Erdman Co. v. Phoenix Land & Acquisition, LLC

650 F.3d 1115, 2011 U.S. App. LEXIS 16875, 2011 WL 3568929
CourtCourt of Appeals for the Eighth Circuit
DecidedAugust 16, 2011
Docket10-2854
StatusPublished
Cited by29 cases

This text of 650 F.3d 1115 (Erdman Co. v. Phoenix Land & Acquisition, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Erdman Co. v. Phoenix Land & Acquisition, LLC, 650 F.3d 1115, 2011 U.S. App. LEXIS 16875, 2011 WL 3568929 (8th Cir. 2011).

Opinion

LOKEN, Circuit Judge.

Erdman Company (“Erdman”) and Erdman Architecture & Engineering Company (“EAEC”) filed this diversity action to foreclose a contractor’s lien and an architect’s and engineer’s lien against Phoenix Land & Acquisition, LLC (“Phoenix Land”), and Phoenix Health, LLC (“Phoenix Health”), as owners of the property, and three financial institutions with recorded security interests in the property. Phoenix Land filed a counterclaim, asserting breach of contract, negligence, breach of implied warranty, breach of fiduciary relationship, and deceptive trade practices by Erdman, and negligence by EAEC. Erdman and EAEC now appeal the district court’s 1 order denying their motion to compel arbitration of Phoenix Land’s counterclaim. We have jurisdiction over an appeal from an interlocutory order “denying an application ... to compel arbitration.” 9 U.S.C. § 16(a)(1)(C). The district court held that Erdman waived the right to arbitrate by evidencing its intent to resolve the entire dispute through litigation. Reviewing the waiver determination de novo but the district court’s underlying factual findings for clear error, we affirm. See Lewallen v. Green Tree Servicing, L.L.C., 487 F.3d 1085, 1090 (8th Cir.2007) (standard of review).

I.

Erdman, a Wisconsin-based contractor specializing in health care facilities, entered into a Design-Build Contract with Phoenix Land as Owner to design and build a one-story addition to a surgical center in Fort Smith, Arkansas. Section 12.2 of the Contract provided that “[a]ny controversy or claim arising out of or relating to this Contract or its breach not resolved by mediation, except for claims relating to Design-Builder’s lien rights ... shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then in effect.” The Contract identified EAEC as a wholly- *1117 owned subsidiary of Erdman that would perform Erdmaris obligations to provide Design Services for the project. The Contract was signed by Erdman’s Executive Vice President on behalf of both Erdman and EAEC. Phoenix Health has an unexplained ownership interest in the project site but was not named or referred to in the Contract.

After work on the project began, Phoenix Land signed a series of change orders that altered the plans by adding a second floor “dead shell space” for future expansion and by allowing for the addition of a third floor at a later date. Excavation for the elevator included in the new plans went below the area covered by a geotechnical report prepared for the project and penetrated an abandoned mineshaft. A sinkhole developed, damaging completed work and delaying the project. Erdman demanded time and extra monies to remediate this allegedly unforeseen condition. Phoenix Land investigated, concluded Erdman was responsible for the sinkhole, and refused to make progress payments when Erdman would not complete the project without additional funding. Erdman halted construction with the project not completed.

Erdman and EAEC then filed this action to foreclose their respective liens for amounts unpaid under the Contract. The Complaint also alleged a breach of contract claim against Phoenix Land, and unjust enrichment claims against Phoenix Land and Phoenix Health. Their answer denied the lien claims, asserting numerous affirmative defenses, and pleaded Phoenix Land’s counterclaim. After obtaining a three-week extension, Erdman and EAEC filed their reply to the counterclaim, and Erdman moved to dismiss Phoenix Land’s fraudulent misrepresentation claim or, in the alternative, for a more definite statement of that claim. On the same day, Erdman and EAEC moved to compel arbitration of the counterclaim and to stay adjudication of the counterclaim but permit adjudication of the lien claims pending the arbitration. Though they argued that there was nothing to arbitrate until Phoenix Land asserted its counterclaim, footnote 9 to their lengthy Motion to Compel acknowledged that their initial claims for breach of contract and unjust enrichment “are also covered by the agreement to arbitrate and ... should also be referred to mediation and arbitration.” 2 Two weeks later, Erdman and EAEC also filed a third party complaint against the geotechnical consultant and two Erdman subcontractors.

