Durr Mechanical Construction, Inc. v. The City Of New York

CourtUnited States Bankruptcy Court, S.D. New York
DecidedJune 16, 2021
Docket20-01214
StatusUnknown

This text of Durr Mechanical Construction, Inc. v. The City Of New York (Durr Mechanical Construction, Inc. v. The City Of New York) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Durr Mechanical Construction, Inc. v. The City Of New York, (N.Y. 2021).

Opinion

UNITED STATES BANKRUPTCY COURT SOUTHERN DISTRICT OF NEW YORK --------------------------------------------------------------- In re: ) NOT FOR PUBLICATION ) ) DURR MECHANICAL ) Chapter 11 CONSTRUCTION, INC., ) Case No. 18-13968 (DSJ) ) Debtor. ) --------------------------------------------------------------- ) DURR MECHANICAL ) CONSTRUCTION, INC., ) ) Plaintiff, ) Adv. Proc. No. 20-1214 (DSJ) ) - against - ) ) THE CITY OF NEW YORK and THE ) NEW YORK CITY DEPARTMENT OF ) ENVRONMENTAL PROTECTION, ) ) Defendants. ) ) ---------------------------------------------------------------

MEMORANDUM OF DECISION AND ORDER A P P E A R A N C E S: CULLEN and DYKMAN LLP Counsel for Durr Mechanical Construction, Inc. 100 Quentin Roosevelt Boulevard Suite 402 Garden City, NY 11530 By: Elizabeth Aboulafia, Esq. C. Nathan Dee, Esq.

NEW YORK CITY LAW DEPARTMENT Counsel for the City of New York and the New York City Department of Environmental Protection 100 Church Street Room 3-124 New York, NY 10007 By: Amanda Papandrea, Esq. DAVID S. JONES UNITED STATES BANKRUPTCY JUDGE This case involves a high-dollar dispute between New York City and a City agency, on the one hand, and a general contractor that performed work on a major City project, on the other. Defendants the City of New York (“the City”) and the New York City Department of Environmental Protection (“DEP” and, collectively, “Defendants”) have moved to dismiss the adversary proceeding brought by Durr Mechanical Construction, Inc. (“Durr”), the debtor in a Chapter 11 bankruptcy before this Court. [ECF No. 5 (the “Motion to Dismiss”)]. They also have filed a supplemental motion [ECF No. 11 (the “Motion to Compel ADR”)], seeking to compel alternative dispute resolution (“ADR”) as to two of Durr’s claims pursuant to a provision within

the relevant contract between Durr and the City. For the reasons that follow, the Court grants Defendants’ Motion to Compel ADR, holds this action in abeyance, and reserves judgment on the Motion to Dismiss. I. BACKGROUND A. The Main Bankruptcy Durr, a general contractor, filed a voluntary Chapter 11 petition in December 2018. [Bankr. S.D.N.Y. 18-13968, ECF (“Bankr. ECF”) No. 1 (the “Petition”)]. The resulting bankruptcy case is assigned to the Honorable Lisa G. Beckerman. [Bankr. ECF No. 503]. Durr recently filed an amended Chapter 11 plan of liquidation. Bankr. ECF 510. In April 2021, the Court approved Durr’s disclosure statement and scheduled a hearing on confirmation of its third amended Chapter 11 plan. [Bankr. ECF No. 525]. B. Factual History Durr commenced the adversary proceeding in September 2020. [ECF No. 1 (the “Complaint”)]. Durr alleged that it entered a contractwith the City (the “Contract”) in 2007 to work on the heating, ventilation, and air conditioning (“HVAC”) at the Croton Water Filtration Plant (the “Croton Plant”) in the Bronx. [Id. ¶ 11]. 1. History of the Croton Plant The Croton Watershed serves as one of the three principal sources of drinking water for New York City. [Id. ¶¶ 17–18]. The federal government and the New York State government required the City to build the Croton Plant, and the City stipulated with the state department of health that it would design the plant by 1995 and construct it by 1999. [Id. ¶ 18]. The City breached the terms of that stipulation, and the federal government sued the

