Environmental Barrie v. Slurry Systems Inc

CourtCourt of Appeals for the Seventh Circuit
DecidedAugust 29, 2008
Docket06-3910
StatusPublished

This text of Environmental Barrie v. Slurry Systems Inc (Environmental Barrie v. Slurry Systems Inc) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Barrie v. Slurry Systems Inc, (7th Cir. 2008).

Opinion

In the

United States Court of Appeals For the Seventh Circuit ____________

No. 06-3910

E NVIRONMENTAL B ARRIER C O ., LLC,

Plaintiff-Appellee, v.

S LURRY S YSTEMS, INC., Defendant-Appellant. ____________ Appeal from the United States District Court for the Northern District of Illinois, Eastern Division. No. 06 C 0212—Rebecca R. Pallmeyer, Judge. ____________

A RGUED S EPTEMBER 17, 2007—D ECIDED A UGUST 29, 2008 ____________

Before F LAUM, R IPPLE, and W OOD , Circuit Judges. W OOD , Circuit Judge. After an arbitration hearing to resolve a construction contract dispute between Environ- mental Barrier Company (“EBC”) and Slurry Systems, Inc. (“SSI”), Arbitrator Franklin I. Kral issued an award in favor of EBC in the amount of $388,919.88. When SSI did not pay, EBC filed suit in Illinois court to confirm the award, and SSI responded by removing the case to the U.S. District Court for the Northern District of Illinois. SSI 2 No. 06-3910

urged the district court to vacate the arbitral award, or in the alternative, to modify it. The district court did neither: instead, it confirmed the award entered by Arbitra- tor Kral. In the course of doing so, the court held that EBC had “standing” to enforce the arbitration clause in the contract and that the arbitrator had not exceeded his powers. On appeal, SSI is now urging us to find that EBC never obtained the right to enforce the contract’s arbitra- tion clause. SSI’s appellate briefs present this argument as a challenge to arbitrability, based on the fact that SSI agreed to arbitrate only with EBC’s predecessor-in-interest, not with EBC itself. This is a major shift from the way SSI presented its case first to the arbitrator and later to the district court, where it framed the issue in terms of EBC’s standing to pursue this arbitration. The difference is crucial—indeed, on these facts, fatal—to SSI’s claim.

I On February 29, 2000, the U.S. Army Corps of Engineers entered into a contract with SSI for work on a project to reduce flooding during heavy rains. The McCook Reservoir Project, as it was called, involved the construction of a multibillion-gallon reservoir; SSI won the right to build the overburden cutoff wall. SSI in turn subcontracted part of its work to an entity called Geo-Con, Inc., using a form contract that the parties signed in April 2000. The parties’ briefs recount in detail the progress of SSI’s and Geo-Con’s work from 2000 to 2003; we include only the facts pertinent to this appeal. No. 06-3910 3

Attachment A to the SSI/Geo-Con subcontract elaborated on Article 8.1 of the text, specifying that “Contractor and Subcontractor shall jointly work together to perform all of the work together [sic] to minimize the overall cost of the work.” Attachment A also included a longer version of Article 10.1, which described how the parties would allocate revenues, costs, profits, and loss and gave guid- ance for a final settling-up based on the actual distribution of costs. The subcontract also contained an exclusivity clause, Article 1.3; a broad arbitration clause covering “[a]ny claim arising out of or related to this Subcon- tract,”Article 6.2; and a clause restricting assignment or sub-subcontracting, Article 7.4.2. The project’s scope and methodology changed as the work proceeded, requiring the Corps at one point to suspend operations while it figured out an alternative way to finish the project. Once the modifications to the Prime Contract were in place, SSI and Geo-Con resumed their joint effort to complete their portion of the work. By April 2003, they were finished with their construction work. What remained to be done was the final reckoning of who owed whom how much; this proved to be more difficult. There were, for instance, several pending change orders, and it was unclear how costs and profits would be shifted among the parties. To the extent that these financial details are relevant, we return to them later. EBC entered the picture in September 2003, when Geo- Con, for reasons unrelated to the McCook project, filed for bankruptcy in the U.S. Bankruptcy Court for the Southern District of New York. During Geo-Con’s reorga- 4 No. 06-3910

