Electric Power Board v. Westinghouse Electric Corp.

716 F. Supp. 1069, 1988 U.S. Dist. LEXIS 17127, 1988 WL 161167
District Court, E.D. Tennessee·Decided August 26, 1988·No. CIV-1-87-93·Published·Cited by 22 cases

Opinion

MEMORANDUM

EDGAR, District Judge.

This is a product liability action in which the plaintiff, Electric Power Board of Chattanooga (hereinafter “EPB”), claims that the defendants manufactured and sold defective electrical equipment to the EPB and that the defective nature of the electrical equipment caused an electrical explosion and fire resulting in extensive property and related damage to the EPB. This Court has jurisdiction over the EPB claims sounding in product liability, including negligence, strict liability and breach of warranty because the parties are diverse. See 28 U.S.C. § 1332.

Presently before the Court are various motions of the defendants for summary judgment. Defendant Westinghouse Electric Corporation (hereinafter “Westinghouse”) has filed a motion for summary judgment asserting the EPB’s claims based on strict liability, negligence and warranty are barred by the applicable Tennessee product liability statutes of repose and limitation, T.C.A. § 29-28-103 and § 47-2-725(2). Defendants Universal Electric Company (hereinafter “Universal”) and Wagner Electric Corporation (hereinafter “Wagner”) have also filed similar motions based generally on these same theories. Defendant Monsanto Company (hereinafter “Monsanto”) has joined in the motion for summary judgment of its co-defendant Wagner and thereby adopts the arguments of Wagner, supplemented with its own specific arguments.

Factual Background

On Monday, September 23, 1985, an explosion occurred in the penthouse vault atop the American National Bank Building in downtown Chattanooga, Tennessee. The explosion occurred during the time an electrical maintenance crew employed by the EPB was performing service work on EPB’s “network” system located in the penthouse vault. Specifically, the equipment being serviced consisted of a “network protector” employed in the system of multiple electrical circuits making up the utility system supplying power to the large bank building. Network protectors are employed to control the flow of electrical power from multiple sources into a single electrical circuit.

The three-man EPB maintenance crew present on September 23, 1985, had monitored the operation of the network protector in the electrical penthouse vault at various times prior to the accident, and determined certain repair work was necessary, specifically, the replacement of certain parts in the network protector. Subsequent to the completion of the repair work, the crew’s foreman placed the just-repaired network protector back into service and the explosion occurred. All three EPB employees on the maintenance crew were severely injured by the explosion and resulting fire, one of whom later died from his injuries. Presently pending in the Circuit Court of Hamilton County, Tennessee is the person *1072 al injury case of the injured and deceased crewmen arising from this accident. The suit in this Court is for property and related damages incurred by the EPB as a result of the explosion. EPB claims these defendants are liable as manufacturers for property damage resulting from the explosion because the network protector and related electrical parts identified as the cause of the explosion were defective and unreasonably dangerous when sold to it. Also a subject of this suit is EPB’s claim against defendants Wagner and Monsanto that two transformers located within the vault and damaged by the explosion were defective and unreasonably dangerous as a result of their discharge of toxic dielectric fluid containing PCB’s. EPB also seeks incidental damages for the costs of repair and clean-up from those defendants, as well as punitive damages against Westinghouse and its fees and costs incurred in prosecuting this suit.

Ten-Year Statute of Limitation and Repose

Defendants collectively assert as undisputed that the EPB purchased the CM-22 Network Protector sometime in 1967, and the explosion giving rise to EPB’s claims occurred in September of 1985. The EPB filed this suit on March 19, 1987 — some twenty years after purchase. Defendants point out that this is well beyond the statutory period of repose which sets a maximum period of time within which claims based on theories of product liability must be brought. Therefore, defendants argue, EPB’s claims arising under the Tennessee Products Liability Act are barred by T.C.A. § 29-28-103(a). 1 Specifically, that section provides, inter alia, that an action must be brought within ten years from the date on which the allegedly defective product was first purchased for use or consumption. T.C.A. § 29-28-103(a). As has been previously held by this Court:

T.C.A. § 23-3703 [now T.C.A. § 29-28-103] is clearly not a conventional statute of limitation based upon the occurrence of an event giving rise to a cause of action. Instead it establishes an absolute limit of ten years from the date a product was sold for use or consumption after which all product liability actions are barred.

