Concrete Contractors, Inc. v. E.B. Roberts Construction Co.

664 P.2d 722
CourtColorado Court of Appeals
DecidedMay 23, 1983
Docket81CA1079
StatusPublished
Cited by7 cases

This text of 664 P.2d 722 (Concrete Contractors, Inc. v. E.B. Roberts Construction Co.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Concrete Contractors, Inc. v. E.B. Roberts Construction Co., 664 P.2d 722 (Colo. Ct. App. 1983).

Opinion

COYTE, Judge.

Defendants, E.B. Roberts Construction Co. (Roberts), C & W Manhattan Associates (C & W), Roland Walters, Allied Bank of Texas, and K-Mart Corporation, appeal the judgment of the trial court awarding plaintiffs, Concrete Contractors, Inc. (CCI), and Ideal Construction Service, Inc. (Ideal), damages for defendants’ breach of contract and determination that plaintiffs were entitled to a lien upon the subject property. We affirm in part and reverse in part.

Defendants C & W and Roland Walters, trustee, were owners of real property in Brighton, Colorado, on which there was a deed of trust in favor of Allied Bank of Texas. They entered into a contract with Roberts for the construction of a K-Mart store on the subject property. Roberts, as general contractor, then entered into a subcontract with CCI for the performance of concrete and paving work on the project. However, CCI was unable to obtain the necessary performance bonds as required by Roberts. Roberts, CCI, and Ideal then entered into a written amendment to the contract in which it was stated that Ideal was substituted for CCI in the original contract. On the date of the amendment, Ideal obtained a performance bond from defendant Continental Insurance Company in favor of defendants Roberts and Allied Bank of Texas guaranteeing Ideal’s performance.

Roberts began work on the project in early July 1979. CCI performed most of the concrete work, having purchased concrete from defendant Mobile Premix Concrete, Inc., for that purpose. However, CCI did not complete the paving work. On December 10, 1979, Roberts notified CCI that it viewed CCI as having breached the con *724 tract and therefore terminated CCI from any further performance under the contract. Roberts thereafter secured a substitute contractor to complete the contract.

Plaintiffs originally brought an action to foreclose their mechanic’s lien in the amount of $66,407.02 which had been filed on February 26, 1980. All of the defendants bringing this appeal filed an answer and counterclaim in which they alleged that plaintiffs had breached their contract in that they had not performed in a timely fashion or in a workmanlike manner and had failed to pay defendant Mobile Premix Concrete, Inc. Defendant Mobile Premix responded by filing a counterclaim against plaintiffs and a cross-claim to foreclose its own mechanic’s lien as well as a cross-claim against defendant Continental Insurance Company for the value of materials supplied to plaintiff for which it had not been paid. Defendants Roberts and Allied Bank of Texas later filed a cross-claim against defendant Continental Insurance Company on Ideal’s performance bond. Plaintiffs then added a claim against defendant Roberts only for breach of contract.

Prior to trial, the court entered a stipulated judgment in favor of Mobile Premix against plaintiffs and Continental Insurance Company and ordered that the property be subject to a mechanic’s lien in the amount of $66,486.92. Following trial to the court, the court entered judgment in favor of plaintiffs against Roberts in the amount of $28,031 for the balance due on the work completed and $8,941 for lost profits on the breach of contract claim, ordered that plaintiffs had a lien on the property in the amount of $28,031, and dismissed appellants’ counterclaim. On appellants’ motion for a new trial, the court ordered that plaintiffs’ mechanic’s lien be merged with the prior judgment awarded to Mobile Premix and that any payment thereon to Mobile Premix would be deemed a payment to plaintiffs.

I

Appellants first contend that the trial court should have extinguished plaintiffs’ mechanic’s lien claim. They assert basically two reasons for this contention. First, that because the plaintiffs knew that the amount of the lien stated in the lien statement filed February 26, 1980, was far in excess of any reasonable claim for the value of labor and materials provided, the lien must be extinquished pursuant to § 38-22-128, C.R.S.1973 (1981 Cum.Supp.). Secondly, they contend plaintiffs included lost profit in the lien statement thereby making the claim excessive and forfeiting all of their rights to any lien.

Section 38-22-128, C.R.S.1973 (1982 Repl. Vol. 16A) provides as follows:

“Any person who files a lien under this article for an amount greater than is due without a reasonable possibility that said amount claimed is due and with the knowledge that said amount claimed is greater than that amount due, and that fact is shown in any proceeding under this article, shall forfeit all rights to such lien plus such person shall be liable to the person against whom the lien was filed in an amount equal to the costs and all attorneys fees.”

That statute was added to the general mechanics’ lien article in 1975. At that time the General Assembly did not repeal the existing statute dealing with allegedly excessive mechanic’s lien statements which was contained in § 38-22-123, C.R.S.1973 (1982 Repl.Vol. 16A). That statute provides in part as follows:

“[I]f any person files either of said statements for a lien for a larger sum than is due or to become due, in fact, or in probability, as the case may be, with intent to cheat or defraud any other person, and that fact appears in any proceeding under this article, such person shall forfeit all rights to such lien under this article.”

Because these statutes relate to the same subject and are in pari materia, we must construe the statutes together and reconcile the provisions, giving effect to each. Buck v. District Court, 199 Colo. 344, 608 P.2d 350 (1980). Before a mechanic’s lien may be extinquished pursuant to these statutes it must first be shown that there is *725 no reasonable probability that the amount claimed is due. Only then does the question of the lien claimant’s state of mind arise. The “cheat or defraud” standard in § 38-22-123 encompasses the “knowledge” standard in § 38-22-128. If a person intends to cheat or defraud someone regarding the amount of a mechanic’s lien, he would necessarily have to have had knowledge that the amount was in error. Thus, the standard to be applied is both knowledge and intent to cheat or defraud.

In ruling on this issue, the trial court found that, although the amount of the lien claimed in the lien statement was in excess of that actually awarded by the court, it was not excessive and thus denied the motion for discharge of the lien. The record supports the conclusion that there was no intent to cheat or defraud.

II

Appellants next contend that the trial court erred in awarding any damages to either CCI or Ideal on the basis of breach of contract. This argument is based on the premise that CCI was not a party to the final contract, Ideal having been substituted for CCI in the original contract, and that Ideal, the only party with standing to sue on the contract, admittedly suffered no damages. We disagree.

It is true that following the amendment of the contract Ideal and Roberts were the only parties to the contract as written. However, where a contract is made for the benefit of a third party, that third party has an interest and a right of action in the contract. Sanders v. Black, 136 Colo. 417, 318 P.2d 1100

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gorsuch, Ltd. v. Wells Fargo National Bank Ass'n
830 F. Supp. 2d 1202 (D. Colorado, 2011)
Murray v. Crawford
689 F. Supp. 2d 1289 (D. Colorado, 2010)
East Meadows Co. v. Greeley Irrigation Co.
66 P.3d 214 (Colorado Court of Appeals, 2003)
E.B. Roberts Construction Co. v. Concrete Contractors, Inc.
704 P.2d 859 (Supreme Court of Colorado, 1985)
Downing v. Travelers Insurance
691 P.2d 375 (Idaho Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
664 P.2d 722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/concrete-contractors-inc-v-eb-roberts-construction-co-coloctapp-1983.