Environmental Defense Fund, Inc. v. Hoffman

566 F.2d 1060
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 25, 1977
DocketNos. 76-1366, 76-1431
StatusPublished
Cited by26 cases

This text of 566 F.2d 1060 (Environmental Defense Fund, Inc. v. Hoffman) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Defense Fund, Inc. v. Hoffman, 566 F.2d 1060 (8th Cir. 1977).

Opinion

HEANEY, Circuit Judge.

The principal question raised on this appeal is whether the final revised environmental impact statement (EIS),1 filed by the Corps of Engineers in conjunction with the Cache River-Bayou DeView Channelization Project, complies with the National Environmental Policy Act, 42 U.S.C. § 4321 et seq., (NEPA) and the mandate of this Court in Environmental Defense Fund, Inc. v. Froehlke, 473 F.2d 346 (8th Cir. 1972). The trial court concluded that the EIS fully complied with NEPA and that the action of the Corps in deciding to proceed as proposed in the EIS was not arbitrary and capricious. Accordingly, the trial court vacated an injunction it had previously issued restraining any construction on the project and dismissed the complaint. We affirm.

I

This is the second time the Cache River Project has been before this Court. The project involves clearing, realigning, enlarging and rechanneling, for flood control and drainage purposes, over two hundred and thirty-one miles of the Cache River, its upper tributaries and its principal tributary— the Bayou DeView. This public works project is presently estimated to cost the federal government over ninety-three million dollars.2 The lengthy history of the project, which was first authorized twenty-seven years ago,3 was outlined by this Court in Environmental Defense Fund, Inc. v. Froehlke, supra at 348. In that case, this Court reviewed the first EIS filed by the Corps in connection with the project and found it to be in violation of NEPA, the guidelines adopted by the Council on Environmental Quality (CEQ) and the regulations of the Corps itself. The Corps was ordered to submit a revised EIS and the trial court was ordered to grant appropriate injunctive relief. Id. at 356. On March 16, 1973, the trial court issued an injunction restraining any further construction pending the preparation of a revised EIS by the Corps. About four miles of the project had been completed at the time the injunction was filed.

Congress authorized a modification of the project in the Water Resources Development Act of 1974, Pub.L.No.93-251, § 99, 88 Stat. 41 (1974), in accordance with the Report of the Chief of Engineers, Department of the Army, Modification of Cache River Basin Feature, Mississippi River and Tributaries Project, Arkansas, H.Doc.No. 92-366, 92d Cong., 2d Sess. (1972). The Act authorized acquisition by fee or easement of not more than seventy thousand acres of Cache River Basin bottomlands to mitigate fish and wildlife resource losses as a result of the project. At least thirty thousand acres of the mitigation lands are to be available for public use. Federal expenditure for the mitigation lands is not to exceed seven million dollars. The Act further provides that “[n]o less than 20 per centum of the funds appropriated each fiscal year for the Cache River project shall be appropriated to implement mitigation until the full mitigation amount has been appropriated.”

On November 8, 1974, the Corps filed a final revised EIS, which consisted of six volumes including appendices, with the CEQ and the trial court. Soon thereafter, the federal defendants filed a motion to dissolve the injunction and dismiss the complaint. They later also filed a motion for [1064]*1064summary judgment. The trial court denied these motions and directed the parties to proceed with discovery. In November, 1975, the trial court held an extensive four-day hearing on the merits of the revised EIS at which more than twenty persons testified and numerous exhibits were presented. Briefs were filed by the plaintiffs,4 the federal defendants,5 the interve-nors6 and the amicus curiae.7 On March 22, 1976, the trial court filed its memorandum opinion discussing each of the issues raised by the plaintiffs with respect to the adequacy of the final revised EIS. It concluded that the revised EIS satisfied the requirements of NEPA, the guidelines of the CEQ and the regulations of the Corps; that the revised EIS formed an adequate basis on which the decision to proceed with the project could be made; and that the decision to proceed itself was not arbitrary and capricious. It then vacated the injunction it had previously issued restraining any construction on the project and dismissed the complaint. This appeal followed. Since the filing of this appeal, several events of significance to the issues raised have occurred.

On November 26, 1976, a contract was awarded for construction on the next upstream segment of three and one-tenth miles. On March 21, 1977, this Court refused to enjoin construction of this segment pending appeal. Construction is presently underway on the three and one-tenth-mile segment which is expected to be completed by the end of November, 1977.

Approximately one hundred and twenty acres of mitigation land has been purchased. Over fifteen thousand acres of mitigation land are scheduled for acquisition by mid-1978, subject to the availability of funds.

On February 21, 1977, President Carter announced a major review of all water resource projects in connection with the budget for fiscal year 1978. Water Resource Projects: The President’s Message to Congress Recommending Deletion of Funds for 19 Projects from the 1978 Fiscal Year Budget, 13 Weekly Comp, of Pres.Doc. 234 (February 21, 1977). The Cache River Project was one of nineteen major water resource projects which were initially identified as unsupportable on “economic, environmental, and/or safety grounds.” The President instructed the Secretaries of the Interior, the Army and of Agriculture to work with the CEQ and the Office of Management and Budget in carrying out a complete evaluation of each of the nineteen water resource projects questioned by the President. Representatives from each agency initially screened the projects and it was determined that the Cache River [1065]*1065Project required a more extensive review, Data was compiled to provide a detailed data base for each of the projects requiring further evaluation.8

In connection with this review, a public hearing lasting more than nine hours was held in Jonesboro, Arkansas, which is located within the project area. Public Works for Water and Power Development and Energy Research Appropriation Bill, 1978: Hearings before a Subcomm. of the Comm. on Appropriations House of Representa[1066]*1066tives, 95th Cong., 1st Sess. 256 (1977) [hereinafter cited as Public Works]. Approximately two thousand two hundred persons attended the hearing. Id. at 256-260. Two hundred and sixty-seven individuals spoke at the public hearing; twenty-six spoke in opposition to the project.9

The Cache River Project was found, by the representatives of the reviewing agencies, to meet all of the economic, environmental and safety criteria established. Nonetheless, the President recommended the deletion of funding for the project, the deauthorization of the project and that consideration be given to the protection of the remaining bottomland habitat. Public Works, supra at 3-5, 12. The following were listed as factors in the President’s decision:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Court of Appeals, Third Circuit
869 F.2d 719 (Third Circuit, 1989)
No Gwen Alliance of Lane County, Inc. v. Aldridge
841 F.2d 946 (Ninth Circuit, 1988)
Deukmejian v. Nuclear Regulatory Commission
751 F.2d 1287 (D.C. Circuit, 1984)
Nos. 83-1643, 83-1644
732 F.2d 1375 (Eighth Circuit, 1984)
Story v. Marsh
732 F.2d 1375 (Eighth Circuit, 1984)
James River Flood Control Ass'n v. Watt
553 F. Supp. 1284 (D. South Dakota, 1982)
Watershed Associates Rescue v. Alexander
586 F. Supp. 978 (D. Nebraska, 1982)
California v. Block
690 F.2d 753 (Ninth Circuit, 1982)
State of California v. Block
690 F.2d 753 (Ninth Circuit, 1982)
Farmland Preservation Ass'n v. Goldschmidt
611 F.2d 233 (Eighth Circuit, 1979)
Minnesota Public Interest Research Group v. Adams
482 F. Supp. 170 (D. Minnesota, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
566 F.2d 1060, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-defense-fund-inc-v-hoffman-ca8-1977.