Mass Construction Co. v. State

26 Ill. Ct. Cl. 412, 1969 Ill. Ct. Cl. LEXIS 20
CourtCourt of Claims of Illinois
DecidedApril 17, 1969
DocketNo. 5254
StatusPublished
Cited by1 cases

This text of 26 Ill. Ct. Cl. 412 (Mass Construction Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mass Construction Co. v. State, 26 Ill. Ct. Cl. 412, 1969 Ill. Ct. Cl. LEXIS 20 (Ill. Super. Ct. 1969).

Opinion

Perlin, C.J.

Claimant, a Delaware Corporation, seeks to recover the sum of $69,454.00 alleged to be due and unpaid under a contract for the erection of two parallel seven-span bridges on Interstate Route No. 57 over the Little Wabash River in Effingham County, Illinois. The amount requested is for the construction of eight cofferdams (watertight enclosures from which water is pumped to expose the bottom of a river, and permit work to be done there) at the contract unit price of $8,000.00 each, and for 1,732 cubic yards of cofferdam excavation at the contract unit price of $7.00 per cubic yard.

The project involved the erection of twelve concrete piers to be erected as part of the substructure for the two bridges to support their superstructures. The piers, having the same general structural detail, were designated as follows:

Pier No. 1-East Pier No. 3-East Pier No. 6-East

Pier No. 1-West Pier No. 3-West Pier No. 6-West

Pier No. 2-East Pier No. 4-East Pier No. 5-West

Pier No. 2-West Pier No. 4-West Pier No. 5-East

The contract between claimant and respondent was executed on July 1,1963. Claimant was required to begin work ten days after execution and approval of the contract, and to complete performance prior to August 1, 1964, subject to certain provisions for extensions of time. Claimant’s bid was accepted in the amount of $486,454.80.

The evidence shows that at the time the contract was executed claimant and respondent anticipated that cofferdams would be required to be driven in connection with piers No. 3 and 4, which was stated specifically in the contract. Claimant’s witness, Walter C. Glaze, an engineer who prepared the bids for claimant, testified that the parties anticipated the possibility that cofferdams would also be required to be driven in connection with the construction of piers Nos. 1, 2, 5, and 6 (both East and West).

The language of the contract pertaining to the cofferdams and cofferdam excavation is as follows:

“Cofferdams: It is anticipated that cofferdams will be required for the construction of piers Nos. 3 and 4 of the bridges. Bid items for these cofferdams are included in the total bill of materials on the plans. . . .
“The contract unit price each for cofferdams at the piers designated will be payment in full for furnishing all materials and the construction of the cofferdams, its maintenance during construction of the pier, and subsequent removal; . . .
“Cofferdam Excavation: This work shall consist of all foundation excavation for the piers without classification except rock, within the limits of the cofferdams, and the disposal of all excess material obtained from such excavation as elsewhere specified. . . .
“This work will be paid for at the contract unit price per cubic yard for cofferdam excavation.”

The undisputed evidence further shows that construction was begun by claimant during the first week in July, 1963. Excavation for piers Nos. 3, 4 and 6 was commenced. Claimed encountered a “fine, runny, silty sand” at pier No. 6, and tried to carry out the excavation operation by using a crane with digging buckets, but, as fast as it dug, the soil would come in from the sides and both ends of the hole. A point was reached where the approach embankment constructed by another contractor was endangered. Claimant found it impossible to proceed without the construction of cofferdams.

On July 19, 1963, claimant wrote to the District Engineer for respondent as follows:

“In the contract covering the above Section, piers Nos. 3 and 4 of both structures call for cofferdams as payment items. After excavating at pier No. 6, we find that unstable subsoil conditions similar to that of piers Nos. 3 and 4 prevail; that is a running silt condition. At pier No. 5 we presently have an excavation approximately 40 feet wide at the top, and are still unable to get down to the footing elevation. The sides are filling in so badly that it is impossible to proceed on construction without cofferdams. Rather than delay construction and further disturb adjacent subsoil, we are preparing to drive a cofferdam at this location — pier No. 6.
“We are of the opinion the same condition will also prevail at several of the other piers.
“We invite your inspection of the aforementioned conditions, and, if you have any feasible solutions other than using cofferdams, we will cooperate in trying other suggested methods.
“Please let us know your findings as soon as possible.”

By letter dated July 22, 1963, the District Engineer, I. 0. Bliss, through his agent, Robert M. Gamble, replied:

“Replying to paragraph three of your letter, dated July 19, 1963, this is to inform you that an inspection has been made of the excavation for pier No. 6, and it appears that your only solution is to use sheeting or cofferdam. (Emphasis supplied)
“The plans and special provisions require payment for a cofferdam for piers Nos. 3 and 4 of both bridges. No cofferdam is required on the remaining piers, and no payment can be made if you decide to use cofferdams on these piers. The borings on the plans show that even though piers Nos. 1, 2, 5, and 6 are approximately 13 feet higher than piers Nos. 3 and 4, the excavation is well in waterbearing sandy loam, which would indicate that sheeting of some type would be required. tf

Mr. Herman Mass, president of Mass Construction Company, testified that upon receiving the letter he decided to proceed under protest. He further testified that he did not agree with the conclusion of the District Engineer that no payment would he made for cofferdams at piers Nos. 1, 2, 5 and 6, although they were necessary, because the plans and proposal state that they only estimate the amount of cofferdams, which may he required. Mr. Mass stated that he protested the conclusion, but decided to proceed because of the time limit and penalty clause for noncompletion.

Mr. Gamble, the only witness presented for respondent, testified that it would have been impractical to have constructed the bridge without the cofferdams, although he further stated that he did not make any recommendations to the State that they re-negotiate for new cofferdams on the balance of the piers.

A letter from claimant to Mr. Virden E. Staff, Chief Highway Engineer, Department of Public Works and Buildings, which was admitted into evidence without objection, summarizes claimant’s position in the instant proceedings, and states in part:

II
“In its Proposal to the Department, which was incorporated into the Contract, the Contractor was required to give the following assurances to the Department:
6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evans Construction Co. v. State
44 Ill. Ct. Cl. 112 (Court of Claims of Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
26 Ill. Ct. Cl. 412, 1969 Ill. Ct. Cl. LEXIS 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mass-construction-co-v-state-ilclaimsct-1969.