Environmental Defense Fund, Inc. v. Alexander

501 F. Supp. 742, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20242, 1980 U.S. Dist. LEXIS 17670
CourtDistrict Court, N.D. Mississippi
DecidedOctober 1, 1980
DocketEC 77-53, 77-54-K
StatusPublished
Cited by19 cases

This text of 501 F. Supp. 742 (Environmental Defense Fund, Inc. v. Alexander) is published on Counsel Stack Legal Research, covering District Court, N.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Defense Fund, Inc. v. Alexander, 501 F. Supp. 742, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20242, 1980 U.S. Dist. LEXIS 17670 (N.D. Miss. 1980).

Opinion

MEMORANDUM OPINION

READY, Chief Judge.

This is another chapter in the saga of the ongoing controversy relating to the Tennessee-Tombigbee Waterway (TTW), a navigation project in Alabama and Mississippi which Congress authorized in 1946 and commenced funding in 1971.

On July 14, 1971, Environmental Defense Fund, Inc. (EDF), Committee for Leaving the Environment of America Natural (CLEAN) and James D. Williams brought a class action on behalf of all persons aggrieved or detrimentally affected by the project against the Secretary of the Army, Chief of Engineers and United States Corps of Engineers to enjoin construction of TTW. The district court on April 13, 1972, dismissed five of the six causes of action alleged in the complaint and ordered an evidentiary hearing on the cause of action based upon noncompliance with the National Environmental Policy Act of 1969 (NEPA). On August 4,1972, the complaint was dismissed *746 with prejudice. The district court, while declining to make a substantive review under NEPA, found that defendants had fully complied with NEPA’s procedural requirements, EDF v. Corps of Engineers, 348 F.Supp. 916 (N.D.Miss.1972). On appeal, the Fifth Circuit affirmed, holding not only that NEPA’s procedural requirements had been fully satisfied but also that substantive review by the courts was foreclosed since Congress, which had authorized TTW before NEPA became law and approved and funded its construction after it enacted NEPA, was the ultimate decisionmaker. EDF v. Corps of Engineers, 492 F.2d 1123 (5 Cir. 1974). Certiorari was not applied for.

On November 30,1976, the present action was filed to enjoin the continued construction of the waterway. As before, plaintiffs are EDF, CLEAN and a plaintiff class of individuals aggrieved or detrimentally affected by TTW. Additional plaintiffs are Louisville & Nashville Railroad (L&N), Randall Grace, National Audubon Society, Birmingham Audubon Society and Alabama Conservancy. After extensive discovery, plaintiffs on January 30, 1978, filed an amended complaint which consisted of 15 counts.

In a lengthy evidentiary hearing on the first two counts, the district court held that plaintiffs’ primary claim that defendants lacked statutory authorization to construct a channel 300' wide was barred by laches, and that other challenges to modifications of original project design were without merit. EDF v. Alexander, 467 F.Supp. 885 (N.D.Miss.1979), aff’d, 614 F.2d 474 (5 Cir. 1980), pet. for cert. filed, 49 USLW 3031 (Aug. 5, 1980).

Following status conference on May 30, 1980, the court dismissed Count XI upon motion of plaintiffs and scheduled the remaining 12 counts to be considered for disposition on cross-motions for summary judgment and defendants’ alternative motion for judgment on the pleadings. The parties have submitted a plethora of exhibits and affidavits as well as voluminous briefs in support of their respective motions.

After due consideration, the court finds that plaintiffs are not entitled to prevail and their amended complaint is dismissed with prejudice, except in one particular as to Count XIV. Instead of treating the counts seriatim, the court has organized discussion of the remaining claims as follows: (1) NEPA issues, (2) benefit/cost computation, (3) local assurances, (4) fish and wildlife, (5) discharge of dredged material, and (6) failure to publish agency regulations.

I. NEPA ISSUES

In Counts VII, VIII, IX and X, plaintiffs challenge a variety of environmental and economic aspects of the project which they claim violate NEPA, 42 U.S.C. § 4321 et seq. These contentions may be summarized as follows:

(1) illegal segmentation of TTW into two parts, one a waterway between Pickwick Pool in Tennessee and Demopolis, Alabama, and the other a waterway between Demopolis and Mobile, and failure to prepare, circulate and file an Environmental Impact Statement (EIS) discussing the effects on both segments before continuing con- ■ struction;
(2) failure to analyze and disclose project alternatives in the 1976 Economic Reanalysis Summary;
(3) failure to prepare a supplemental or revised EIS after making major changes in project design and subsequently identifying adverse environmental and economic impacts.

