Arkansas Wildlife Federation v. United States Army Corps of Engineers

431 F.3d 1096, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20257, 2005 U.S. App. LEXIS 28075, 2005 WL 3466082
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 20, 2005
Docket04-3546
StatusPublished
Cited by21 cases

This text of 431 F.3d 1096 (Arkansas Wildlife Federation v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arkansas Wildlife Federation v. United States Army Corps of Engineers, 431 F.3d 1096, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20257, 2005 U.S. App. LEXIS 28075, 2005 WL 3466082 (8th Cir. 2005).

Opinion

MURPHY, Circuit Judge.

Appellants brought this case against the United States Army Corps of Engineers alleging that the Corps had violated the National Environmental Policy Act (the Act) in connection with its Grand Prairie Area Demonstration Project (the Project) in East Central Arkansas and seeking declaratory and injunctive relief. Both sides moved for summary judgment, and the district court 1 granted judgment to the Corps. Appellants argue on their appeal that the cumulative impact analysis in the Final Environmental Assessment (FEA) was inadequate and that a Supplemental Environmental Impact Statement (SEIS) should have been prepared. We affirm.

The Grand Prairie Region consists of over 500,000 acres located between Mississippi and Arkansas, and it is a major rice producing area. This region relies on groundwater primarily from the Alluvial Aquifer and the Sparta Aquifer. The Alluvial Aquifer provides ninety percent of the agricultural water used in the region, and it will be depleted by 2015 unless protective action is taken. Depletion of the Alluvial Aquifer would cause severe economic hardship to the region; seventy seven percent of the irrigated crop would be lost, *1099 and rice production would decline by twenty three percent. The Sparta Aquifer provides drinking water to local residences and supplies the water needs of local industry, but the suitability of its drinking water will eventually be destroyed if it continues to be diverted for other uses as the Alluvial Aquifer is depleted.

The Grand Prairie Project was designed by the Corps to allow continued irrigation of the agricultural region while preserving the Alluvial Aquifer. The Corps issued a draft Environmental Impact Assessment (EIS) for public comment in early 1998. In July 1998 in response to the public comments, the Corps issued a draft General Reevaluation Report (GRR). The Final Environmental Impact Assessment (FEIS) was issued in 1999, and a Record of Decision (ROD) was signed in 2000. The FEIS and ROD selected “Alternative 7B” as the plan to be implemented. The Project has five components: (1) conservation of water by increasing agricultural efficiency of water usage, (2) reduction of water withdrawals from the Alluvial Aquifer so that there is no net loss of water and an end to drawing on the Sparta Aquifer for irrigation, (3) additional on farm reservoirs, (4) construction of a system that would pump excess water from the White River into the Grand Prairie region, and (5) various environmental improvement features. Since the signing of the ROD in 2000, twenty four percent ($71,000,000) of the total estimated cost of the Project ($319,-000,000) has already been invested.

Arkansas Wildlife Federation (AWF) 2 filed suit in February, 2004, alleging that the Corps had failed to comply with the Act and seeking a preliminary and permanent injunction against the construction of the water import feature of the Project. AWF alleged that the Corps had not considered all reasonably feasible alternatives before adopting Alternative 7B, that the FEIS and ROD had not adequately considered the cumulative impacts of the proposed project, that the Corps had not adequately considered the direct and indirect impacts of the Project on the White River basin, and that the Corps improperly tiered 3 the minimum flow requirements of the Arkansas State Water Plan to the FEIS.

In March, 2004 the Corps issued for public comment a Draft Environmental Assessment (DEA) and a Finding of No Significant Impact (FONSI). The DEA included a list of proposed changes to the original plan, including (1) converting 29 miles of canals into pipelines, (2) providing water delivery by pipeline instead of existing streams, (3) use of 113 acres of borrow pits to store materials for constructing levees instead of hauling material from a farther distance, (4) construction of a separate building to house the control system, (5) widening of a canal, (6) alignment changes to canals and pipelines, (7) replacement of canal 3200 with multiple small pipelines, and (8) rehabilitation of existing reservoirs.

*1100 The Corps issued a Final Environmental Assessment (FEA) and a FONSI in July 2004 which approved the changes proposed in the DEA. The Corps determined that the changes adopted by the FEA were minor and would cause no significant unmitigated environmental impacts not already considered and that preparation of a SEIS was therefore not required. AWF amended its pleadings to challenge this finding and argued that a SEIS was required.

Both sides moved for summary judgment. The district court found that AWF’s four year delay in challenging the FEIS, GRR, and ROD was unreasonable and that those claims were barred by lach-es. Alternatively, the district court held that the Corps had complied with the Act in connection with the FEIS, GRR, and ROD. The court additionally held that the Corps had adequately considered the cumulative impacts and the direct and indirect effects of the Project and that a SEIS had not been required following the changes adopted by the FEA. AWF appeals, arguing that the district court erred in finding no SEIS was required because the cumulative impact analysis by the Corps had been inadequate, substantial changes in the Project had been made, and significant new information had been discovered. ’

We review the district court’s grant of summary judgment de novo. Nunley v. Department of Justice, 425 F.3d 1132, 1135 (8th Cir.2005), but challenges to agency action are reviewed for whether it was arbitrary and capricious. 5 U.S.C. § 706(2)(A); Marsh v. Oregon Natural Resources Council, 490 U.S. 360, 374, 109 S.Ct. 1851, 104 L.Ed.2d 377 (1989). We are not free to substitute our own judgment for that of the agency, but rather our role is to “ensure that the agency has adequately considered and disclosed the environmental impact of its actions.” Mid States Coalition for Progress v. Surface Trans. Bd., 345 F.3d 520, 534 (8th Cir.2003)(quoting Baltimore Gas & Elec. Co. v. Natural Resources Defense Council, Inc., 462 U.S. 87, 98, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983)).

I.

[1,2) AWF contends that neither the FEIS nor the FEA adequately considered the cumulative impacts of past, present, and future action on the Project. In order to evaluate the FEA properly AWF argues we must first review the adequacy of the FEIS. The Corps responds that AWF’s failure to appeal the district court’s ruling on laches prevents it from now challenging the adequacy of the cumulative impact analysis in the FEIS.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Missouri v. U.S. Department of Interior
73 F.4th 570 (Eighth Circuit, 2023)
Black Warrior Riverkeeper, Inc. v. U.S. Army Corps of Eng'rs
354 F. Supp. 3d 1253 (N.D. Alabama, 2018)
Lakes & Parks Alliance v. Federal Transit Administration
91 F. Supp. 3d 1105 (D. Minnesota, 2015)
Defenders of Wildlife v. Salazar
877 F. Supp. 2d 1271 (M.D. Florida, 2012)
Wilderness Society v. United States Forest Service
850 F. Supp. 2d 1144 (D. Idaho, 2012)
FRIENDS OF THE NORBECK v. US Forest Service
780 F. Supp. 2d 975 (D. South Dakota, 2011)
Missouri v. United States Army Corps of Engineers
516 F.3d 688 (Eighth Circuit, 2008)
National Wildlife Federation v. Harvey
440 F. Supp. 2d 940 (E.D. Arkansas, 2006)
Sierra Club Northstar Chapter v. Bosworth
428 F. Supp. 2d 942 (D. Minnesota, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
431 F.3d 1096, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20257, 2005 U.S. App. LEXIS 28075, 2005 WL 3466082, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arkansas-wildlife-federation-v-united-states-army-corps-of-engineers-ca8-2005.