EMC Corp. v. Clearpoint Research Corp.

9 Mass. L. Rptr. 611
CourtMassachusetts Superior Court
DecidedMarch 3, 1999
DocketNo. 932120
StatusPublished

This text of 9 Mass. L. Rptr. 611 (EMC Corp. v. Clearpoint Research Corp.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EMC Corp. v. Clearpoint Research Corp., 9 Mass. L. Rptr. 611 (Mass. Ct. App. 1999).

Opinion

Sosman, J.

Plaintiff EMC Corporation (EMC) brought the present action for breach of contract seeking return of monies it had paid to defendant Clearpoint Research Corporation (CRC). In its amended complaint, EMC has also brought a claim for intentional interference with contractual relations and violation of G.L.c. 93A against defendant Vincent Bono, the president of CRC. Bono has now moved for summary judgment on the ground that, as president and chief executive officer of CRC, he can not be liable [612]*612for intentional interference with EMC’s contract with CRC and that CRC’s breach of the contract was not a violation of G.L.c. 93A. For the following reasons, defendant Bono’s motion is ALLOWED.

Facts

On June 5, 1992, EMC and CRC entered into an agreement whereby CRC agreed to develop certain computer memory products for EMC.1 The Agreement set forth a schedule for the project, specifying certain “milestones” that were to be reached by specified dates over the course of the summer and fall of 1992.

The Agreement also set a payment schedule, which was tied to the achievement of the various milestones, Specifically, EMC agreed to pay CRC $600,000 upon execution of the Agreement, $400,000 upon first gate level model simulation demonstration (which was to be achieved by June 15, 1992), and $500,000 upon each of the next three milestones up to the anticipated September 30, 1992 completion of the development and testing of the memory products in question. The Agreement specified that these scheduled payments to CRC were “(f]or and in consideration of the Development of the Products.” The Agreement also made clear that these scheduled payments were the entire price to be paid:

As the full and sole compensation for all of the work performed by Developer [CRC] under Article II hereof, and all rights, title and interests granted by [CRC] under Articles II and III hereof, EMC shall pay to [CRC] the amount specified in Exhibit B, according to the schedule set forth in Exhibit B. The amounts specified in Exhibit B shall be due and payable only upon delivery of the applicable phase of the work to EMC and acceptance by EMC of that phase of the work as set forth in this Agreement, which acceptance shall not be unreasonably withheld. ■

The Agreement also provided that, in the event CRC failed to achieve a stated milestone on schedule, CRC “shall devote all appropriate resources to this project until it is back on schedule.” CRC agreed that, during the term of the Agreement, it would not “perform any work for any third party which would materially conflict with, or create any material impediment against, [CRC] performance of any active or proposed Project(s) under this Agreement.” If delay in completion of any milestone exceeded certain limits, the Agreement gave EMC the option to terminate the Agreement or to proceed with the Agreement with decreased price or purchase obligations on its part. If EMC elected to terminate the Agreement on account of CRC delay, EMC was to grant CRC an exclusive license to the development products and CRC was to “pay back to EMC all moneys paid by EMC in connection with the milestones set forth above, over a period of one year in four (4) equal payments.” Otherwise, the parties expressly agreed that there would be no liability for incidental or consequential damages for any form of breach (other than breach of the Agreement’s confidentiality provisions).

The Agreement contained an integration clause, specifying that the written agreement was “the complete and exclusive statement of the agreement between the parties and supersedes all prior oral and written communications, agreements, representations, statements, negotiations, and undertakings between the parties relating to the subject matter hereof.” The Agreement also provided that modifications would not be binding unless made in writing and signed by both sides.

The Agreement was executed and the first scheduled payment of $600,000 was made on or about June 5, 1992. The next milestone, to be achieved by June 15, 1992, was not reached by that date. On July 8, 1992, the parties modified the definition for that milestone and changed the payment terms. The milestone, originally defined as a simulation demonstration “of a successful signature analysis for a given set of SCAN vectors (provided by EMC), and demonstration of a read and write memory operation,” was now defined as a “50% random vector success rate (of 10 vectors) at the Behavioral Level Model, and demonstration of a read and write memory operation.” In advance of achieving that modified milestone, EMC agreed to loan $400,000 to CRC “as an advance against” that milestone. The loan was evidenced by a demand promissory note. The $400,000 was advanced to CRC sometime shortly after the parties’ July 8 agreement.