nization, EBC (through two intermediary entities) acquired substantially all of Geo-Con’s assets for a purchase price of $2.1 million. The bankruptcy court found that EBC was the only qualified purchaser of Geo-Con’s assets. In an order dated April 16, 2004, the court approved the sale in accordance with the terms set forth in a letter from the intermediaries. Part II of the offer letter addressed the Geo-Con acquisition and set forth a list of “excluded assets.” The exclusions included “[a]ll contracts for services to be performed by Geo-Con, except . . . P90099 McCook, IL” (emphasis added). In other words, the McCook contract was acquired by the intermediary, and then passed along to EBC. There was a Schedule A to the offer letter that listed equipment loans and leases. This was the “Schedule A” to which the bankruptcy court referred when it said in its order that the contracts listed in Schedules A and C were executory. The sale of the McCook contract was later reflected on Schedule D to the April 29, 2004, bill of sale between Geo- Con and EBC that carried out the bankruptcy court’s order. The bill of sale provided that Geo-Con was selling “all of Seller’s accounts receivable (including without limitation the accounts set forth on Schedule A hereto),” and “contracts” specified as the “Assumed Contracts.” This was a different “Schedule A” than the one attached to the offer letter mentioned in the bankruptcy court’s April 16 order. Schedule A to the bill of sale lists accounts receivable and contracts that EBC was acquiring, and it includes the McCook project. Thus, the fact that the bankruptcy court had described the contracts listed in Schedules A and C as executory has little bearing on this case. No. 06-3910 5

SSI asserts that it was not aware of Geo-Con’s bank- ruptcy proceedings as they were taking place. It learned about them, however, no later than June 17, 2004, when EBC notified SSI by letter that EBC had succeeded to Geo- Con’s rights under the subcontract. The letter contained a demand that SSI pay EBC the balance due to Geo-Con for the work that Geo-Con had performed under the subcontract. At the time, EBC believed that this balance was $711,000. (It later found out that SSI had received two additional payments from the Corps that it had not disclosed, totaling $425,951.38; the discrepancy is im- material for our purposes.) EBC’s June 2004 letter also noted that the “subcontract between Geo-Con and Slurry Systems calls for mediation and arbitration of disputes,” but it added that EBC’s preference is to resolve its claim against Slurry Systems amicably, if possible, without the expenditure of mediation fees and expenses which, pursuant to the contract, are to be shared equally by the parties. Accordingly, we request an opportunity to meet with you within the next two weeks to discuss and hope- fully resolve EBC’s claim. If you are unwilling to meet with us within that time, EBC will commence media- tion and arbitration proceedings. SSI did not respond positively to EBC’s letter. On July 7, 2004, SSI’s attorneys sent a letter to EBC’s counsel, express- ing the opinion that “all disputes between Geo-Con and Slurry Systems have been resolved,” and adding that, “[a]s a matter of fact, Geo-Con actually owes Slurry Systems, but because of Geo-Con’s liquidation, there is no point in 6 No. 06-3910

Slurry pursuing the matter.” SSI’s letter noted EBC’s statement that the subcontract between Geo-Con and SSI “calls for the mediation and arbitration of disputes,” and requested that EBC provide SSI “with a copy of the subcontract if you still plan to pursue this matter[.]” EBC did pursue the matter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Wiley & Sons, Inc. v. Livingston
376 U.S. 543 (Supreme Court, 1964)
At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
Agco Corporation v. Max Anglin
216 F.3d 589 (Seventh Circuit, 2000)
Robert Zivitz and Nancy Zivitz v. Joel Greenberg
279 F.3d 536 (Seventh Circuit, 2002)
Steel Co. v. Citizens for a Better Environment
523 U.S. 83 (Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Environmental Barrie v. Slurry Systems Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-barrie-v-slurry-systems-inc-ca7-2008.