Mid States Coalition for Progress v. Surface Transportation Board

345 F.3d 520, 2003 U.S. App. LEXIS 20245, 2003 WL 22251298
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 2, 2003
DocketNo. 02-1359, 02-1481, 02-1482, 02-1767, 02-1785, 02-1792, 02-1794, 02-1804, 02-1863
StatusPublished
Cited by44 cases

This text of 345 F.3d 520 (Mid States Coalition for Progress v. Surface Transportation Board) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid States Coalition for Progress v. Surface Transportation Board, 345 F.3d 520, 2003 U.S. App. LEXIS 20245, 2003 WL 22251298 (8th Cir. 2003).

Opinions

MORRIS SHEPPARD ARNOLD, Circuit Judge.

Petitioners challenge the decision of the Surface Transportation Board issued January 30, 2002, giving final approval to the Dakota, Minnesota & Eastern Railroad Corporation’s (DM & E) proposal to construct approximately 280 miles of new rail line to reach the coal mines of Wyoming’s Powder River Basin (PRB) and to upgrade nearly 600 miles of existing rail line in Minnesota and South Dakota. They maintain that in giving its approval the Board violated 49 U.S.C. § 10901, the National Environmental Policy Act (NEPA) (42 U.S.C. §§ 4321-4347), the National Historic Preservation Act (16 U.S.C. §§ 470 to 470w-6), and the Fort Laramie Treaty of 1868. Although we conclude that the Board should prevail on almost all of the issues raised by the petitioners, our rulings on a few issues require us to vacate the Board’s decision and to remand for further proceedings not inconsistent with this opinion.

[533]*533I.

Under 49 U.S.C. § 10901, the Board has exclusive licensing authority for the construction and operation of rail lines. This statute provides that the Board shall authorize the construction and operation of a proposed new line “unless the Board finds that such activities are inconsistent with the public convenience and necessity.” Although the Board’s authorizing statute does not define the term “public convenience and necessity,” in reaching its decisions the Board has historically asked whether there is a public demand or need for the proposed service, whether the applicant is financially able to undertake the construction and provide service, and whether the proposal is in the public interest and would not unduly harm existing services. If the Board is satisfied that the proposed project is not inconsistent with the public convenience and necessity, it proceeds to conduct an environmental review as required by NEPA. Once the environmental review is completed, the Board determines whether its original conclusion is still warranted after taking into account the potential environmental effects of the project and the cost of any necessary environmental mitigation.

In this case, the Board made an initial determination that DM & E’s proposal was merited under § 10901. The Board found that there was public demand for the line because it would offer a shorter and less expensive method by which to transport coal from the PRB mines to power plants. It also concluded that the proposed project would benefit existing shippers and that DM & E had demonstrated its financial fitness to carry the project through to completion. Having preliminarily found that the project would not be inconsistent with the public convenience and necessity, the Board instructed its Section of Environmental Analysis (SEA) to examine the potential environmental effects resulting from the construction and continuing operation of the proposed project.

SEA, in coordination with five cooperating federal agencies, then produced a nearly 5,000-page draft environmental impact statement (DEIS) examining the effects both of constructing the rail line extension to the PRB mines and rehabilitating DM & E’s existing lines in Minnesota and South Dakota to accommodate the coal traffic anticipated as a result of the project. SEA initially allowed 90 days for public review of and comment on the DEIS, but later extended this period by 60 days to ensure that the large number of persons and entities who wished to comment had ample opportunity to do so. The environmental review culminated with the issuance of a final environmental impact statement (FEIS), which contained further analysis in response to the comments received on the DEIS. The FEIS also made recommendations to the Board regarding environmentally preferable routing alternatives and mitigation measures. In all, the environmental review process took nearly four years and generated roughly 8,600 public comments.

II.

The NEPA mandates that a federal agency “take a ‘hard look’ at the environmental consequences” of a major federal action before taking that action. Baltimore Gas & Elec. Co. v. Natural Res. Def. Council, Inc., 462 U.S. 87, 97, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983) (quoted case omitted). To comport with this standard, an agency must prepare a “detailed statement” (generally, an EIS), 42 U.S.C. § 4332(2)(C), “from which a court can determine whether the agency has made a good faith effort to consider the values NEPA seeks to protect.” Minnesota Pub. Interest Research Group v. Butz, 541 F.2d [534]*5341292, 1299 (8th Cir.1976), cert. denied, 430 U.S. 922, 97 S.Ct. 1340, 51 L.Ed.2d 601 (1977).

In reviewing the agency’s decision, we are not free to substitute our judgment for that of the agency. Vermont Yankee Nuclear Power Corp. v. Natural Res. Def. Council, Inc., 435 U.S. 519, 555, 98 S.Ct. 1197, 55 L.Ed.2d 460 (1978); Friends of the Boundary Waters Wilderness v. Dombeck, 164 F.3d 1115, 1128 (8th Cir.1999). Our role in the NEPA process “is simply to ensure that the agency has adequately considered and disclosed the environmental impact of its actions and that its decision is not arbitrary or capricious.” Baltimore Gas, 462 U.S. at 97-98, 103 S.Ct. 2246; see 5 U.S.C. § 706.

A.

We begin our review of the agency’s actions under NEPA by addressing the objections raised by the city of Rochester, the Mayo Foundation, and Olmstead County, since their objections are to a large degree overlapping. DM & E’s existing line, carrying an average of three trains per day, runs through Rochester and Olm-stead County. In the FEIS, SEA recommended reconstruction of the existing line as the environmentally preferable alternative for the Rochester area, and the Board in its final decision accepted this recommendation. SEA rejected the proposed construction of a bypass around Rochester and a no-action alternative. Because Rochester is the largest community located on DM & E’s projected route and Mayo is one of the most sophisticated medical centers in the nation, they could be expected to be particularly alert to any environmental degradation that might arise from the project that the Board approved. We therefore address their claims with some degree of specificity.

1. Reconstruction of the rail line through Rochester would result in increased rail traffic through the city.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blue Ridge Environmental Defense League v. SCDES
Supreme Court of South Carolina, 2026
Earth Island Institute v. Usfs
87 F.4th 1054 (Ninth Circuit, 2023)
Eagle County, Colorado v. STB
82 F.4th 1152 (D.C. Circuit, 2023)
Hippely v. United States
Federal Claims, 2022
Ctr. for Biological Diversity v. David Bernhardt
982 F.3d 723 (Ninth Circuit, 2020)
In re Applications of Enbridge Energy, Ltd.
930 N.W.2d 12 (Court of Appeals of Minnesota, 2019)
Wildearth Guardians v. Jewell
District of Columbia, 2019
WildEarth Guardians v. Zinke
368 F. Supp. 3d 41 (D.C. Circuit, 2019)
Rodeo Citizens Assn. v. County of Contra Costa
California Court of Appeal, 2018
Rodeo Citizens Ass'n v. Cnty. of Contra Costa
231 Cal. Rptr. 3d 332 (California Court of Appeals, 5th District, 2018)
Standing Rock Sioux Tribe v. United States Army Corps of Engineers
255 F. Supp. 3d 101 (District of Columbia, 2017)
Committee of 100 on the Federal City v. Foxx
87 F. Supp. 3d 191 (District of Columbia, 2015)
Vermonters for a Clean Environment, Inc. v. Madrid
73 F. Supp. 3d 417 (D. Vermont, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
345 F.3d 520, 2003 U.S. App. LEXIS 20245, 2003 WL 22251298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-states-coalition-for-progress-v-surface-transportation-board-ca8-2003.