E.B. Roberts Construction Co. v. Concrete Contractors, Inc.

704 P.2d 859, 1985 Colo. LEXIS 479
CourtSupreme Court of Colorado
DecidedAugust 19, 1985
Docket83SC63
StatusPublished
Cited by54 cases

This text of 704 P.2d 859 (E.B. Roberts Construction Co. v. Concrete Contractors, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E.B. Roberts Construction Co. v. Concrete Contractors, Inc., 704 P.2d 859, 1985 Colo. LEXIS 479 (Colo. 1985).

Opinion

LOHR, Justice.

We granted certiorari to review the judgment of the Colorado Court of Appeals in Concrete Contractors, Inc. v. E.B. Roberts Construction Co., 664 P.2d 722 (Colo.App.1982), a case arising out of a project to construct a K-Mart store in Brighton, Colorado. The Adams County District Court awarded damages to Concrete Contractors, Inc. (CCI) and Ideal Construction Service, Inc. (Ideal) against E.B. Roberts Construction Co. (Roberts), the general contractor, in the amount of $28,031 for work performed under a subcontract, and additional damages of $8,941 for profits lost when Roberts wrongfully terminated the subcontract. The trial court also decreed that the plaintiffs had a mechanic’s lien in the amount of $28,031 based on the work performed. Roberts appealed, and the court of appeals affirmed. We granted certiorari to determine whether CCI and Ideal forfeited all rights to a mechanic’s lien by wrongfully filing a lien statement for an amount exceeding the amount due. See §§ 38-22-123, -128, 16A C.R.S. (1982). We also elected to review on certiorari whether CCI, which was not a party to the written subcontract between Ideal and Roberts, could enforce the subcontract when CCI performed the work to be accomplished by Ideal pursuant to that agreement. We affirm the judgment.

I.

Roberts was hired as the general contractor on a project to build a K-Mart store in Brighton, Colorado. The store was to be constructed on land owned by C & W Manhattan Associates and encumbered by a deed of. trust in favor of the Allied Bank of Texas.

On April 30, 1979, Roberts and CCI entered into a $224,410 lump-sum contract which obligated CCI, as a subcontractor, to perform the site concrete, building foundation, and asphalt paving work on the K-Mart project. CCI earlier had submitted to Roberts a bid proposal to do this and other work, in which CCI estimated unit prices for the various components of the job.

One provision of the contract obligated CCI to furnish a performance bond guaranteeing to Roberts and the Allied Bank that CCI would perform the contract, and a payment bond guaranteeing to Roberts and the Allied Bank that all of CCI’s subcontractors, laborers and material suppliers would be paid. CCI could not obtain the necessary bonds. On June 15, 1979, Roberts, CCI and Ideal entered into a “Contract Amendment” whereby Ideal was substituted for CCI as the subcontractor in the April 30 contract. Ideal was able to acquire the necessary bonds, and they were executed on June 15 with The Continental Insurance Company as surety.

Harold Baumgartner testified that he was the owner and chief executive of CCI and a vice president of Ideal and that Ideal was a separate corporation from CCI. Baumgartner further testified that “we [CCI] occasionally run a job through that company [Ideal] for our higher-sized bonds.” There is no other evidence in the record concerning the relationship between Ideal and CCI or the identity of the owners or officers of these corporations.

The record also is barren of any evidence of a formal agreement between Ideal and CCI, or among Ideal, CCI and Roberts, that *862 CCI would perform the concrete and asphalt work on the K-Mart project as required by the contract. Nevertheless, that is what the parties contemplated and that is what happened. Despite the fact that Ideal had been substituted for CCI as the subcontractor, CCI performed the work, billed Roberts for progress payments, and received such payments from Roberts. 1 In matters concerning the administration and progress of the job, CCI personnel dealt with Roberts personnel and vice versa. It is apparent from the record that, from the first, the relevant parties knew that CCI would be performing the subcontract work and all parties acted accordingly. The trial judge so found. Nothing in the written contract or the bonds, however, gives any indication of this arrangement.

