Jim Black v. Coleman

CourtColorado Court of Appeals
DecidedNovember 26, 2025
Docket24CA0080
StatusUnpublished

This text of Jim Black v. Coleman (Jim Black v. Coleman) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jim Black v. Coleman, (Colo. Ct. App. 2025).

Opinion

24CA0080 Jim Black v Coleman 11-26-2025

COLORADO COURT OF APPEALS

Court of Appeals No. 24CA0080 Jefferson County District Court No. 22CV30319 Honorable Ryan P. Loewer, Judge

Jim Black Construction, Inc.,

Plaintiff-Appellee,

v.

Derek Coleman,

Defendant-Appellant.

JUDGMENT AFFIRMED IN PART AND VACATED IN PART

Division I Opinion by JUDGE J. JONES Grove and Schutz, JJ., concur

NOT PUBLISHED PURSUANT TO C.A.R. 35(e) Announced November 26, 2025

Wilson Elser Moskowitz Edelman & Dicker LLP, Ryan A. Williams, Gabrielle Lalonde, Denver, Colorado; Mark Champoux, Daniel A. Richards, Nicholas R. Peppler, Denver, Colorado, for Plaintiff-Appellee

Thomas P. Howard, LLC, Thomas P. Howard, Scott E. Brenner, Sam Thomas, Louisville, Colorado, for Defendant-Appellant ¶1 Defendant, Derek Coleman, appeals the trial court’s judgment

in favor of plaintiff, Jim Black Construction, Inc. (Jim Black), on its

claims for foreclosure of a mechanic’s lien, breach of contract,

unjust enrichment, and promissory estoppel. We affirm the part of

the judgment on the mechanic’s lien foreclosure and breach of

contract claims and vacate the part of the judgment on the unjust

enrichment and promissory estoppel claims.

I. Background

¶2 Late one night, a fire broke out in Coleman’s home, causing

significant damage. While firefighters were putting out the fire,

representatives from Jim Black met with Coleman in his front yard.

That night, Coleman and Jim Black agreed that Jim Black would

stabilize Coleman’s house to mitigate further damage. Two days

later, Coleman went to Jim Black’s office and engaged the company

to restore Coleman’s house to its pre-fire condition. During this

meeting, Coleman signed two contracts: (1) a restoration “Proposal”

(Proposal), which provided that Jim Black would supply labor and

materials for the project; and (2) a “Work Authorization and

Direction to Pay” (Work Authorization), which, among other things,

allowed Jim Black to begin the restoration process as authorized by

1 either Coleman or his insurance company. With the agreements

signed, Jim Black started restoring the property.

¶3 Shortly thereafter, Cogdill Consulting (Cogdill), a third party

working with Coleman’s insurance company, created an estimate

for the project. Jim Black agreed to Cogdill’s estimate and referred

to it throughout the restoration process.

¶4 Several months into the project, Coleman asked Jim Black to

change parts of the house’s pre-fire architectural design, and Jim

Black subsequently added those changes to its restoration plan. To

comply with Coleman’s request, Jim Black had to obtain new bids

from subcontractors and new estimates for the cost of repair, all of

which slowed down the restoration project. As a result of the

slowdown, Coleman became dissatisfied and terminated Jim Black

about twenty months into the project.

¶5 After being terminated, Jim Black sent Coleman its final

invoice for the project, totaling $166,857.44. The invoiced amount

was based on Cogdill’s estimate, a change order sent to Coleman by

Jim Black, and various invoices from Jim Black’s subcontractors.

When Coleman received the invoice, he emailed Jim Black asserting

that there were “a lot of things that [Jim Black] charged more than

2 once.” Jim Black representatives offered to meet with Coleman to

discuss the alleged duplicate charges, but Coleman didn’t respond

to the requests. After it didn’t hear from Coleman or receive

payment, Jim Black filed a mechanic’s lien against Coleman’s

property for the final invoice amount. Jim Black then filed suit

against Coleman, asserting claims for foreclosure of the lien, breach

of contract, unjust enrichment, and promissory estoppel. Coleman

asserted counterclaims for breach of contract, promissory estoppel,

fraud, negligent misrepresentation, and recording of an excessive

lien.

¶6 During discovery, Jim Black found a duplicate charge of

$2,160 in its initial billing, which related to engineering fees (an

accounting error) and reduced the claimed lien by that amount,

plus 10% profit and 10% overhead fees (for a total of $2,592),

resulting in a new total of $164,265.44.

¶7 Following a bench trial, the court found in Jim Black’s favor

on all of its claims and all of Coleman’s counterclaims. The court

ordered Coleman to pay Jim Black $164,265.44 (the revised

amount), plus interest, costs of enforcement, and attorney fees.

3 Coleman only appeals the portion of the judgment on Jim Black’s

claims.