Hawkins v. D & J Press Co., 527 F.Supp. 386, 388 (E.D.Tenn.1981) (Wilson, J.).

In its response in opposition to the defendants’ argument that the statute of repose bars its claims against these defendants, EPB asserts that the statute may not bar its warranty claims, which it asserts accrued upon tender or on the date of delivery of the network protector equipment by Westinghouse in 1967. As EPB notes, this argument has been rejected by another judge of this Court in a similar case involving similar legal theories and some of the same parties pending in another division. See Electric Power Board of Chattanooga, et al. v. Monsanto Co., et al., No. CIV-1-85-634, Order (E.D.Tenn. Oct. 27, 1986) (Hull, J.). In that order, the Court held: “the very broad language in Tennessee’s Products Liability Act, § 29-28-102(6), suggests that it includes all possible legal theories which could be pleaded regarding the purchase of a defective or unreasonably dangerous product.” 2 Id. at 2 (emphasis added). An appeal of that order is pending. The Tennessee product liability statute of repose has been consistently upheld against various constitu *1073 tional challenges as a proper exercise of legislative authority to statutorily limit the exposure to liability of product manufacturers and sellers. See Kochins v. Linden-Alimak, Inc., 799 F.2d 1128 (6th Cir.1986); Mathis, 719 F.2d 134 (6th Cir.1983); Hawkins, 527 F.Supp. 386 (E.D.Tenn.1981);

Free access — add to your briefcase to read the full text and ask questions with AI

Electric Power Board v. Westinghouse Electric Corp., 716 F. Supp. 1069, 1988 U.S. Dist. LEXIS 17127, 1988 WL 161167 (E.D. Tenn. 1988).

716 F. Supp. 1069 (Electric Power Board v. Westinghouse Electric Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Frazier v. Breville USA, Inc.
M.D. Tennessee, 2025
Neal Blankenship v. Consolidation Coal Company
850 F.3d 630 (Fourth Circuit, 2017)
Strayhorn v. Wyeth Pharmaceuticals, Inc.
882 F. Supp. 2d 1020 (W.D. Tennessee, 2012)
Evans v. Walter Industries, Inc.
579 F. Supp. 2d 1349 (N.D. Alabama, 2008)
Marksmeier v. McGregor Corp.
722 N.W.2d 65 (Nebraska Supreme Court, 2006)
Otay Land Co. v. U.E. Ltd., L.P.
440 F. Supp. 2d 1152 (S.D. California, 2006)
Ruffing v. Union Carbide Corp.
193 Misc. 2d 350 (New York Supreme Court, 2002)
Rivas v. Safety-Kleen Corporation
119 Cal. Rptr. 2d 503 (California Court of Appeal, 2002)
Greene v. Brown & Williamson Tobacco Corp.
72 F. Supp. 2d 882 (W.D. Tennessee, 1999)
Uniroyal Chem Co Inc v. Deltech Corp
160 F.3d 238 (Fifth Circuit, 1999)
Uniroyal Chemical Co. v. Deltech Corp.
160 F.3d 238 (Fifth Circuit, 1998)
Becton v. Rhone-Poulenc, Inc.
706 So. 2d 1134 (Supreme Court of Alabama, 1997)
A.S.I., Inc. v. Sanders
835 F. Supp. 1349 (D. Kansas, 1993)
Reading Co. v. City of Philadelphia
823 F. Supp. 1218 (E.D. Pennsylvania, 1993)
Spence v. Miles Laboratories, Inc.
810 F. Supp. 952 (E.D. Tennessee, 1992)
Vernon Village, Inc. v. Gottier
755 F. Supp. 1142 (D. Connecticut, 1990)