Noyes v. Pugin

27 P. 548, 2 Wash. 653, 1891 Wash. LEXIS 105
CourtWashington Supreme Court
DecidedAugust 1, 1891
DocketNo. 205
StatusPublished
Cited by15 cases

This text of 27 P. 548 (Noyes v. Pugin) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noyes v. Pugin, 27 P. 548, 2 Wash. 653, 1891 Wash. LEXIS 105 (Wash. 1891).

Opinion

The opinion of the court was delivered by

Anders, C. J.

— This action was brought by respondent in tbe court below upon a quantum meruit for services alleged to have been rendered for and at the request of appellant, as architect in drawing plans and making estimates for the erection of a building to be known as tbe “Noyes Block” in the city of Seattle. A general denial was filed by tbe defendant, and upon the issues thus joined a trial was had by a jury, who returned a verdict for plaintiff for the amount claimed in tbe complaint.

It appears from the record that tbe plaintiff testified substantially, at the trial, tbat tbe defendant, at a certain time and place, told him tbat two architects (as be recollected or thought) bad proposed to make drawings or [655]*655sketches of the proposed building, with the understanding that, if the sketches were not adopted by defendant, the latter was to pay nothing for the work, and that he would like to have plaintiff also make such sketches upon the same terms; that plaintiff accepted the proposal, made the sketches, and submitted them to the defendant, who expressed himself satisfied, and stated that they were just what he wanted, and gave plaintiff the order to go on and complete the drawings ; that he agreed with defendant to make the drawings and specifications complete, let the contract, and superintend the erection of the building, for three and one-half per cent, of the estimated cost thereof; that he completed the plans, and wrote the specifications in full, with the exception of some minor details as to the interior finish; and that the defendant, on being notified that the plans were ready, refused to accept the same, and denied ever having requested or ordered plaintiff to do the work. The plaintiff estimated the cost of the building according to his plans and specifications at $90,000, and testified that the labor performed by him in making the drawings and specifications was worth two and one-half per cent, of that sum; and in this he was corroborated by other witnesses. Several architects also testified that the usual price charged by architects for drawing plans and specifications and superintending the erection of buildings, or, in other words, for “full professional services,” was five per cent, of the estimated cost. The defendant claimed and testified that he never employed or requested plaintiff to make plans and specifications for his building; that the only agreement or understanding between him and plaintiff was that if the latter should submit sketches which should be adopted by defendant, then and in that event he was to pay plaintiff for the work, but not otherwise; and that plaintiff proposed to do the whole work for two and one-half per cent, of the cost of the building; and that plaintiff, [656]*656at the time of said proposal, stated that the building could be constructed for $60,000.

The first contention of appellant is that the evidence fails to show any employment of respondent by him, or that he ever requested the latter to perform the labor .for which he now seeks compensation, and that the court below erred in not setting aside the verdict for insufficiency of the evidence. Upon that point both parties testified fully; and, there being a direct conflict between the testimony of plaintiff and defendant, it was for the jury to determine, under all the facts and circumstances before them, upon which side lay the preponderance of the evidence; and, not being convinced that the verdict was unwarranted by the evidence, we cannot say that the court erred in refusing to set it aside and grant a new trial upon the ground above indicated.

Counsel for appellant further contend that the court erred in charging the jury as to the measure of damages recoverable by plaintiff. The following is the instruction complained ofs

“ If you find from the evidence that there was a contract of employment to do the work as claimed by' plaintiff, your next inquiry should be, did the plaintiff do the work as requested? If he has, he is entitled to recover what the evidence shows such work to be reasonably worth. Was there a contract to do this work that the plaintiff claims? If there was not, he is not entitled to recover. If there was a contract, and he has performed the work according to that contract, he is entitled to recover what the evidence shows the services were worth.”

The point made is that, as the plaintiff claimed to have done the work under a contract whereby he was to receive three and one-half per cent, upon the estimated cost of the building as compensation for his entire services, the jury should have been instructed that he could only recover what the services rendered were worth, at the contract [657]*657price. On the other hand, the respondent claims that, as the contract was broken by appellant, he was no longer bound by its terms, and was entitled to recover what he could show his labor was worth; or, in other words, that the law implies a contract, in such cases, to pay the reasonable value of the work done, without regard to the original agreement between the parties. And the question for our determination is, which .of the two theories should be adopted in the case at bar. The plaintiff had his choice of two remedies, viz.: Either to bring his action for a breach of the contract — in which event he might have recovered not only the value of the labor actually performed, at the contract price, but also all profits he might have shown would have been realized by him if he had been permitted to do the entire work in accordance with the terms of the agreement — or to disregard the contract and sue for the value of his services. He chose the latter alternative, and must be confined to such an amount as he ought to recover under the circumstances. In regard to the measure of damages, it is a universal and cardinal principle that the person injured shall receive a compensation commensurate with his loss or injury, and no more; and it is a right of the person who is bound to pay this compensation not to be compelled to pay more, except costs. Sutherland on Damages, p. 17, § 1, and cases cited. Applying this principle to the case before us, what should be the compensation of appellant for the work actually done? His labor conferred no benefit upon appellant, because his plans were not adopted or used by the latter; and hence the cases holding that a defendant who has prevented the other party from fully performing his contract of service must pay for benefits received are not applicable to this case. He proved by a number of witnesses that the whole work he agreed to do was worth five per cent, of the cost of the building, which was placed by him at $90,000, and [658]*658the part performed was worth two and one-half per cent., and the jury by their verdict awarded him that proportion of $>90,000. But he also testified, as we have seen, that he agreed to do the entire work of drawing the plans and specifications, letting the contract and superintending the erection of the building for three and one-half per cent, of the estimated cost. If, therefore, he had performed the whole work according to his agreement, and appellant had neglected or refused to pay him therefor, and he had brought his action upon the common counts for work and labor, instead of suing upon the contract, the measure of the recovery, according to the adjudged cases, would have been the contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dravo Corp. v. L. W. Moses Co.
492 P.2d 1058 (Court of Appeals of Washington, 1971)
Ahrens v. Ladley
334 P.2d 778 (Washington Supreme Court, 1959)
Crosby v. State
106 So. 741 (Supreme Court of Florida, 1925)
Bailey v. Furleigh
208 P. 1091 (Washington Supreme Court, 1922)
LeDoux v. Seattle North Pacific Shipbuilding Co.
195 P. 1006 (Washington Supreme Court, 1921)
Dyer Bros. Golden West Iron Works v. Pederson
192 P. 1002 (Washington Supreme Court, 1920)
Bookhout v. Vuich
172 P. 740 (Washington Supreme Court, 1918)
Jones v. Chicago, Burlington & Q. R.
147 P. 508 (Wyoming Supreme Court, 1915)
Grayson v. Durant
1914 OK 581 (Supreme Court of Oklahoma, 1914)
Gabrielson v. Hague Box & Lumber Co.
104 P. 635 (Washington Supreme Court, 1909)
Peyser v. Western Dry Goods Co.
102 P. 750 (Washington Supreme Court, 1909)
Scherrer v. City of Seattle
100 P. 144 (Washington Supreme Court, 1909)
Jones v. City of Seattle
98 P. 743 (Washington Supreme Court, 1908)
Chase v. Smith
77 P. 1069 (Washington Supreme Court, 1904)
Guley v. Northwestern Coal & Transportation Co.
35 P. 372 (Washington Supreme Court, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
27 P. 548, 2 Wash. 653, 1891 Wash. LEXIS 105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noyes-v-pugin-wash-1891.