On August 6, 1992, EMC confirmed in writing that CRC had achieved that milestone (as modified). Where the milestone had been achieved, EMC confirmed that “the loan advanced by EMC to Clearpoint in accordance with our amended Agreement is hereby canceled as evidenced by our return of the Note marked ‘Canceled.’ ” CRC in turn formally acknowledged that “the cancellation of the note is in complete fulfillment of EMC’s obligations in connection with the achievement of the second milestone.”

CRC did not achieve any further development milestones, and no further payments were made. On October 29, 1992, EMC wrote to CRC reserving its rights with respect to CRC’s failure to meet the project schedule. On February 10, 1993, EMC wrote to CRC announcing its election to terminate the Agreement and demanding the return of the $1,000,000 previously paid to CRC. Under the Agreement, the amount was to be paid back in four equal installments. Thus, EMC demanded four payments of $250,000, to be made on May 7, 1993, August 7, 1993, November 7, 1993, and February 7, 1994.

On April 13, 1993, EMC filed the present action against CRC seeking a declaratory judgment with respect to the monies allegedly owing and claiming breach of contract and “money owed and due.” On April 21, 1993, EMC obtained a prejudgment attachment against CRC in the amount of $1,020,220.07, [613]*613but was unable to identify or locate any assets of CRC to attach.

On May 4, 1993, EMC filed an amended complaint naming Vincent Bono as a defendant. Bono was, at all relevant times, the president and controlling shareholder of CRC. The amended complaint alleged that Bono, and other unidentified persons at CRC acting under his direction, “diverted up to One Million Dollars ($1,000,000) from the project for purposes other than those contemplated under the Agreement.” The amended complaint then sought to recover from Bono individually for having “intentionally and maliciously interfered with the June 5, 1992 Agreement by apparently diverting up to One Million Dollars ($1,000,000) from the Memory Product Project for purposes other than those contemplated under the terms of the Agreement."

On July 16, 1993, CRC was placed in bankruptcy by way of an involuntary petition. On August 6, 1993, the case was converted to Chapter 11. CRC was ultimately liquidated, and EMC has not received any payment from CRC.

Discussion

1. Intentional interference with contractual relations

EMC contends that the monies paid to CRC were not used exclusively for the development project set forth in the Agreement. It further contends that Bono directed the expenditure of those funds and thereby “diverted” them from the EMC project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whitinsville Plaza, Inc. v. Kotseas
390 N.E.2d 243 (Massachusetts Supreme Judicial Court, 1979)
Sereni v. Star Sportswear Manufacturing Corp.
509 N.E.2d 1203 (Massachusetts Appeals Court, 1987)
Steranko v. Inforex, Inc.
362 N.E.2d 222 (Massachusetts Appeals Court, 1977)
Laurendeau v. Kewaunee Scientific Equipment Corp.
456 N.E.2d 767 (Massachusetts Appeals Court, 1983)
Boothby v. Texon, Inc.
608 N.E.2d 1028 (Massachusetts Supreme Judicial Court, 1993)
Nader v. Citron
360 N.E.2d 870 (Massachusetts Supreme Judicial Court, 1977)
Lexington Insurance v. All Regions Chemical Labs, Inc.
647 N.E.2d 399 (Massachusetts Supreme Judicial Court, 1995)
Massachusetts Employers Insurance Exchange v. Propac-Mass, Inc.
420 Mass. 39 (Massachusetts Supreme Judicial Court, 1995)
Community Builders, Inc. v. Indian Motocycle Associates, Inc.
692 N.E.2d 964 (Massachusetts Appeals Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
9 Mass. L. Rptr. 611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/emc-corp-v-clearpoint-research-corp-masssuperct-1999.