El Paso & Southwestern R. Co. v. Eichel & Weikel

226 U.S. 590, 33 S. Ct. 179, 57 L. Ed. 369, 1913 U.S. LEXIS 2267
CourtSupreme Court of the United States
DecidedJanuary 13, 1913
Docket252
StatusPublished
Cited by7 cases

This text of 226 U.S. 590 (El Paso & Southwestern R. Co. v. Eichel & Weikel) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
El Paso & Southwestern R. Co. v. Eichel & Weikel, 226 U.S. 590, 33 S. Ct. 179, 57 L. Ed. 369, 1913 U.S. LEXIS 2267 (1913).

Opinion

Mr. Justice Pitney

delivered the opinion of the court.

Writ of error sued out under § 709, Rev. Stat., to review a judgment of the Court of Civil Appeals, that being the highest court of the State in which a decision in the suit could be-had,because the Supreme Court of Texas denied a petition for writ of error to review the judgment in that court.

The action was brought by defendants in error in the District Court of El Paso County, Texas, to recover damages for certain alleged breaches of contract committed by the railroad company, now plaintiff in error. Damages were recovered accordingly, and the judgment awarding them was affirmed by the Court of Civil Appeals. 130 S. W. Rep. 922. Whether the jurisdiction of this court is. *592 properly invoked depends upon whether any Federal right or immunity was duly set up or claimed by the plaintiff in error in the state court, and there overruled.

The controversy in suit arose out of a written contract between ihé parties whereby the railroad company, owner of a railroad located in the then Territory of New Mexico, for the purpose of procuring crushed stone ballast from a quarry owned by it and situate in the Territory, agreed to provide a crushing and quarry plant capable of producing 1000 cubic yards of ballast in ten horns, with the necessary appurtenances and equipment, including coal, water,' and railroad cars, and the defendants in error agreed that with and from said plant' they would quarry, crush, prepare and deliver ballast at the rate of 750 cubic yards for each day’s work, at prices fixed by the contract. The contract contained a clause providing that monthly payments to the extent of 90 per centum of the engineer’s estimates should be made to the defendants in error during the progress of the work, with a final payment at the completion of the whole work contemplated, “upon the certificate of. the Company’s Engineer of Maintenance of Way that the Contractor has acceptably discharged all of his obligations under this agreement in conformity to the following specifications.” Also the following, appended to the specifications: “The decision of the Company’s Engineer of Maintenance of Way shall be final and conclusive in any dispute which may arise between the parties to this agreement relative to or touching the same; and each of the parties hereto waives any right of action, suit or suits, or other remedy in law or otherwise, by virtue of the covenants herein, so that the decision of said Engineer of Maintenance of Way shall, in the nature of an award, be final and conclusive on the rights and claims of said parties.”

The plaintiffs, in their petition, set up numerous grounds of action. So far as they were submitted to the jury they • *593 were summarized by the trial judge as follows: Plaintiffs alleged that the defendant failed to furnish a crusher plant of the capacity agreed to be furnished, that the plant actually furnished was of much less capacity, and that instead of furnishing coal and water of a quality reasonably sufficient and suitable , for the purpose of operating the plant and quarry, the defendant furnished coal and water entirely unsuitable for that purpose; that by reason of the incapacity of the plant and the unsuitability of the coal and water, plaintiffs were prevented from producing the quantity of ballast required by the contract, and which they had a right to produce and would have produced but for the defendant’s alleged defaults; that the cost of the ballast actually produced was greatly enhanced by reason of said defaults, -and plaintiffs were finally compelled to shut down, and abandon their contract; wherefore they sought to recover the retained ten per cent., certain penalties that had been exacted under the terms of the contract for failure to produce ballast, and-certain freight charges against them deducted by defendant for goods transported over its own line; and also to recover for the enhanced cost of production of the ballast actually produced and for the profits which they alleged they would have made under the contract if it had been fairly performed by the defendant.

The defense, so far as now pertinent, was, that the contract was made and intended to be performed in the then Territory of New Mexico and was made with reference to the laws in force therein, and that there was in that Territory, at the time of the making of the contract and at the time of the suit, “a certain non-statutóry and unwritten law, to the effect that agreements such as those herein specially referred to (meaning the agreement respecting the arbitrament, of the engineer), are valid and binding, and that neither of the parties to such contract and agreement has any right of action in a cause based *594 thereon, but must rely for a decision of such rights and claims on the determination thereof by such engineer.”

This defense was set up by exceptions to the plaintiffs’ petition, and by special pleas thereto. The cause proceeded to trial, whereupon the defendant introduced, for the purpose of showing the laws of New Mexico at the time the contract was made, certain decisions of this court, to wit: Kihlberg v. United States, 97 U. S. 398; Sweeney v. United States, 109 U. S. 618; Martinsburg & Potomac R. Co. v. March, 114 U. S. 549; Chicago, Santa Fe &c. R. Co. v. Price, 138 U. S. 185; United States v. Robeson, 9 Pet. 319, 327; United States v. Gleason, 175 U. S. 588; Mercantile Trust Co. v. Hensey, 205 U. S. 298.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graco Robotics, Inc. v. Oaklawn Bank
914 S.W.2d 633 (Court of Appeals of Texas, 1996)
Traweek v. City and County of San Francisco
659 F. Supp. 1012 (N.D. California, 1986)
Moye v. North Carolina
283 U.S. 810 (Supreme Court, 1931)
Blum Milling Co. v. Moore-Seaver Grain Co.
277 S.W. 78 (Texas Commission of Appeals, 1925)
New York Ex Rel. Rosevale Realty Co. v. Kleinert
268 U.S. 646 (Supreme Court, 1925)
Manhattan Life Ins. Co. of NY v. Cohen
234 U.S. 123 (Supreme Court, 1914)
Forrest City Box Co. v. Sims
208 F. 109 (Eighth Circuit, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
226 U.S. 590, 33 S. Ct. 179, 57 L. Ed. 369, 1913 U.S. LEXIS 2267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/el-paso-southwestern-r-co-v-eichel-weikel-scotus-1913.