Emery v. Raleigh & Gaston Railroad

9 S.E. 139, 102 N.C. 209
Supreme Court of North Carolina·Decided February 5, 1889·Published·Cited by 67 cases

Opinion

Avery, J.

(after stating the facts). The action was brought to recover damage for injury done to plaintiff’s brick-yard in the year 1885, and again in May, 1887, and to his crops,, by overflows caused by the defective construction of a culvert over a creek on the defendant’s line.

The first and second exceptions present the question,, whether his Honor erred in refusing to submit two additional issues tendered by defendant’s counsel. It was not the design in adopting the new procedure, that parties should be bound by rules so technical as those which governed the old system of pleading. The forms of action being disregarded, and it being requisite only, under The Code, to allege the material facts in the complaint, and to admit or deny the allegations in the answer, ordinarily it must be left to the sound discretion of thenidprius Judge to deiermine, when required or allowed to settle tlu> issues, whether the action can be tried more intelligently and satisfactorily by the jury upon specific issues, submitted for the purpose of eliciting distinct findings in the nature of a special verdict, or by confining the inquiry, in imitation of the old method, to a single issue, or a small number of issues, and pointing out, by instruction, how the conflicting evidence, controverted in the pleadings and on trial, though not involved in the terms of the issues submitted, bears upon the verdict to be rendered in response to them, provided, always, that the issues submitted are raised by the pleadings.

*225 It is misleading to embody in one issue two propositions, as to which the jury might give different responses, and on exception taken in apt time, a new trial will in such cases be granted. The facts found by a jury, whether comprehended under one or many issues, must be sufficient to-enable the Court to proceed to judgment. When the judgment can be predicated upon the findings, though it may appear that the Judge who tried the case below refused to-submit more specific issues tendered by a party, yet, if he told the jury how the testimony relating to the issues refused should be considered in connection with the law, in passing upon those submitted, and thereby gave opportunity to enter exception to the instruction given, and to the refusal to give that asked, the appellate Court will not grant a new trial. The Court will impose no limit to the exercise of discretion on the part of the Judge below, in settling the issues, except that the facts established by the responses to them shall constitute a lawful basis for the judgment, and that an appellant was not denied an opportunity to have the law applicable to any material portion of the testimony fairly presented and passed upon by the jury, through the medium of some issue.

The defendant contends that there was error in declining to submit to the jury the two issues offered :

“ 1. What was the depth of rain-fall on 10th of May, 1887 ? Was the rain-fall 10th of May excessive and extraordinary?

“2. What damage did plaintiff sustain by ponding back of the water on that occasion ?”

His Honor presented the whole question of negligence on. the part of the defendant in the first of the five issues, to-which the jury responded, and which is in the following language:

“ Has the defendant negligently ponded water back upon the plaintiff’s land ?”

*226 The Judge instructed the jury upon the question of negligence on deferídaut’s part as follows:

“It was the duty of defendant to have constructed its culvert so it would carry off the water of the stream under all ordinary circumstances and the usual course of nature, even to the extent of such heavy rains as are ordinarily expected, unless it. lias the right of grant, actual or presumed, to make it smaller. If the defendant so constructed the culvert that it was not sufficient to carry off the water of the stream undei ordinary circumstances (and by ordinary circumstances is nm;tnt the usual rain-fall), even if such heavy rains are occasional, and by reason of insufficient culvert the plaintiff’s land was overflowed, the answer to the first issue should be 1 Yes,’ unless the defendant had acquired the right to pond water on the plaintiff’s land.”

We think his Honor stated the law correctly, and is sustained by the case of Wright v. Wilmington, 92 N. C., 156, and the authorities there cited; also Woo'd on Railways, vol. 2, sec. 253, p. 873.

By applying the law, as stated by the Court, the jury would naturally determine from the testimony whether the rain-fall of the 10th of Majq 1887, or that in the year 1885, was so extraordinary and excessive that it could not have been reasonably expected to fall, and if such was the character of the rain at either date, they would naturally leave out any injury sustained by such a rain-fall, in making their estimate of the damage; or if they found that all the damage sustained by the plaintiff, both in his brick-yard and as to his crops, was attributable to extraordinary rains, they would of course respond “ No ” to the issue. Plis Honor, in addition to the language quoted from his charge, told the jury that the defendant was “ not negligent, if the overflow was the result of extraordinary and unusual rain-fall.” The •defendant introduced a witness, P. B. Hawkins, who testi *227 fied that he built the culvert in 1859, was contractor for the work, and that one Bodwell, a civil engineer, had direction of the construction.

