Airport Impact Relief, Inc. v. Wykle

192 F.3d 197, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20109, 49 ERC (BNA) 1596, 1999 U.S. App. LEXIS 24603, 1999 WL 768213
CourtCourt of Appeals for the First Circuit
DecidedOctober 1, 1999
Docket99-1469
StatusPublished
Cited by42 cases

This text of 192 F.3d 197 (Airport Impact Relief, Inc. v. Wykle) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Airport Impact Relief, Inc. v. Wykle, 192 F.3d 197, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20109, 49 ERC (BNA) 1596, 1999 U.S. App. LEXIS 24603, 1999 WL 768213 (1st Cir. 1999).

Opinion

TORRUELLA, Chief Judge.

Plaintiffs-appellants Airport Impact Relief, Inc. (“AIR”) and individual residents of East Boston 1 filed the present action to review and set aside the June 25, 1998 decision of Peter Markle, Division Administrator of the Federal Highway Administration (“FHWA”), to approve the Massachusetts Highway Department’s (“MHD”) revised plans for a construction project without preparing a supplemental environmental impact statement (“SEIS”). After conducting what it termed a “Phase One Nonjury Trial,” the district court entered judgment in favor of the defendants, finding that Markle’s decision to approve the *200 changes to the project without preparing an SEIS was not “arbitrary and capricious.” Plaintiffs appeal, and we affirm.

BACKGROUND

The Central Artery/Tunnel Project (the “CA/T Project”) is an extensive construction project planned in Boston, Massachusetts that is designed to ameliorate traffic congestion through downtown Boston and the two tunnels connecting downtown Boston with East Boston and Logan Airport. The portion of the project at issue connects two new roadways (Route 1A NorthBound and Route 1A Southbound) with the Massachusetts Bay Transportation Authority’s (“MBTA”) Blue Line Airport Station. We refer to this portion as the Logan Airport/Route 1A Interchange.

In 1985, the FHWA conducted an environmental review of the CA/T Project and prepared a Final Environmental Impact Statement (“FEIS”). The FHWA then approved the construction plans for the CA/T Project in 1986. In 1991, the project plans were revised, and the FHWA prepared a Final Supplemental Environmental Impact Statement (“FSEIS”) addressing the changes to the project. The FHWA approved the revised project in its 1991 Record of Decision.

In 1997, MHD issued a Notice of Project Change. (“NPC”) proposing a number of changes to the surface roads and transit elements of the Logan Airport/Route 1A Interchange. One change involves extending service road SR-2 so that it continues north to connect to the intersection of Prescott and Frankfort Streets. Under the previous design, SR-2 detoured east before continuing north. The proposed extension of SR-2 would result in the extended portion being located approximately 750 feet west of SR-2’s location in the 1991 approved plans. This would move SR-2 to the west of a seven-acre parcel of land known as the Robie Parcel. Thus, SR-2 would no longer bisect the Robie Parcel or separate it from the airport.

In addition to relocating SR-2, the proposed changes consist of: (1) the relocation of Airport Station approximately 500 feet north of its current location; (2) the redesign of Airport Station’s passenger entrances and bus platforms, including the elimination of the planned cross-platform connection between Logan Airport shuttle buses and the Blue Line trains; (3) the elimination of a bus loop- that would have connected both sides of Airport Station; (4) changes in the elevations of ramps and roadways, including raising Route 1A Southbound to as high as 36 feet; (5) the realignment of Ramp T-S and service road SR-10 to Terminal A; (6) the widening and extension of service road SR-10; (7) the elimination of service road SR-1; (8) the redesign of Ramp 1A-S as a surface roadway; and (9) the addition of service road SR-14 to connect Logan Airport and Airport Station.

The NPC was circulated for public comment by MHD as part of the environmental review process required by the Massachusetts Environmental Protection Act (“MEPA”). Several members of the public, including representatives of appellant AIR, raised environmental issues and concerns regarding the NPC. On May 13, 1998, Massachusetts Secretary of Environmental Affairs Trudy Coxe determined that the environmental effects of the changes did not require MHD to prepare a supplemental state environmental impact report.

