted in additional compensation to Claimant of $99,488.00, still approximately $50,000.00 shy of what Evans had locked itself into with its subcontractor, Mid-

[[Image here]]

Continental, at $22.00 a lineal foot, or $149,402.00, spoken to in more detail below.

Count III is a dispute as to a unit price. The evidence came in by way of a videotaped evidence deposition of Jim Halsey, principal for Mid-Continental, taken on April 9, 1986, and a 64-paragraph joint stipulation of fact filed on August 14, 1986, specifically addressed in paragraphs 1 through 28.

In part, the contract provides “unit prices and material substitutions have been accepted and are incorporated in this contract.” The unit prices were incorporated by an attached page. The attached page had unit prices for eight different items of work.

Under the general requirements of the contract, Evans had to “provide unit prices for specified work items” (section 1.01 B). Under subsection C of section 1.01, unit price was defined to mean a “fixed price, including all overhead profit and all other costs of whatever nature and character, for a specified unit of work.” CDB had the right nonetheless to “reject or negotiate any unit prices which it considers excessive or unreasonable.” In fact, Evans’ $704,000.00 bid listed unit prices for eight different aspects of the job. Six of the eight unit prices were accepted by CDB, and became part of the final contract. Two of the eight unit prices Evans submitted were rejected by CDB under its right to “reject or negotiate any unit price which it considers excessive or unreasonable.” The unit prices that were rejected were the ones submitted for epoxy coated crack injection, the subject matter of Count III, and epoxy coated welded wire fabric, the subject matter of Count IV. The matter came before this tribunal to determine among other matters the appropriate price for the epoxy coated crack injection actually performed in excess of the 1,750 feet estimated under the contract, referred to in Count III as “epoxy coated crack injection.”

A setting forth of some of the stipulated paragraphs in this regard is helpful. They are as follows:

“3. Under Division 3 of the Project Manual, Concrete, Section 03730, entitled ‘Concrete Rehabilitation’, Section 3.01.D. appearing at page 03730-11, the following work was to have been performed:
Vertical, through slab cracks in the repair areas shall be repaired by full depth epoxy injection (Pressure (sic) Injected Crack Sealant).
4. The project manual, Division 1-General Requirements, Section 01151, dealing with unit prices, Section 1.01.C. Provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Divane Bros. Electric Co. v. State
22 Ill. Ct. Cl. 546 (Court of Claims of Illinois, 1957)
Chism, Inc. v. State
26 Ill. Ct. Cl. 181 (Court of Claims of Illinois, 1967)
Mass Construction Co. v. State
26 Ill. Ct. Cl. 412 (Court of Claims of Illinois, 1969)
Grogan v. State
32 Ill. Ct. Cl. 46 (Court of Claims of Illinois, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
44 Ill. Ct. Cl. 112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/evans-construction-co-v-state-ilclaimsct-1991.