The defendant offered to show by the witness Hawkins “ the reputation of Bodwell as an intelligent and expert engineer.” On objection by the plaintiff, the testimony was held to be incompetent, and the defendant excepted. Counsel on the argument in this Court did not abandon this exception, but failed to cite any authority in support of it; and we cannot see how the fact that the engineer, who had the oversight of the construction of the culvert, was an intelligent and expert engineer, tends to show that the culvert was in fact so constructed as to carry off any but an excessive fall of rain.

The plaintiff had, before the introduction of the witness P. B. Hawkins, “ offered to prove, as tending to show negligence, that, some two hundred yards below, on the same stream, the Roanoke Navigation Company had constructed a culvert before defendant, which was twenty-six feet wide,” but upon objection by defendant the testimony -was then excluded. The witness Hawkins, having qualified himself to speak as an expert, said: “ I think the culvert a sufficiently large culvert for the size of the stream. I thought it sufficient to carry off any rise. It was the largest culvert I ever built.” Subsequently the Court, being of opinion that the defendant, by the examination of Hawkins, had “opened the door” and made the evidence previously excluded competent, allowed a witness to testify, after objection on the part of the defendant, that the culvert built by the Roanoke Navigation Company, two hundred yards below, on the same stream, was larger than that built by Hawkins, and this is the ground of another exception relied on by the defendant. We concur with his Honor in his ruling.

Free access — add to your briefcase to read the full text and ask questions with AI

Emery v. Raleigh & Gaston Railroad, 9 S.E. 139, 102 N.C. 209 (N.C. 1889).

9 S.E. 139 (Emery v. Raleigh & Gaston Railroad) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Edwards v. Hardin
439 S.E.2d 808 (Court of Appeals of North Carolina, 1994)
Cody v. . England
5 S.E.2d 833 (Supreme Court of North Carolina, 1939)
Oliver v. City of Raleigh
212 N.C. 465 (Supreme Court of North Carolina, 1937)
T. L. Edge v. North State Feldspar Corp.
193 S.E. 2 (Supreme Court of North Carolina, 1937)
Dehart v. . Jenkins
190 S.E. 218 (Supreme Court of North Carolina, 1937)
Chapman-Hunt Co. v. Haywood County Board of Education
150 S.E. 713 (Supreme Court of North Carolina, 1929)
Chicago, R. I. & P. Ry. Co. v. Turner
1929 OK 548 (Supreme Court of Oklahoma, 1929)
Moss v. Best Knitting Mills
130 S.E. 635 (Supreme Court of North Carolina, 1925)
Okmulgee Gas Co. v. Kelly
1924 OK 827 (Supreme Court of Oklahoma, 1924)
State v. . Kincaid
110 S.E. 612 (Supreme Court of North Carolina, 1922)
Shaw v. City of Greensboro
101 S.E. 27 (Supreme Court of North Carolina, 1919)
Williamson v. . Rabon
98 S.E. 830 (Supreme Court of North Carolina, 1919)
Freeman v. Nathan
149 S.W. 248 (Court of Appeals of Texas, 1912)
Lyon v. Chicago, Milwaukee & St. P. Ry. Co.
121 P. 886 (Montana Supreme Court, 1912)
Power Co. v. . Navigation Co.
68 S.E. 190 (Supreme Court of North Carolina, 1910)
Roanoke Rapids Power Co. v. Roanoke Navigation & Water Power Co.
152 N.C. 472 (Supreme Court of North Carolina, 1910)
Rich v. . Morisey
62 S.E. 762 (Supreme Court of North Carolina, 1908)
Davenport v. . R. R.
62 S.E. 431 (Supreme Court of North Carolina, 1908)
Davenport v. Norfolk & Southern & Suffolk & Carolina Railroad Companies
148 N.C. 287 (Supreme Court of North Carolina, 1908)
Eagan v. Central Vermont Railway Co.
69 A. 732 (Supreme Court of Vermont, 1908)