Dyer Bros. Golden West Iron Works v. Pederson

192 P. 1002, 112 Wash. 390, 1920 Wash. LEXIS 787
CourtWashington Supreme Court
DecidedSeptember 8, 1920
DocketNo. 15803
StatusPublished
Cited by6 cases

This text of 192 P. 1002 (Dyer Bros. Golden West Iron Works v. Pederson) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dyer Bros. Golden West Iron Works v. Pederson, 192 P. 1002, 112 Wash. 390, 1920 Wash. LEXIS 787 (Wash. 1920).

Opinions

Parker, J.

This action was originally commenced by the plaintiff, Dyer Brothers Grolden West Iron Works, seeking recovery from the defendant Pederson, and Fidelity & Deposit Company, for the furnishing of structural steel for a large bridge ■ constructed by Pederson under a contract with the city of Seattle; Fidelity & Deposit Company being surety upon the bond furnished by Pederson to secure the faithful performance of the contract, and the payment of laborers, [392]*392subcontractors, and materialmen, as prescribed by § 1159, Rem. Code. Tbe plaintiff also sought to have its recovery made a charge upon funds in the hands of the city payable to Pederson upon the contract. The defendant Erickson Construction Company filed its answer and cross-complaint, seeking recovery of compensation from the defendant Pederson and the Fidelity & Deposit Company, and also from the fund, for the furnishing of labor and superintendence in the excavation for the piers of the bridge. Pederson responded to this cross-complaint of Erickson Construction Company by answer and cross-complaint, alleging, in substance, that the Erickson Construction Company had entered upon the work of excavation and partially completed it, in pursuance of an express oral contract with him to.do the same for the lump sum of $18,000, according to the specifications of his contract with the city; that Erickson Construction Company abandoned the work, leaving it unfinished, resulting in his damage in the sum of $27,431, which amount he necessarily expended in excess of the $18,000 he would have paid to Erickson Construction Company had the work been completed under its contract. Pederson prayed for recovery of damages against Erickson Construction Company accordingly. A trial of these issues in the superior court for King county, upon the merits, resulted in a decree denying recovery both to Erickson Construction Company and to Pederson. From this disposition of their respective claims, both Erickson Construction Company and Pederson have appealed to this court.

All parties to the action having proceeded upon the theory that it is of equitable cognizance, the trial court concluded that formal findings of fact were unnecessary, and did not make findings apart from the recitals [393]*393in the decree, which, after reciting the making of the original contract between Pederson and the city for the construction of the bridge, reads in part as follows:

. . on or about August 24th, 1915, the defendant Erickson Construction Company entered into a contract with the defendant Hans Pederson for excavation and construction of coffer dams on the said Fifteenth Avenue Northwest Bridge, Seattle, Washington, for the lump sum of $18,000, upon which construction the defendant Erickson Construction Company entered, and that thereafter the said Erickson Construction Company breached said contract and abandoned the said work, and that, as a result of the said abandonment of said work, and the breach of the said contract and the refusal of said Erickson Construction Company to proceed further, the said Pederson was damaged in the extent of $23,369.69, with interest at the rate of six per cent per annum from November 4th, 1916, the same being the cost to the said Pederson to complete the contract upon which the said Erickson Construction Company had entered.
“Thereafter and in due time the Erickson Construction Company filed a motion for new trial, and said motion for new trial having come on for hearing, and having been on the 20th day of November, fully argued and heard, the court, on the 24th day of November, 1919, handed down his decision upon the motion for new trial, finding and holding that the whole case was controlled by section X of article VIII, paragraph 2, of the city charter of the city of Seattle, which reads as follows:
“ ‘Bids may be received for all or any part or division of any proposed contract and no contract shall be sublet except for the furnishing of material without the previous consent of the city council.’ ”

and that Hans Pederson had, in violation of said charter provision, sublet the contract in question to the Erickson Construction Co., and that said subletting, being in violation of the city charter, was void, and that Hans Pederson could- not recover upon said [394]*394contract because of its invalidity, to which, and to all of which, the defendants Hans Pederson and the Fidelity & Deposit Co. of Maryland duly excepted and except.

“It is, therefore, now by the court ordered, adjudged and decreed:
“That the action of Erickson Construction Co. as against Hans Pederson be dismissed, to which counsel for Erickson Construction Co. excepted and except.
“It is further ordered, adjudged and decreed that the action of Hans Pederson on his cross-complaint as against the Erickson Construction Co. be dismissed, to which Hans Pederson excepted and excepts.”

We are not here concerned with the rights of other parties adjudicated by the decree. In so far as these findings may be considered as findings of fact, they were duly excepted to by counsel for Erickson Construction Company. The exception by counsel for Pederson, noted in the decree, is manifestly nothing more than an exception to the court’s conclusion of law that the subcontract between him and Erickson Construction Company was void because not consented to by the city council, as prescribed in the city charter provision above quoted in the recitals of the decree.

It seems to be necessary for us to first answer the inquiry, Was there a subcontract, apart from the question of its validity, entered into between Erickson Construction Company and Pederson, as recited in the decree, for the performance of which, by Erickson Construction Company, it was to be paid by Pederson the lump sum of $18,000 ? That the trial judge was so convinced, treating the question purely as one of fact, there seems no room for doubting, in view of the recitals in the decree, above quoted. A reading of the evidence, as set forth in the abstracts thereof prepared by counsel for the respective parties, convinces us, as [395]*395manifestly it did the trial court, that there was such a meeting of the minds of Erickson Construction Company and Pederson in the making of the contract; that its terms were certain and well understood by each; that Erickson Construction Company commenced and proceeded in the performance of the contract for a period of some three months before abandoning the work, then notifying Pederson that it would not proceed further with the work; and that Pederson had then paid to Erickson Construction Company upon the contract sums aggregating $9,898. We think it would be quite unprofitable to here review the evidence in detail.

The principal contentions here made by counsel for Erickson Construction Company seem to be that, in any event, the contract between it and Pederson was void and of no effect, because of the failure of the city council to consent thereto; that therefore it is entitled to recover in this action as upon quantum meruit, and have its recovery measured by the reasonable value of the labor and services actually furnished by it to Pederson, irrespective of the compensation therefor specified in the contract; and that, because of the invalidity of the contract, Pederson has no basis upon which to rest his counterclaim for damages by reason of the alleged breach thereof by Erickson Construction Company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bellevue Square Managers, Inc. v. GRS Clothing, Inc.
98 P.3d 498 (Court of Appeals of Washington, 2004)
Dravo Corp. v. L. W. Moses Co.
492 P.2d 1058 (Court of Appeals of Washington, 1971)
State Ex Rel. Salem Pacific Corp. v. Combo Construction Co.
458 P.2d 410 (Oregon Supreme Court, 1969)
Morrison v. Nelson
231 P.2d 335 (Washington Supreme Court, 1951)
Fox & Co. v. State
7 P.2d 961 (Washington Supreme Court, 1932)
Davis v. Thurston County
205 P. 840 (Washington Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
192 P. 1002, 112 Wash. 390, 1920 Wash. LEXIS 787, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dyer-bros-golden-west-iron-works-v-pederson-wash-1920.