Defendants contend that plaintiffs, in attempting to raise charges of NEPA noncompliance, have failed to state claims upon which relief can be granted or that, since there is no genuine issue of material fact, defendants are entitled to summary judgment on all NEPA issues.

Of the many environmental challenges made by plaintiffs, the primary complaint is that the 1976 Economic Reanalysis Summary revealed for the first time that “TTW’s *747 fundamental purpose was to move goods from waters north of Pickwick, Tennessee, through Demopolis, Alabama, and down the river below Demopolis to Mobile,” and it was then first disclosed that TTW would require work downstream from Demopolis to achieve maximum navigation benefits. According to plaintiffs, when Corps officials in 1975 discovered that 8-barge tows could not navigate south of Demopolis, they decided to divide the TTW project by treating the 300' waterway between Pickwick and Demopolis separately from the 200' waterway between Demopolis and Mobile, and to continue construction on the northern part while studying need for work on the southern part. It is urged that this procedure contravenes NEPA since an EIS on the entire project-Pickwick to Mobile-must be prepared, published and filed before work may continue north of Demopolis. No EIS on the TTW, so plaintiffs contend, has ever discussed and analyzed the impacts of the project upon the river south of Demopolis or upon the Port of Mobile.

In advancing this contention plaintiffs ignore the history of TTW, Black WarriorTombigbee River (BWT) and the Port of Mobile as separate congressionally-authorized navigation projects as well as the adjudication that defendants have fully complied with NEPA. This court has previously recounted TTW’s history. The salient features are that TTW’s original 1939 survey, as contained in House Document 269, reported that the “improvement desired is a navigable waterway of dimensions which would permit modern barge-line operation between the Tennessee and Tombigbee Rivers.” 1 House Document 486, which was incorporated in the authorizing statute, Pub.L.No. 79-525, 79th Cong., 2d Sess., enacted July 24, 1946, discussed the “function of the canal and its connections as a through route between the Gulf of Mexico and the Ohio, upper Mississippi, Missouri, and Illinois Rivers.” 2 As we have previously found, TTW was designed from its inception as

a navigational project for two-way barge traffic to connect the north-flowing Tennessee River with the south-flowing Tombigbee River so as to provide a continuous waterway from the Tennessee, upper Mississippi and Ohio Valleys to the tidewater Port of Mobile on the Gulf of Mexico.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Shoreacres v. Texas Commission on Environmental Quality
166 S.W.3d 825 (Court of Appeals of Texas, 2005)
San Carlos Apache Tribe v. United States
272 F. Supp. 2d 860 (D. Arizona, 2003)
Sierra Club v. U.S. Army Corps of Engineers
935 F. Supp. 1556 (S.D. Alabama, 1996)
Walker v. Kerr-McGee Chemical Corp.
793 F. Supp. 688 (N.D. Mississippi, 1992)
MO. COALITION FOR ENVIRONMENT v. Corps of Engineers
678 F. Supp. 790 (E.D. Missouri, 1988)
County of Bergen v. Dole
620 F. Supp. 1009 (D. New Jersey, 1985)
Texas Committee On Natural Resources v. Marsh
736 F.2d 262 (Fifth Circuit, 1984)
Horton v. Hartford Life Insurance
570 F. Supp. 1120 (N.D. Mississippi, 1983)
Environmental Defense Fund, Inc. v. Alexander
554 F. Supp. 451 (N.D. Mississippi, 1982)
Merritt v. Quaker Oats Co.
538 F. Supp. 24 (S.D. Mississippi, 1981)
Environmental Defense Fund v. Marsh
651 F.2d 983 (Fifth Circuit, 1981)
Izaak Walton League of America v. Marsh
655 F.2d 346 (D.C. Circuit, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
501 F. Supp. 742, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20242, 1980 U.S. Dist. LEXIS 17670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-defense-fund-inc-v-alexander-msnd-1980.