Defendants in the United States District Court for the Eastern District of New York for violations of federal environmental laws. [Id. ¶ 19]. New York State and the state department of health intervened, claiming violations of state environmental laws. [Id.]. The District Court entered a consent decree (the “Consent Decree”), through which the City agreed to construct the Croton Plant (the “Project”). [Id. ¶ 20]. The Consent Decree defined temporal milestones by which the City was required to have completed successive phases of Project construction. [Id. ¶¶ 21–23, 25]. The federal government, New York State, and the state department of health (collectively, the “Regulators”) would enforce the City’s compliance with each of the milestones by imposing financial penalties for any

noncompliance by the City. [Id. ¶¶ 22, 35]. The Consent Decree required the DEP to submit certified monthly progress reports on the Project. [Id. ¶ 36]. The parties amended the Consent Decree multiple times, with the second such supplement (the “Second Supplement”) containing the Project’s operative deadlines at the time of the Complaint. [Id. ¶¶ 26–27]. The Second Supplement includes both interim and long-term milestones. [Id. ¶¶ 27–28]. In 2004, the City submitted certifications that it met several interim milestones, which the Regulators approved. [Id. ¶¶ 29–31]. Among them was Interim Milestone O, set for May 1, 2011: the “Substantial Completion – Begin Start-up and Testing” for the Croton Plant’s HVAC system. [Id. ¶ 30]. 2. Relevant Contract Provisions Referencing the Consent Decree and ADR In the Complaint, Durr alleged as follows. The Contract by which Durr was to perform HVAC work at the Croton Plant was made “subject to the terms of the Consent Decree,” in that the Contract’s terms expressly incorporated the Consent Decree’s Long Term and Interim Milestones, referring to them as “Project Milestones.” [Id. ¶¶ 24, 34, 39]. The specific provision in question, titled “Detailed Specification 01271,” provides:

[t]he work under these Contracts shall be entirely completed in a manner acceptable to the City within the Period of Performance indicated in Schedule A in the General Conditions. The work to be performed under [the Contract] is subject to the Order on Consent in the US District Court of Eastern New York [sic].

[ECF No. 1-1 at 22 (pdf pag.)]

The City included a similar provision in its contracts with all of its “prime contractors” on the Project, including Durr. [ECF No. 1 ¶ 34 & n.11]. Accordingly, Interim Milestone O, with its May 1, 2011 completion date, was the deadline for Durr to complete its HVAC work under the Contract. [Id. ¶ 29]. Neither the District Court nor the Regulators modified this Interim Milestone. [Id. ¶ 32]. The City included liquidated damages provisions in all of its construction contracts for the Project. [Id. ¶ 37]. These provisions required indemnification or offset on account of any monetary penalties assessed against the City under the Consent Decree if a contractor’s performance caused a failure to meet one of the Project Milestones, the deadline for Durr’s HVAC work among them. [Id.]. Durr alleged that the incorporation of the Consent Decree’s Long Term and Interim Milestones as Project Milestones, as well as the liquidated damages provisions against the prime contractors, “imposed fundamental affirmative obligations” on the City with regard to the prime contractors. [Id. ¶ 39]. These asserted obligations included providing the prime contractors with timely access to the work site, avoiding interference, disruption, and delay of the prime contractors’ work so that they could meet the Project Milestones, supplying complete, coordinated designs and specifications, and effectively coordinating the work of the prime contractors. [Id. ¶¶ 39–41]. Durr alleged that the City failed to satisfy these obligations. [Id. ¶¶ 42–46].

Article 27 of the Contract, entitled “Resolution of Disputes,” required the use of alternative dispute resolution as follows: 27.1 All disputes between the City and the Contractor of the kind delineated in this article that arise under, or by virtue of, this Contract shall be finally resolved in accordance with the provisions of this article and the PPB [Procurement Policy Board] Rules. This procedure for resolving all disputes of the kind delineated herein shall be the exclusive means of resolving any such disputes.

. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dean Witter Reynolds Inc. v. Byrd
470 U.S. 213 (Supreme Court, 1985)
In Re S.G. Phillips Constructors, Inc.
45 F.3d 702 (Second Circuit, 1995)
In Re United States Lines, Inc.
197 F.3d 631 (Second Circuit, 1999)
Mbna America Bank, N.A. v. Kathleen A. Hill
436 F.3d 104 (Second Circuit, 2006)
In Re Sw Bach & Co.
425 B.R. 78 (S.D. New York, 2010)
Brownstone Investment Group, LLC v. Levey
514 F. Supp. 2d 536 (S.D. New York, 2007)
Epic Systems Corp. v. Lewis
584 U.S. 497 (Supreme Court, 2018)
Microsoft Corp. v. Samsung Electronics Co.
60 F. Supp. 3d 525 (S.D. New York, 2014)
Katsoris v. WME IMG, LLC
237 F. Supp. 3d 92 (S.D. New York, 2017)
Delaware Trust Co. v. Wilmington Trust, N.A.
534 B.R. 500 (S.D. New York, 2015)
Nicosia v. Amazon.com, Inc.
834 F.3d 220 (Second Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Durr Mechanical Construction, Inc. v. The City Of New York, Counsel Stack Legal Research, https://law.counselstack.com/opinion/durr-mechanical-construction-inc-v-the-city-of-new-york-nysb-2021.