Elar Investments, Inc. v. Southwest Culvert Co.

676 P.2d 659, 138 Ariz. 25, 38 U.C.C. Rep. Serv. (West) 138, 1983 Ariz. App. LEXIS 635
CourtCourt of Appeals of Arizona
DecidedDecember 1, 1983
DocketNo. 2 CA-CIV 4678
StatusPublished
Cited by3 cases

This text of 676 P.2d 659 (Elar Investments, Inc. v. Southwest Culvert Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elar Investments, Inc. v. Southwest Culvert Co., 676 P.2d 659, 138 Ariz. 25, 38 U.C.C. Rep. Serv. (West) 138, 1983 Ariz. App. LEXIS 635 (Ark. Ct. App. 1983).

Opinion

OPINION

BIRDSALL, Judge.

This appeal arises out of a trial to the court without a jury. The court awarded judgment to the plaintiff-appellee Elar in the net amount of $80,993.67 plus attorneys fees and costs. The “net” amount was the result of damages found for breach of contract less the balance due defendants-appellants on the contract. The damages awarded Elar may be characterized as:

Extended financing charges $41,228.28
Subcontractor’s increased charges 26,554.00
Extra materials purchased 4,443.73
Additional labor costs 19,619.00
$91,845.01

The appellants contracted to supply the appellee with the necessary prefabricated steel for construction of 15 townhome units constituting Phases III and IV of appellee’s development. The total contract price for the steel was $30,926.68.

The appellants contend the judgment for their contract breach should not have included the “extended financing charges” and the subcontractor’s increased charges. They do not contest the increased labor and materials items. They further contend they should have recovered on their counterclaim for “extras” in the amount of $6,129.68.

The appellee has cross-appealed for additional damages claimed to result from a “loss on investment” resulting from delay caused by the appellants’ multiple breaches. . This claim was for $279,528.68.

[27]*27We affirm the judgment of the trial court as entered.

The record contains evidence supporting the following additional facts, all of which were found by the trial court pursuant to request. See Rule 52(a), Rules of Civil Procedure, 16 A.R.S. The appellee ordered all the steel on March 20, 1979, with delivery to be completed by April 10. Such deliveries as were made did not commence until April 11 and were not completed until October 22, 1979, approximately six and one-half months late. There was no compatible, readily available substitute product. The appellants were promptly informed of deficiencies in materials and delivery and assured the appellee corrections would be made. The appellee continued to use the materials in order to mitigate damages.

Although the appellants do not contest the findings of contract breach, we set forth some of those findings because they are helpful in understanding the total picture. We are mindful of the fact that this damage award is three times the contract price. Although the nature of the breach is irrelevant except as it causes the damage, it explains how the delays arose and probably why the trial court did not find that the appellants were entitled to their claimed extras.

“5. The parties agreed that the Super C material; joists, rafters, track, lintels and all material for each unit (town-home) was to be delivered to that unit’s lot or slab in one bundle per unit for ease of construction and assembly, (emphasis in original)
if if % 5¡s í}: *
7. While Defendants’ agent, MITCHELL RECH, assured the Plaintiff that unit delivery would be accomplished, Plaintiff NEVER received any of the steel ordered from the Defendant by the unit (townhome). Delivery was always accomplished by bits and pieces.
8. As a direct result of not delivering the steel in unit bundles, the Plaintiff was forced to move the material all over the project from the time of its delivery until the project was completed or until they needed the materials delivered [e.g., the Defendants delivered joists for virtually all of the units (townhomes) very early in the delivery schedule, and the joists are used last].
9. The Defendants often substituted heavier gauge strapping and material for lighter gauge steel ordered, thereby causing problems with fasteners, strapping, drilling, cutting, and fastening of the steel, as well as attaching dry wall and plywood to the steel.
10. The Defendants delivered steel that was not stamped with the material gauge or its test strength in violation of the ICBO recommendation, and City code.
11. The Defendants delivered, pursuant to contract, screws and fasteners for the material; however, much of the fasteners and screws were improper for the type of material, gauge of material, or the type of fastening that had to be done causing substantial construction problems and in some cases a breakage rate of almost 65%.
12. Plaintiff and Defendants agreed that the tolerances to which the steel would be cut would be + or - lh inch; Defendants’ agent, himself, acknowledged that 20% of the material cut in the plan was in excess of that tolerance, and Plaintiff had to re-cut approximately 50% of the material delivered by Defendants because of improper sizing.
13. Defendants failed to deliver sufficient gusset plates used in conjunction with strapping to complete the units— Defendants delivered plates for 5V2 units as opposed to the 15 units that were ordered.
14. Defendants delivered door and window lintels not cut to length which Plaintiff had to cut or torch on the job.
15. 1,110 pieces of Super C steel delivered by Defendants to Plaintiff did not fit any place in the project or comply with any of the specifications or cut lists.”

The trial court also found that:

“21. The Court finds that it was within the contemplation of the parties that [28]*28failure of the Defendants to perform the contract and deliver the steel in question per specifications and on time would cause delay to Plaintiff’s construction schedule and result in damages.”

Other material facts include that two of the 15 units were still unsold at the time of trial, January 1982, and the other 13 were sold at dates much later than August 1, 1979, the date two expert witnesses, an appraiser and a real estate broker, testified they would have been sold except for the delay. However, the court, in denying the appellee’s claim for “loss of investment,” found that:

“... after the 6V2 month delay the failure to sell Eastern Heights Village Townhomes and consequential loss of income to Plaintiff was caused by the sudden and unanticipated drastic rise in interest rates rather than by Defendants’ breach; and the Court specifically finds that rise in interest rates and its effect on the market was not within the contemplation of the parties at the time they entered into the contract.” [Findings number 23]

The appellant contends that the evidence does not show the “extended financing charges” were within the contemplation of the parties. Since this case involves the sale of goods, it comes under the UCC-A. R.S. § 44-2301, et seq. The provisions of particular importance are:

“§ 44-2393. Buyer’s damages for breach in regard to accepted goods
“§ 44-2394.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Standard Chartered PLC v. Price Waterhouse
945 P.2d 317 (Court of Appeals of Arizona, 1997)
Chestnut Hill Development Corp. v. Otis Elevator Co.
739 F. Supp. 692 (D. Massachusetts, 1990)
ELAR INVESTMENTS v. Southwest Culvert Co.
676 P.2d 659 (Court of Appeals of Arizona, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
676 P.2d 659, 138 Ariz. 25, 38 U.C.C. Rep. Serv. (West) 138, 1983 Ariz. App. LEXIS 635, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elar-investments-inc-v-southwest-culvert-co-arizctapp-1983.