While the state environmental review process proceeded, MHD also requested federal approval of the changes from the FHWA. On April 24, 1998, MHD submitted to the FHWA an Environmental Reevaluation of the proposed changes, consisting of the NPC and additional information gathered during the state review process. In the Environmental Reevaluation, MHD analyzed the environmental impacts of the proposed changes and expressed its belief that the FHWA need not conduct any further environmental review under the *201 National Environmental Policy Act of 1969 (“NEPA”). In a June 1, 1998 letter to the FHWA, Acting Deputy Regional Administrator Mindy Lubber of the United States Environmental Protection Agency (“EPA”) expressed the opinion that the changes merited a thorough environmental review and comment process under NEPA. After the FHWA reviewed the Environmental Reevaluation, FHWA Division Administrator Markle issued a June 25, 1998 decision letter to MHD, concurring in MHD’s conclusion that the proposed changes will have “negligible environmental impacts,” and therefore do not require the preparation of an SEIS.

In July of 1998, plaintiffs filed the present action, challenging the FHWA’s approval of the project changes and naming as defendants; (1) Markle, Division Administrator of the FHWA; (2) Kenneth R. Wykle, Administrator of the FHWA; (3) Kevin J. Sullivan, Commissioner of MHD; and (4) Patrick J. Moynihan, Chairman of MBTA and Secretary of the Executive Office of Transportation and Construction. In Count One, plaintiffs claimed that the June 25, 1998 decision violated section 102(2)(C) of NEPA, 42 U.S.C. § 4332(2)(C), and its applicable regulations by failing to require an SEIS to be prepared. In Counts Two and Three, which are not at issue in this appeal, plaintiffs claimed that the FHWA violated: (1) section 4® of the Department of Transportation Act of 1996, 49 U.S.C. § 303(c) and 23 U.S.C. § 138, and (2) Title VI of the Civil Rights Act of 1964, 42 U.S.C. §§ 2000 et seq. Count Three was dismissed by stipulation on October 1, 1998.

The FHWA’s administrative record was filed with the district court, and the parties sought to resolve the case through cross-motions for summary judgment. The district court advised the parties that any motions for summary judgment would be treated as motions for judgment upon the conclusion of a “Phase One Nonjury Trial.” Both sides then moved for judgment in their favor upon conclusion of the Phase One Trial on both Counts One and Two.

The district court conducted a three-day “Phase One Nonjury Trial” to address three issues: (1) the extent to which evidence beyond the FHWA’s administrative record would be considered in reviewing the FHWA’s decision; (2) whether the evidence created a genuine issue of material fact that would require a Phase Two Trial on the merits of the case; and (3) whether any party was entitled to judgment as a matter of law at the end of the Phase One Trial. The parties stipulated to various facts, and their counsel presented the parties’ respective positions and argued the pending motions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Historic Bridge Foundation v. Buttigieg
22 F.4th 275 (First Circuit, 2022)
Allen v. National Institutes of Health
974 F. Supp. 2d 18 (D. Massachusetts, 2013)
Tempest Fisheries v. Locke
701 F.3d 5 (First Circuit, 2012)
United States v. Commonwealth of Mass.
724 F. Supp. 2d 170 (D. Massachusetts, 2010)
Theodore Roosevelt Conservation Partnership v. Salazar
605 F. Supp. 2d 263 (District of Columbia, 2009)
Town of Winthrop v. Administration
535 F.3d 1 (First Circuit, 2008)
Northwest Bypass Group v. U.S. Army Corps of Engineers
552 F. Supp. 2d 97 (D. New Hampshire, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
192 F.3d 197, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20109, 49 ERC (BNA) 1596, 1999 U.S. App. LEXIS 24603, 1999 WL 768213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/airport-impact-relief-inc-v-wykle-ca1-1999.