E.I. Du Pont De Nemours and Company, Inc. v. United States

365 F.3d 1367, 58 ERC (BNA) 1321, 2004 U.S. App. LEXIS 8368, 2004 WL 899979
CourtCourt of Appeals for the Federal Circuit
DecidedApril 28, 2004
Docket03-5137
StatusPublished
Cited by19 cases

This text of 365 F.3d 1367 (E.I. Du Pont De Nemours and Company, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E.I. Du Pont De Nemours and Company, Inc. v. United States, 365 F.3d 1367, 58 ERC (BNA) 1321, 2004 U.S. App. LEXIS 8368, 2004 WL 899979 (Fed. Cir. 2004).

Opinion

MICHEL, Circuit Judge.

E.I. DuPont de Nemours & Co., Inc. (“DuPont”) instituted this Contract Disputes Act action to recover costs it incurred pursuant to the Comprehensive Environmental Response Compensation and Liability Act (“CERCLA”) for an ordnance plant it built and operated for the government during World War II. On the parties’ cross-motions for summary judgment, the United States Court of Federal Claims entered judgment for the government. E.I. Dupont De Nemours & Co. v. United States, 54 Fed. Cl. 361 (2002). The trial court correctly held that the government had agreed to indemnify DuPont for the costs at issue. Id. at 369. It erred, however, in concluding that a predecessor to the Anti-Deficiency Act, current version at 31 U.S.C. § 1341 (2000), bars DuPont’s recovery. Id. at 372. Accordingly, we reverse the judgment in favor of the government and remand for a determination of damages and entry of judgment in favor of DuPont.

BACKGROUND

In 1940, the government commissioned DuPont to construct and operate a plant in Morgantown, West Virginia, to produce chemicals for the government’s use in producing munitions for World War II. The contract at issue, Contract No. W-ORD-490, entered into on November 28, 1940 (the “MOW 1 Contract”), provided that DuPont would acquire the site for the plant and design, construct, and operate it in exchange for reimbursement of its costs plus a fixed fee. The government would own the plant and all of its production.

The cost reimbursement provision of the MOW Contract (“Reimbursement Clause” 2 ) provided as follows:

1. The Contractor shall be reimbursed in the manner hereinafter described for such of its actual expenditures in the performance of the work under this contract, heretofore or hereafter incurred, as may be approved or ratified by the Contracting Officer and as are included in the following items:
k. Losses, expenses, and damages, not compensated by insurance or otherwise (including settlements made with the written consent of the Contracting *1370 Officer), actually sustained by the Contractor in connection with the work and found and certified by the Contracting Officer as not having resulted from personal failure on the part of the corporate officers of the Contractor or of other representatives of the Contractor having supervision and direction of the operation of the plant as a whole, to exercise good faith or that degree of care which they normally exercise in the conduct of the Contractor’s business.

MOW Contract, Article IV-A(l)(k). The MOW Contract also included the following indemnification provision (“Indemnification Clause”):

8. It is the understanding of the parties hereto, and the intention of this contract, that all work under this Title III is to be performed at the expense of the Government and that the Government shall hold [DuPont] harmless against any loss, expense (including expense of litigation), or damage (including damage to third persons because of death, bodily injury or property injury or destruction or otherwise) of any kind whatsoever arising out of or in connection with the performance of the work under this Title III, except to the extent that such loss, expense, damage or liability is due to the personal failure on the part of the corporate officers of [DuPont], or of other representatives of [DuPont] having supervision or direction of the operation of the plant as a whole, to exercise good faith or that degree of care which they normally exercise in the conduct of [DuPont’s] business.

MOW Contract, Article III-A(8).

In 1946, the government terminated the MOW Contract and entered into a supplemental agreement with DuPont (the “Termination Supplement”). Neither DuPont nor the government was able to locate a copy of the Termination Supplement, but the trial court credited DuPont’s evidence 3 that the Termination Supplement included the following provisions:

(c) Upon payment of said sum of $ [_] as aforesaid, all rights and liabilities of the parties under the Contract and under the Act, 4 insofar as it pertains to the Contract, shall cease and be forever released except:
(3) Claims by [DuPont] against the Government which are based upon responsibility of [DuPont] to third parties and which involve costs reimbursable under the contract, but which are not now known to [DuPont].
(7) All rights and liabilities of the parties under the contract articles, if any, applicable to options (except options to continue or increase the work under the Contract), covenants not to compete, covenants of indemnity, and agreements with respect to the future care and disposition by [DuPont] of Government- *1371 owned facilities remaining in his custody.

Termination Supplement, Articles 4(c)(3) (the “Unknown Claims Clause”) & 4(c)(7) (the “Preservation of Indemnity Clause”), respectively. The government does not challenge the trial court’s finding that the Termination Supplement included these provisions.

The United States Environmental Protection Agency (“EPA”) notified DuPont in 1984 that it was proposing to list the MOW site on the National Priorities List for clean-up pursuant to CERCLA. 5 Ultimately, on April 20, 1990, DuPont (and several other potentially responsible parties) 6 agreed, pursuant to a consent order with EPA, to conduct a remedial investigation and feasibility study regarding the site. DuPont incurred $1,322,334.88 in attorney and consulting fees as a result.

After DuPont received no response to the claim it filed pursuant to the Contract Disputes Act, 41 U.S.C. §§ 601-613 (2000), with the Contracting Officer for the Army Corps of Engineers to recover its CERC-LA-related costs in 1993, and after its subsequent negotiations with the government failed, DuPont filed the present action.

On cross-motions for summary judgment on the- issue of liability, the trial court found, as noted above, that the Termination Supplement included the above-quoted Unknown Claims 7 and Preservation of Indemnity Clauses. DuPont, 54 Fed. Cl. at 365, 367. It held, further, that both the Indemnification and Reimbursement Clauses in the MOW Contract “were drafted broadly enough to be properly interpreted to place the risk of unknown liabilities on the government, including liability for costs incurred pursuant to CERCLA.” Id. at 369. The trial court concluded, nonetheless, that recovery was barred by the Anti-Deficiency Act, 31 U.S.C. §

Related

Oxy USA, Inc. v. United States
Federal Claims, 2022
Joseph Pakootas v. Teck Cominco Metals, Ltd.
905 F.3d 565 (Ninth Circuit, 2018)
Peoples Gas Light and Coke Com v. Beazer East Inc.
802 F.3d 876 (Seventh Circuit, 2015)
Shell Oil Company v. United States
751 F.3d 1282 (Federal Circuit, 2014)
Shell Oil Company v. the United States 06-141c & 0
108 Fed. Cl. 422 (Federal Claims, 2013)
Lublin Corp. v. United States
98 Fed. Cl. 53 (Federal Claims, 2011)
Shell Oil Co. v. United States
93 Fed. Cl. 439 (Federal Claims, 2010)
Insurance Co. of North America v. District of Columbia
948 A.2d 1181 (District of Columbia Court of Appeals, 2008)
Williams v. District of Columbia
902 A.2d 91 (District of Columbia Court of Appeals, 2006)
Westfed Holdings, Inc. v. United States
407 F.3d 1352 (Federal Circuit, 2005)
Ford Motor Company v. United States
378 F.3d 1314 (Federal Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
365 F.3d 1367, 58 ERC (BNA) 1321, 2004 U.S. App. LEXIS 8368, 2004 WL 899979, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ei-du-pont-de-nemours-and-company-inc-v-united-states-cafc-2004.