Davis v. Thurston County

205 P. 840, 119 Wash. 414, 1922 Wash. LEXIS 795
CourtWashington Supreme Court
DecidedApril 5, 1922
DocketNo. 16789
StatusPublished
Cited by4 cases

This text of 205 P. 840 (Davis v. Thurston County) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. Thurston County, 205 P. 840, 119 Wash. 414, 1922 Wash. LEXIS 795 (Wash. 1922).

Opinion

Bridges, J.

— Suit for damages growing out of a contract for the construction of a county bridge.

On August 16, 1920, the plaintiff and defendant entered into a written contract by the terms of which the former was to construct a certain small bridge for the latter, for which he was to be paid $1,575, and the bridge was to be completed by September 18 of that year. The complaint, after alleging the contract, set out that, while plaintiff was proceeding with the work of constructing the bridge, defendant ejected him from the premises and refused to permit him to complete the work, and made a contract with other parties for the work; that he was at all times ready, willing and able to construct the bridge according to the terms of the contract; that he had expended a large sum of money in doing such of the work as he had performed when he was stopped, and that he had been damaged in the sum of $1,575. The first portion of the answer was in substance a general denial. There was a first affirmative defense which alleged that the plaintiff failed and refused to build the bridge according to the terms of the contract, but, on the contrary, abandoned the work, and for those reasons, and after the time provided in the contract for the completion of the bridge, the defendant let a contract to other parties to build it. A second affirmative defense alleged that such of the work as the plaintiff did before abandoning it was not in accordance with the contract or the plans and specifications, and that such work was done in a [416]*416careless and negligent manner, and that the plaintiff did not, in good faith, attempt to perform his contract. The reply admitted that the bridge was not bnilt within the time provided in the contract, but alleged that the defendant had waived the time of completion, and denied that the work had been carelessly or negligently done. It further alleged that the plaintiff was delayed in the work he had done on the bridge by his inability to obtain cement and because of high waters in the stream which was being bridged.

There was a verdict by the jury in favor of the plaintiff in the sum of $1,575. Later the plaintiff elected to, and did, waive any amount of the verdict in excess of $1,271. A judgment was entered in that sum, In its appeal the defendant has raised many questions.

(1) Appellant contends that the complaint and reply are inconsistent, in that the former is based solely upon the idea that the respondent was entitled to recover damages because the appellant refused to permit him to complete his contract, whereas the burden of the reply is that he was delayed in the completion of his contract and unable to finish the bridge within the time provided in the contract because of inability to get certain building materials, and because of high waters in the stream. We do not think there is any material variance. The plaintiff is still seeking to recover for the reasons alleged in his complaint. The reply is merely in response to the allegations of the answer alleging that the respondent did not complete the bridge within the contract period, but, on the contrary, abandoned the work, and that such work as he did was not in accordance with the terms of the contract, and was not done in good faith.

(2) The respondent testified that he was delayed in the construction of the bridge and was unable to finish [417]*417it within the contract period because of high waters and inability to obtain cement. All of this character of testimony was received over the constant objections of the appellant. We think the court’s ruling was right. It may be the rule that the respondent could not excuse the failure to build the bridge within the contract time because of high water and lack of cement, but this testimony was not offered or received for this purpose. There being some proof tending to show that time had been waived, this testimony was admissible as tending to disprove appellant’s allegations that respondent had not proceeded in good faith and had abandoned the work.

(3) The appellant also contends that its motions for nonsuit and for judgment notwithstanding the verdict should have been granted. It charges that there was not sufficient proof that the plaintiff had filed his claim with the appellant, as provided by law. We think, however, that the admissions in the answer relieved the respondent of such proof. It is also said that the motions should have been granted because the testimony shows the respondent abandoned the contract, and that he did not, in good faith, attempt to perform it, even if he had not abandoned it. We cannot agree with these contentions. There was ample testimony to carry the case to the jury, to the effect that the appellant had waived the provisions of the contract concerning the time for the completion of the bridge, and that the respondent was able and willing to construct the bridge in accordance with the contract, and that he had not abandoned the proposition, or failed in good faith performance. These questions were all matters to be submitted to the jury upon proper instructions. If, as the testimony tended' to show, although stoutly denied by the appellant, there [418]*418was no time within which the bridge was to be completed, and that the respondent had not abandoned the job, but, on the contrary, was proceeding in good faith, then, so far as those questions are concerned, he would be entitled to recover.

(4) Complaint is made of the following instructions given to the jury:

“If you find in favor of the plaintiff in this case, then I instruct you that the plaintiff would be entitled to recover, as damages, the amount of his expenditures in the performance of the contract up to the time of the stoppage, that is to say, he would be entitled to reimbursement for his expense in so far as he proceeded with the performance of his contract, and in addition to his expenses he would be entitled to recover the profits which he would have realized by performing the whole contract, if he had performed it; the plaintiff’s recovery, if he recovers at all, should include these two items, namely, the expense incurred in part performance, with a further item of the profits which he would have made by the performance of the whole contract.”

The court seems to have taken this instruction verbatim from the case of Anderson v. Hilker, 38 Wash. 632, 80 Pac. 848. But the facts of the two cases are so different that the same instruction could, under no circumstances, be proper in both. In the Anderson case, the plaintiff was seeking to recover for profits he would have made had he been permitted to complete his contract, while here the respondent did not seek any such recovery, consequently, under the rule of the Anderson case, this instruction was wrong because it permitted the respondent to recover lost profits. We will not comment on other specific objections made to this instruction, because we have concluded that it is fundamentally wrong for the same reasons that the instruction approved in the Anderson case was fundamentally wrong. In that case Anderson alleged, and his proof [419]*419tended to show, that he had a contract with Hilker to move a house owned, by the latter, from the town of Ocosta to Hoquiam, for certain agreed compensation; that after he did a part of the work and had gone to considerable expense, Hilker breached the contract. Plaintiff sought to recover on account of his expenditures incurred in part performance and for loss of profits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. McCollum
136 P.2d 165 (Washington Supreme Court, 1943)
Goben v. Des Moines Asphalt Paving Co.
225 N.W. 357 (Supreme Court of Iowa, 1929)
Wise v. Nichols
266 P. 186 (Washington Supreme Court, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
205 P. 840, 119 Wash. 414, 1922 Wash. LEXIS 795, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-thurston-county-wash-1922.