II. Discussion

¶8 Coleman contends the trial court erred by (1) finding that he

failed to prove that Jim Black’s mechanic’s lien was excessive; (2)

finding that the lien, as recorded, included only $2,592 in excess

charges; (3) failing to enforce the provision in the Proposal

addressing changes to the scope of the work; and (4) entering

judgment in Jim Black’s favor on its unjust enrichment and

promissory estoppel claims. We reject Coleman’s first three

contentions but agree with the fourth.

A. Application of the Mechanic’s Lien Statute

¶9 Coleman initially contends that the trial court applied an

incorrect legal standard in determining whether Jim Black’s

mechanic’s lien was excessive and clearly erred by finding that Jim

Black didn’t know that its lien was excessive when recorded. We

disagree with both contentions.

4 1. Correct Legal Standard

a. Standard of Review and Applicable Law

¶ 10 We review the trial court’s interpretation of the mechanic’s lien

statutes de novo. Galiant Homes, LLC v. Herlik, 2025 COA 3, ¶ 22;

Sure-Shock Elec., Inc. v. Diamond Lofts Venture, LLC, 2014 COA 111,

¶ 8.

¶ 11 Section 38-22-128, C.R.S. 2025, governs forfeiture of a

mechanic’s lien when a claimant files a lien for an amount greater

than what’s due. “The intent of section 38-22-128 is to punish and

deter those who abuse the mechanic’s lien statute by knowingly

and intentionally claiming excess amounts . . . .” Honnen Equip.

Co. v. Never Summer Backhoe Serv., Inc., 261 P.3d 507, 510 (Colo.

App. 2011). Thus, a party asserting that a mechanic’s lien is

excessive within the meaning of the statute must show that (1) the

lien amount exceeds what was due when the lien was recorded; (2)

there was no reasonable possibility that the amount of the lien was

then due; and (3) the lien claimant knew that the amount claimed

was greater than the amount due. § 38-22-128; see Honnen Equip.

Co., 261 P.3d at 510 (citing LSV, Inc. v. Pinnacle Creek, LLC, 996

P.2d 188, 192 (Colo. App. 1999)).

5 b. Analysis

¶ 12 Coleman argues that while “the court began by applying the

correct legal standard,” it ultimately applied an erroneous standard

by finding that Jim Black didn’t have any reason to believe that

there was an accounting error in the final invoice (concerning the

duplicate charge of $2,592 for engineering fees). But the court

made that finding expressly in the context of determining whether

Jim Black knew that the amount claimed was greater than the

amount actually owed — one of three elements of an excessive lien

claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James H. Moore & Associates Realty, Inc. v. Arrowhead at Vail, Inc.
892 P.2d 367 (Colorado Court of Appeals, 1994)
E.B. Roberts Construction Co. v. Concrete Contractors, Inc.
704 P.2d 859 (Supreme Court of Colorado, 1985)
O'Reilly v. Physicians Mutual Insurance Co.
992 P.2d 644 (Colorado Court of Appeals, 1999)
Honnen Equipment Co. v. Never Summer Backhoe Service, Inc.
261 P.3d 507 (Colorado Court of Appeals, 2011)
JW CONST. CO., INC. v. Elliott
253 P.3d 1265 (Colorado Court of Appeals, 2011)
Rush Creek Solutions, Inc. v. Ute Mountain Ute Tribe
107 P.3d 402 (Colorado Court of Appeals, 2004)
Ad Two, Inc. v. City & County of Denver
9 P.3d 373 (Supreme Court of Colorado, 2000)
In re Estate of Owens
2017 COA 53 (Colorado Court of Appeals, 2017)
People v. Rediger
2018 CO 32 (Supreme Court of Colorado, 2018)
Carousel Farms Metro. Dist. v. Woodcrest Homes, Inc.
2019 CO 51 (Supreme Court of Colorado, 2019)
Ins. v. Dakota Station II
2021 COA 114 (Colorado Court of Appeals, 2021)
East Ridge of Fort Collins, LLC v. Larimer & Weld Irrigation Co.
109 P.3d 969 (Supreme Court of Colorado, 2005)
Federal Deposit Insurance Corp. v. Fisher
2013 CO 5 (Supreme Court of Colorado, 2013)
Bachelor Gulch Operating Co. v. Board of County Commissioners
2013 COA 46 (Colorado Court of Appeals, 2013)
People v. Fordyce
705 P.2d 8 (Colorado Court of Appeals, 1985)
Wigham Excavating Co. v. Colorado Federal Savings & Loan Ass'n
796 P.2d 23 (Colorado Court of Appeals, 1990)
LSV, Inc. v. Pinnacle Creek, LLC
996 P.2d 188 (Colorado Court of Appeals, 1999)
Target Corp. v. Prestige Maintenance USA, Ltd.
2013 COA 12 (Colorado Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Jim Black v. Coleman, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jim-black-v-coleman-coloctapp-2025.