Divane Bros. Electric Co. v. State

22 Ill. Ct. Cl. 546, 1957 Ill. Ct. Cl. LEXIS 28
CourtCourt of Claims of Illinois
DecidedMay 14, 1957
DocketNo. 4625
StatusPublished
Cited by1 cases

This text of 22 Ill. Ct. Cl. 546 (Divane Bros. Electric Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Divane Bros. Electric Co. v. State, 22 Ill. Ct. Cl. 546, 1957 Ill. Ct. Cl. LEXIS 28 (Ill. Super. Ct. 1957).

Opinion

Tolson, C. J.

Divane Bros. Electric Company, A Corporation, filed its complaint on May 20, 1954, in which it seeks payment for certain work performed at the Illinois State Penitentiary, Pontiac, Illinois.

The record consists of the following:

1. Complaint.
2. Departmental Report.
3. Motion to strike and dismiss claimant’s complaint in part.
4. Order dismissing motion, to strike, but without prejudice to raise such objections at the hearing of said cause.
5. Transcript of evidence.
6. Exhibits.
7. Stipulation waiving briefs and arguments.
8. Commissioner’s Report.

The facts of the case are as follows:

On February 21, 1950, claimant entered into a contract with the State of Illinois for certain electrical work at the Pontiac Penitentiary under contract No. 66282, and, thereafter, on March 27, 1950, entered into a separate contract for other electrical work at the Pontiac Penitentiary under contract No. 66308.

The complaint is in Two Counts. Count One refers to contract No. 66282, wherein claimant alleges a balance due it in the amount of $22,334.98. Respondent’s motion to strike in part alleges that the sum of $15,699.22 is not a proper claim, and the amount asked should be reduced accordingly.

Under Count Two of the complaint, claimant alleges that there is a balance in the amount of $6,908.39 due under contract No. 66308, and respondent’s motion to strike alleges that the sum of $6,261.20 should be stricken from this claim.

The matter was referred to Commissioner Herbert G-. Immenhausen, who filed a detailed report in said cause.

At the meeting of the Court of Claims in April, the Commissioner and the Assistant Attorney General for the State of Illinois, who tried the case, advised the Court that claimant had proven its case by a preponderance of the evidence, and that the objections of respondent, heretofore filed, were not well taken, and would not be urged, as provided for in the order dismissing the motion to strike the complaint in part. It is to be further noted that respondent did not offer any testimony at the hearing, but merely submitted a Departmental Report.

The Commissioner’s report carefully analyzed all exhibits and testimony offered in evidence, and the Commissioner’s report in the following words and figures is, therefore, adopted by the Court. It reads as follows:

“Commissioner’s Report
Divane Bros. Electric Company, A Corporation, by Fleck and Pollack, its attorneys, filed a complaint with the Court of Claims on May 26, 1954.
Claimant alleges that on or about February 21, 1950, it entered into a written contract with the State of Illinois, acting by and through the Department of Public Works and Buildings, for electrical wiring of the new power plant at the Illinois State Penitentiary, Pontiac Branch, Pontiac, Illinois, contract No. 66282. Copy attached to the complaint.
Subsequent to the awarding of the contract, and after that work was commenced, additional and extra work was ordered by and through the Department of Public Works and Buildings, which work was not included in the original contract, and, which it was agreed between the parties should be paid for in addition to matters set forth in the original contract.
On September 30, 1952, claimant forwarded to respondent, through the Department of Public Works and Buildings, 24 proposals for acceptance, which itemized the extra work, and totalled $10,831.98.
On December 15, 1952, respondent recommended that claimant be paid for, in addition to the amounts in the contract, the following work under proposals, 1, 3, 4, 5, 6, 10, 12, 13, 15, 14, 20, 16, 21, 23 and 24, a total amount of $8,380.45; and respondent did on December 15, 1952 request of M. F. Seyfrit, Director of the Department of Public Safety, a requisition to cover the said amount and authority to accept the proposals as an addition to contract No. 66282.
The contract was figured, and the amount to be charged thereunder was computed upon the anticipation that the time for the completion of the contract and work done thereunder would be 180 days, which was the time specified by the General Contractor for completion of the entire building, but that, due to delays and circumstances entirely out of *he control of claimant, the work on the wiring project could not be started for a period of 90 days after the awarding of the contract. Respondent ordered the electrical switchboard directly from the manufacturer, and the delivery of said switchboard, upon which much of the work of claimant depended, was delayed, because of changes made in the layout by respondent as late as May 25, 1951, or a period of 15 months after the work on this project was started by claimant. Although the switchboard had been scheduled for delivery on October 1, 1951, it was not actually delivered until March 25, 1952.
Because of the delays, as set forth above, claimant was subjected to extensive labor and material increases, lost time, and necessarily was subjected to much supervision and overhead expense for the extended period. Claimant did on May 22, 1952, before the completion of its work under contract No. 66282, notify respondent of the following additional costs to claimant as a result of the delays:
Labor increases and insurance_________________________________$ 4,092.00
Material increases ______________________________________________________ 1,265.00
Lost time — 832 hours__________________________________________ 2,496.00
Supervision — 12 months____________________________________________ 1,200.00
Gen’l. Supt’s. time — 25 trips____________________________________ 1,250.00
Overhead expense for extended period________________ 1,200.00
$11,503.00
Claimant discussed the matter of payment of its claim with respondent, through the Division of Architecture and Engineering, on March 17, 1953, and at various other times, but no definite action was ever taken regarding the same.
The following is an accurate account of the amount due to claimant, and moneys paid by respondent, and the balance remaining unpaid on account of work done in connection with the State of Illinois Penitentiary, Pontiac Branch, Pontiac, Illinois, power house electrical wiring:
As per contract No. 66282 made and entered into on February 21, 1950 _________________________________________________________________________$ 41,830.00

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evans Construction Co. v. State
44 Ill. Ct. Cl. 112 (Court of Claims of Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
22 Ill. Ct. Cl. 546, 1957 Ill. Ct. Cl. LEXIS 28, Counsel Stack Legal Research, https://law.counselstack.com/opinion/divane-bros-electric-co-v-state-ilclaimsct-1957.