CCI began work on the K-Mart project in July of 1979. CCI completed the building foundation and almost all of the site concrete work but did not begin the asphalt paving of the parking lot. In return, CCI received progress payments from Roberts. Roberts terminated the contract by telegram to Baumgartner on December 10, 1979, asserting that the subcontractor had breached the contract by failing to perform in a timely manner.

On January 28, 1980, CCI presented Roberts with a final invoice for $66,407.02, ostensibly representing the balance due for all work performed prior to termination of the contract. On February 26, CCI and Ideal jointly recorded a mechanic’s lien statement in the office of the Adams County recorder, asserting a claim against the property in the amount of $66,407.02 for “labor and materials furnished and supplied.” See §§ 38-22-101 to -133, 16A C.R.S. (1982 & 1984 Supp.) (general mechanics’ lien statute).

In May of 1980, CCI and Ideal filed suit against Roberts, C & W Manhattan Associates, the Allied Bank and others, seeking to foreclose the mechanic’s lien. The plaintiffs also asked for $66,407.02 in damages, plus interest and costs, for materials and labor supplied but not paid for by Roberts. The plaintiffs subsequently amended the complaint by adding a second claim against Roberts alone for breach of contract, seeking $25,000 in damages, plus interest and costs, representing profits lost because Roberts wrongfully terminated the contract. Roberts counterclaimed, asserting that the plaintiffs had breached the contract by failure to render timely and workmanlike performance and failure to pay a material supplier. 2

Trial was to the court on January 21-23, 1981. At trial, the plaintiffs submitted their final summary of the amount due, totalling $49,992.40 allegedly owed by Roberts. According to Baumgartner, this figure included the amount due for unpaid work performed (the mechanic’s lien claim) and the amount due for lost profits on work not performed (the breach of contract claim).

The district court issued a written order on April 3, 1981, containing findings of fact and conclusions of law. The court found that Roberts breached the contract when it terminated CCI, and awarded the plaintiffs $8,941 in damages, plus interest, representing profits lost because CCI was not allowed to perform the balance of the work required by the contract. The court also awarded the plaintiffs judgment against Roberts in the amount óf $28,031, plus interest, representing the balance due for work performed by CCI and not paid for by Roberts, and decreed a lien on the property in favor of the plaintiffs in that amount. Roberts and the other defendants appealed. The court of appeals affirmed the particular rulings relevant here. Concrete Contractors, Inc. v. E.B. Roberts Construction Co., 664 P.2d at 724-25.

On certiorari, Roberts and other defendants in the trial court (for convenience, *863

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jim Black v. Coleman
Colorado Court of Appeals, 2025
Bewley v. Semler
2018 CO 79 (Supreme Court of Colorado, 2018)
Baker v. Wood, Ris & Hames, Professional Corp.
2016 CO 5 (Supreme Court of Colorado, 2016)
Matthys v. Narconon Fresh Start
104 F. Supp. 3d 1191 (D. Colorado, 2015)
Byerly v. Bank of Colo.
411 P.3d 732 (Colorado Court of Appeals, 2013)
Gorsuch, Ltd. v. Wells Fargo National Bank Ass'n
830 F. Supp. 2d 1202 (D. Colorado, 2011)
DeFranco v. Storage Technology Corp.
622 F.3d 1296 (Tenth Circuit, 2010)
Cody Park Property Owners' Ass'n v. Harder
251 P.3d 1 (Colorado Court of Appeals, 2010)
Lane v. Urgitus
145 P.3d 672 (Supreme Court of Colorado, 2006)
East Meadows Co. v. Greeley Irrigation Co.
66 P.3d 214 (Colorado Court of Appeals, 2003)
Bob Blake Builders, Inc. v. Gramling
18 P.3d 859 (Colorado Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
704 P.2d 859, 1985 Colo. LEXIS 479, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eb-roberts-construction-co-v-concrete-contractors-inc-colo-1985.