EASTERN DREDGING & CONSTR. v. Parliament House
This text of 698 So. 2d 102 (EASTERN DREDGING & CONSTR. v. Parliament House) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
EASTERN DREDGING & CONSTRUCTION, INC.
v.
PARLIAMENT HOUSE, L.L.C., and Bagby Elevator Company, Inc.
EASTERN DREDGING & CONSTRUCTION, INC., and Berkston Insurance A.V.V.
v.
PARLIAMENT HOUSE, L.L.C.
Supreme Court of Alabama.
Kenneth Lee Cleveland of Coretti, Newsom, Cleveland, Hawkins & Cleveland, Birmingham, for appellants.
F. Timothy McAbee, Birmingham, for Parliament House, L.L.C.
HOOPER, Chief Justice.
Parliament House, L.L.C., the operator of a hotel, is the defendant in these two cases appealed from the Jefferson Circuit Court. The cases involve the renovation of the hotel by Eastern Dredging & Construction, Inc. ("Eastern Dredging"), the general contractor, and various subcontractors, including Bagby Elevator Company ("Bagby"). In Case No. 1951449, Eastern Dredging appeals from Judge Jack Carl's order holding that Eastern Dredging had waived its right to arbitrate its claims by failing to commence arbitration proceedings within the time allowed by the trial court in its "Order Compelling Arbitration." In Case No. 1951614, Eastern Dredging appeals an order entered by Judge William J. Wynn denying Eastern Dredging's motion to compel arbitration. We affirm the order in Case No. 1951449 and also affirm the order in Case No. 1951614.
Case No. 1951449
This action was filed October 17, 1995, by Bagby; against Eastern Dredging, Bagby alleged money due on an account and sought recovery on theories of quantum meruit, and *103 breach of contract. Against Parliament House, Bagby sought a recovery under the theory of quantum meruit and sought enforcement of materialman's liens, both claims arising out of work Bagby had done during the hotel renovation. On December 15, 1995, Eastern Dredging filed an answer and filed a cross-claim for a mechanic's lien against Parliament House. Eastern Dredging simultaneously filed a motion to stay the action and a motion to compel arbitration of its claims against Parliament House. Eastern Dredging claimed that a resolution of its claims against Parliament House would resolve some of Eastern Dredging's disputes with Bagby. On February 1, 1996, the trial court granted the motion to stay proceedings on Bagby's claims and the motion to compel arbitration between Eastern Dredging and Parliament House stating:
"[T]he `Motion to Stay Proceedings and Compel Arbitration' is granted and the parties are given 30 days within which to begin arbitration or the stay will be [rescinded]."
Eastern Dredging entered into settlement negotiations with Parliament House. These negotiations delayed Eastern Dredging's filing of its arbitration demand until March 15, 1996, approximately 13 days after the 30 days allowed by the February 1 order had expired. On March 20, Bagby filed a motion to return the case to the trial docket because of Eastern Dredging's failure to comply with the February 1 order. On April 18, 1996, the trial court granted this motion to return the case to the "standard track" docket and specifically held that Eastern Dredging, by failing to comply with the trial court's order, had "waived its right to arbitration under the contract." Eastern Dredging appealed to this Court. Eastern Dredging made a motion to stay the case in the trial court pending the outcome of this appeal, but the trial court denied that motion.
Eastern Dredging argues that it did not waive its right to arbitrate its claims against Parliament House by delaying its demand for arbitration until March 15, 1996, 13 days after the deadline set by the trial court for beginning arbitration.
This case is governed by the Federal Arbitration Act ("FAA"), 9 U.S.C. §§ 2, 3, and 4. The Federal Arbitration Act has been interpreted to require that
"`any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration, whether the problem at hand is the construction of the contract language itself or an allegation of waiver, delay, or a like defense to arbitrability.'"
Ex parte Merrill Lynch, Pierce, Fenner & Smith, Inc., 494 So.2d 1, 2 (Ala.1986)(quoting Moses H. Cone Memorial Hospital v. Mercury Construction Corp., 460 U.S. 1, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983))(emphasis added). Thus, there is a presumption against a court's finding that a party has waived the right to compel arbitration. This Court has previously set out the test for determining whether there has been a waiver:
"It is well settled under Alabama law that a party may waive its right to arbitrate a dispute if it substantially invokes the litigation process and thereby substantially prejudices the party opposing arbitration."
Companion Life Ins. Co. v. Whitesell Mfg., Inc., 670 So.2d 897, 899 (Ala.1995). In the Companion Life Ins. Co. case, this Court elaborated on what constituted a waiver of the right to arbitrate: when the party has participated in the judicial process to the extent that arbitration would substantially prejudice the party opposing arbitration only if a party's participation in the judicial process rises to the level of demonstrating an "intention to abandon the right [to arbitrate] in favor of the judicial process" will a waiver be found. 670 So.2d at 899.
Whether there has been a waiver should be determined on a case-by-case basis and the answer will vary depending on the specific facts of the case. Companion Life Ins. Co., 670 So.2d at 899. Moreover, this Court noted in Ex parte Merrill Lynch that "[m]erely answering on the merits, asserting a counterclaim (or cross-claim) or participating in discovery, without more, will not constitute a waiver." 494 So.2d at 3 (quoting Clar Productions, Ltd. v. Isram Motion Pictures, 529 F.Supp. 381, 383 (S.D.N.Y.1982), quoting, in turn, Demsey & Assocs. v. S.S. Sea Star, 461 F.2d 1009, 1018 (2d Cir.1972)). *104 Eastern Dredging petitioned the trial court to compel arbitration at the same time it answered Bagby's complaint. Eastern Dredging filed a cross-claim in order to preserve its right to a mechanic's lien; Ala.Code 1975, § 35-11-221, imposes a six-month statute of limitations on such a lien. The only other action taken by Eastern Dredging or by any other parties between the filing of the motion to compel arbitration on December 15, 1995, and the filing of the March 15, 1996, motion was a motion to consolidate all of the cases relating to the Parliament House renovation.
We conclude that Eastern Dredging's delay in commencing arbitration caused no prejudice to the opposing parties. This Court has noted:
"Factors tending to show prejudice may include the length of the party's delay in demanding arbitration and the expense incurred by the other party by participating in the litigation."
Terminix Int'l Co., Ltd. v. Jackson, 669 So.2d 893 (Ala.1995). Parliament House has not alleged that it suffered any prejudice by the delaythe length of time was relatively minor and Parliament House incurred no expenses, because nothing occurred in the 13-day interim.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
698 So. 2d 102, 1997 WL 112726, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-dredging-constr-v-parliament-house-ala-1997.