Environmental Defense Fund, Inc. v. Alexander

554 F. Supp. 451
CourtDistrict Court, N.D. Mississippi
DecidedJuly 20, 1982
DocketEC 77-53-K, EC 77-54-K
StatusPublished

This text of 554 F. Supp. 451 (Environmental Defense Fund, Inc. v. Alexander) is published on Counsel Stack Legal Research, covering District Court, N.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Defense Fund, Inc. v. Alexander, 554 F. Supp. 451 (N.D. Miss. 1982).

Opinion

*452 FIRST ORDER ON REMAND

READY, Chief Judge.

In obedience to the August 24,1981, mandate of the United States Circuit Court of Appeals for the Fifth Circuit issued herein pursuant to opinions released July 13 and August 17 which affirmed in part and reversed in part the final judgment of this court rendered October 1, 1980, 501 F.Supp. 742, it is

ORDERED

1. That summary judgment be granted in favor of plaintiff Louisville & Nashville Railroad Company on the claim that the federal defendants, Secretary of the Army and the United States Army Corps of Engineers, are in violation of the Water Resources Development Act of 1974, 42 U.S.C. § 1962d-17, as well as Engineer Regulation 405-2-680, for having used a lower interest rate formula provided by 42 U.S.C. § 1962d-17(b) to discount future benefits and compute costs of the Tennessee-Tombigbee Waterway (TTW). Accordingly, federal defendants are ordered and directed to cease using the lower formula and utilize instead in all future cost-benefit computations for the TTW the higher interest rate formula specified in 42 U.S.C. § 1962d-17(a).

2. That summary judgment be granted in favor of all plaintiffs on their claim that the federal defendants, Secretary of the Army and United States Army Corps of Engineers, in the course of planning and constructing the TTW, are in violation of the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq. as well as relevant Corps regulations for failing to prepare and submit a supplemental Environmental Impact Statement (EIS) on the project changes made since March 1971, when the original EIS on the navigation project was submitted. Accordingly, the federal defendants are hereby ordered and directed to prepare and submit a final supplemental EIS covering changes in the economic projections and design of the Waterway since the 1971 EIS, for detailed discussion and analysis of at least the following issues, in accordance with Corps Regulations:

(a) Impacts from changes in post-1971 projections of traffic levels, directions and cargo estimated for the TTW.
(b) Impacts from the increased acres of land planned for acquisition and use in the project over and above the land planned for the Waterway’s acquisition and use in the 1971 EIS.
(c) Impacts from the planned substitution of a chain of lakes design for the perched canal in the so-called “canal section” of the Waterway.
(d) Impacts from the planned straightening of the Tombigbee River by artificial cutoffs to isolate 21 miles of the river channel.

The court determines from the record made at today’s pretrial conference that June 1, 1982, represents the expiration of a reasonable time to be allowed for the submission of a final supplemental EIS. Therefore, federal defendants shall, not later than June 1, 1982, submit to the court a final supplemental EIS by filing same with the clerk of court and concurrently serving copy upon plaintiffs’ counsel. Plaintiffs shall have 60 days from receipt of the final sup *453 plemental EIS within which to file written objections, stating the grounds therefor, with the clerk of court. If no such objections are made within this period of time or such additional time as the court may for good cause allow, federal defendants may apply to the court for a final order terminating this action. Should timely objections be interposed by plaintiffs, the court shall, upon notice to all parties, after allowing discovery for a reasonable period of time, conduct an evidentiary hearing to resolve issues raised by plaintiffs as to the sufficiency of the final supplemental EIS as well as the Corps’ compliance, both procedurally and substantively, with NEPA and relevant Corps regulations, and enter a final order. At any such evidentiary hearing, plaintiffs shall have the burden of proof as to all issues raised in their objections.

3. At the pretrial conference this date attended by all attorneys, counsel agreed that they would endeavor to resolve the question of whether there is need for the court to immediately grant an injunction against the work presently in progress on those portions of the TTW for which a final supplemental EIS has been ordered, and that counsel would notify the court by September 17, 1981, as to the progress of their negotiations. All counsel having represented that a reasonable prospect exists for resolving this question and thereby obviating the necessary for an early hearing, it is ordered that the scheduling of an evidentiary hearing be deferred until further notice.

Jurisdiction of these causes is retained to effectuate the foregoing steps.

CONSENT AGREEMENT AND ORDER

In an effort to implement the opinion of the United States Court of Appeals for the Fifth Circuit of July 13, 1981, that Court’s subsequent order of August 17, 1981, and this Court’s order of September 2,1981, the parties have agreed, as set forth below, regarding the Tennessee-Tombigbee Waterway (TTW). Accordingly, it is hereby AGREED and ORDERED as follows:

1. Duration of this Agreement and Order: This Agreement and Order shall be in effect until sixty (60) days after the filing of the Supplemental Environmental Impact Statement (SEIS) with the Court. Any further proceedings in this case shall be in accordance with the Court’s order of September 2, 1981, or such other order as the Court may enter.

The plaintiffs contend that this Agreement and Order should extend until the entry of a final order in this case. Defendants have agreed that this Agreement shall last only until sixty (60) days after the filing with the Court of the SEIS, and contend that no work suspension or other restraint would be appropriate after the time period provided for in this Agreement.

2. New Construction Activity: Upon approval of this Agreement and Order by the Court, and for the duration of this Agreement and Order, the Corps shall not award or proceed with the following new construction contracts: Aberdeen Reservoir Clearing (Contract No. DACW-01-80-C-0190), Lock C — Relocation of TVA Facilities and Lock C — Relocation of Tombigbee Electric Power Facilities; and the Corps shall not perform the work contemplated by these three contracts through any other contract or in any other manner. In addition, for the duration of this Agreement and Order, the Corps shall not engage in negotiations concerning relocation of these TVA Facilities, or in negotiations concerning the relocation of these Tombigbee Electric Power Facilities. The map attached as Appendix A approximately depicts the area covered by Contract No. DACW-01-80-C-0190, which contract precisely describes the work contemplated under the terms of that contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Environmental Defense Fund, Inc. v. Alexander
501 F. Supp. 742 (N.D. Mississippi, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
554 F. Supp. 451, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-defense-fund-inc-v-alexander-msnd-1982.