Airport Impact Relief, Inc. v. Wykle

45 F. Supp. 2d 89, 1999 U.S. Dist. LEXIS 4407, 1999 WL 191611
CourtDistrict Court, D. Massachusetts
DecidedMarch 25, 1999
DocketCiv.A. 98-11342-REK
StatusPublished
Cited by3 cases

This text of 45 F. Supp. 2d 89 (Airport Impact Relief, Inc. v. Wykle) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Airport Impact Relief, Inc. v. Wykle, 45 F. Supp. 2d 89, 1999 U.S. Dist. LEXIS 4407, 1999 WL 191611 (D. Mass. 1999).

Opinion

Opinion

KEETON, District Judge.

Index

I. Introduction.93

II. Factual Background.93

III. Stipulated Factual Findings.94

A. Introduction.94

B. History of CA/T Project Environmental Review.94

C. Differences Between 1991 and 1998 Designs.95

D. Other Projects Allegedly Affected by the Changes.97

E. Section 4(f) Issues.97

IV. The Administrative Record.98

A. Introduction.98

B. Plaintiffs’ Affidavits .98

C. Defendants’ Affidavits .99

V. NEPA Issues.99

*93 A. The Duty to Supplement an EIS.

B. The Standard of Review... i — I

C. Alleged Procedural Flaws in the Decision Not to Prepare SEIS. i — 1

(1) FHWA’s Documentation of Its Decision. rH

(2) Decision Not to Open Process to Public Comment. rH

(3) The Independence of FHWA’s Review. rH

D. Assessing the Likely Impacts of the Changes. tH

(1) How Does the Court Measure the Impacts of the 1998 Changes?. rH

(2) The MHD Base Case. rH

(a) Ramp E-IAS. rH

(b) Shuttle Bus Roadways and Surface Roadway Improvements. rH

(3) Impacts that FHWA Mlegedly Failed to Consider. rH

(a) Community Impacts of Relocating Airport Station. rH

(b) Impact of Moving Arport Station on Public Transit Use. rH

(c) Impact of Change in Design óf Arport Station Bus Platform on

Transit Capacity . ^ tH

(d) Logan Arport Changes from Transfer of Robie Parcel. rH

(e) Effect of Changes on Proposed Urban Ring. ic rH

(f) Impacts of Raising Route 1A SB and Ramp E-IAS. U3 rH

(g) Impact on Open Space... 0 rH

(4) The EPA Letter. l> rH

VI. Section 4(f) Issues..'...:.•. l> rH

A. Introduction. | 0>

B. What Sites are Section 4(f) Protected?.,. 00 rH

C. Does the CA/T Project “Use” Memorial Stadium Park? . 00 rH

D. Aleged Procedural Irregularities. Oí rH

(1) The Independence of FHWA’s Review. Oí rH

(2) Circulation of a Section 4(f) Analysis . Oí rH

(3) Coordination with City of Boston. Oí rH

ORDER 109

I.

This case involves a dispute arising out of changes in the construction plans of the East Boston portion of the Central Artery/Tunnel Project (“CA/T Project”). The plaintiffs are an entity, AirportTmpact Relief, Inc. (“AIR”), and individual residents of East Boston. Defendants are sued in their official capacities as administrators of the Federal Highway Administration (“FHWA”), the Massachusetts Highway Department (“MHD”), and the Massachusetts Bay Transportation Authority (“MBTA”).

Having held a Phase One Nonjury Trial on March 11, 12, and 23, 1999, the court here addresses two principal issues: first, what is the proper scope of the administrative record, and second, are either the plaintiffs or the defendants entitled to judgment as a matter of law?

II. Factual Background

In 1991, FHWA approved construction plans for the CA/T Project.

In 1993, changes were made to the CA/T Project plans that affected East Boston and Logan Airport. These changes (referred to herein as the “1993 NPC”) are not directly challenged in this action. Docket No. 46, ¶ 13.

MHD made further changes to the construction plans in 1996 and 1997. As part of the environmental review required by the Massachusetts Environmental Protection Act (“MEPA”), MHD conducted an Environmental Reevaluation of the project including the changes. AR 41. MHD decided that it was not necessary to prepare a supplemental environmental impact statement (“SEIS”).

MHD submitted its decision not to prepare an SEIS for FHWA approval in 1997. FHWA approved the decision on June 26, 1998.

The challenged changes in the 1998-approved plan are summarized as follows:

*94 (1) MBTA’s Blue Line Airport Station was relocated 480’ to the north.

(2) The system of service roads to be used by the Airport shuttle buses traveling between the Airport terminals and Airport station was redesigned.

(8) Ramp E-1A southbound (“Ramp E-1AS”) and Route 1A southbound (Route 1A SB) were, under the 1998 plan, to be elevated.

(4) The airport service road SR-2 was relocated approximately 700’ closer to the East Boston community on the western side of the “Robie” parcel next to the North Service Area of the Airport.

(5) A new airport service road (SR-14) was created running parallel to Memorial Stadium Park’s northern boundary.

Collectively, these five changes will be referred to in this opinion as “the changes” or the “1998 changes.” The CA/T plan, incorporating these changes will be referred to as the “1998 plan.”

III. Stipulated Factual Findings
A. Introduction

The parties submitted Proposed Findings of Historical Facts and Proposed Evaluative Determinations, Inferences, Opinions and Conclusions (Docket No. 46 and attachment to Docket No.63). By marking upon the opposing side’s proposed findings, the parties have effectively stipulated to various facts.

I accept the stipulations and list those that are material here, adopting them as findings of this opinion (the underlining of phrases connotes that those parts are not agreed to and thus not included in the stipulations). I number the stipulations as the parties have (“P” indicating a paragraph of Docket No. 46 and “D” indicating a paragraph of attachment to Docket No.63).

B. History of the CA/T Project Environmental Review

Dl. A final Environmental Impact Statement/Report (“FSEIS/R”) for the Central Artery/Third Harbor Tunnel was published by the Federal Highway Administration and the Massachusetts Highway Department in August 1985.

D4. In May 1990, a 10-volume draft supplemental EIS/R (“DEIS/R”) for the CA/T Project was issued by the MHD and FHWA.

D6. In November, 1990, the MHD issued an 11-volume final supplemental EIR for the CA/T Project pursuant to the Massachusetts Environmental Policy Act.

D7. In January 1991, FHWA issued a 2-volume Final Supplemental SEIS....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
45 F. Supp. 2d 89, 1999 U.S. Dist. LEXIS 4407, 1999 WL 191611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/airport-impact-relief-inc-v-wykle-mad-1999.