II.

Federal policy favors arbitration as a form of dispute resolution, as reflected in the Federal Arbitration Act. 9 U.S.C. § 1 et seq. But a party may waive its contractual right to arbitrate. See Lewallen, 487 F.3d at 1090. Although the issue of waiver arises under a variety of arbitration agreements and in a variety of procedural settings, we apply a uniform three-factor test in determining whether a party has waived its right to arbitration, finding waiver when the party seeking arbitration “(1) knew of its existing right to arbitration; (2) acted inconsistently with that right; and (3) prejudiced the other party by its inconsistent actions.” Hooper v. Advance Am., Cash Advance Ctrs. of Mo., Inc., 589 F.3d 917, 920 (8th Cir.2009) (quotation omitted).

*1118 1. The first factor, whether Erdman and EAEC knew of the right to arbitrate, is obvious from the fact that Erdman, a sophisticated party with over fifty years of health care facility design and construction, drafted the Contract containing detailed mediation and arbitration provisions, and is presumed to know its contents. See Pinken v. Frank, 704 F.2d 1019, 1025 (8th Cir.1983). Erdman and EAEC argue they lacked the relevant knowledge because all the claims in their initial complaint, including the breach of contract and unjust enrichment claims, “are covered by the carve-out language in the Contract’s dispute resolution provision.” This contention is frivolous because it is squarely contrary to footnote 9 in their Motion to Compel to the district court. As in Hooper, 589 F.3d at 921, we decline to disturb the district court’s finding of knowledge.

2. The second factor, whether Erdman acted inconsistently with its right to arbitrate, is likewise clear on this record. “A party acts inconsistently with its right to arbitrate if the party substantially invokes the litigation machinery before asserting its arbitration right.” Lewallen, 487 F.3d at 1090 (quotation omitted). The district court found that Erdman “initially decided to forego arbitration in attempting to collect from Phoenix Land and Phoenix Health.” Thus, unlike many waiver cases, where a defendant responded to the plaintiffs lawsuit and, at some point, asserted its right to arbitrate, Erdman and EAEC initiated the lawsuit, joining arbitrable contract and unjust enrichment claims against Phoenix Land for the alleged $2,559,948 unpaid contract balance without simultaneously seeking to arbitrate this contract dispute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doyle v. UBS Fin. Servs., Inc.
Second Circuit, 2025
Powell v. UHG I LLC
S.D. California, 2024
Connie Lange v. GMT Auto Sales, Inc.
Missouri Court of Appeals, 2024
Reynolds v. Bacon CA2/1
California Court of Appeal, 2023
Morgan v. Sundance, Inc.
596 U.S. 411 (Supreme Court, 2022)
Zhang v. Diaz
W.D. Missouri, 2021
Robyn Morgan v. Sundance, Inc.
992 F.3d 711 (Eighth Circuit, 2021)
Millennium Anesthesiology Consultants, LLC v. Walsh
562 S.W.3d 373 (Missouri Court of Appeals, 2018)
Paul Gunderson v. BNSF Railway Company
850 F.3d 962 (Eighth Circuit, 2017)
Craig Schultz v. Verizon Wireless Services, LLC
833 F.3d 975 (Eighth Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
650 F.3d 1115, 2011 U.S. App. LEXIS 16875, 2011 WL 3568929, Counsel Stack Legal Research, https://law.counselstack.com/opinion/erdman-co-v-phoenix-land-acquisition-llc-ca8-2011.