Ducote v. Arnold

416 So. 2d 180
CourtLouisiana Court of Appeal
DecidedMay 25, 1982
Docket12786
StatusPublished
Cited by18 cases

This text of 416 So. 2d 180 (Ducote v. Arnold) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ducote v. Arnold, 416 So. 2d 180 (La. Ct. App. 1982).

Opinion

416 So.2d 180 (1982)

Gail A. Cucurullo, Wife of/and Michael J. DUCOTE
v.
Arthur H. ARNOLD, Sr. & Cecil A. McConnell a/k/a A. J. McConnell, Jr., d/b/a Arnold Construction Co.

No. 12786.

Court of Appeal of Louisiana, Fourth Circuit.

May 12, 1982.
Dissenting Opinion May 25, 1982.
Rehearing Denied July 16, 1982.

*181 Fiasconaro & Fiasconaro, Paul S. Fiasconaro, New Orleans, for plaintiffs-appellees.

Gary J. Dragon, Chalmette, for defendants-appellants.

Before BARRY, AUGUSTINE and WILLIAMS, JJ.

BARRY, Judge.

The defendant construction company appeals a judgment which held that it breached a building contract.

Plaintiffs, Mr. & Mrs. Michael Ducote, entered into a written contract on March 15, 1978 with Arnold Construction Company[1] to build an addition[2] to their residence for $40,650.00 to be paid in five stage installments. Work began March 20, 1978 after which plaintiffs made four payments totaling $33,862.50. Ten months later, January 18, 1979, the work was incomplete which prompted plaintiffs to dismiss Arnold and hire another contractor to correct faulty work and finish the job.

Plaintiffs sued Arnold for damages alleging breach of contract due to faulty workmanship and failure to complete the work within a reasonable time. Arnold reconvened for the balance of the contract and sought damages for humiliation. The lower court awarded plaintiffs $14,600.50, consisting of $6,100.50 to complete the work, $5,000.00 for mental anguish and inconvenience, plus $3,500.00 attorney's fees. Defendant appeals saying there was no breach of contract because of its failure to perform, and alternatively, urges the trial court erred in computing the damages, in allowing recovery for mental anguish, and awarding legal fees. Plaintiffs answer the appeal seeking an increase in all items of quantum.

BREACH OF CONTRACT

The contract does not have a completion date, rather it provides the work should be completed within a "reasonable time." George Pope, a building expert, testified for the defendant on the problems incurred in matching the existing residence to the new addition. Mr. Pope noted because of roots in the ground where the chain walls were placed, it was reasonable for the excavation work to take four to five weeks. Mr. Pope stated, after listening to the testimony of others, it was his opinion the amount of time defendants worked on this job was not unreasonable. A carpenter subcontractor said he could normally frame, sub-floor, and roof new construction in seven work days, whereas this job took four weeks because of the unique problems encountered in connecting the old and new roofs. Mr. Arnold, one of the defendant partners, testified the *182 roots were a major unanticipated problem that required extra time. He also stated the original house had sunk approximately 1½ inches which caused the addition to be out of plumb. Another problem was the necessity to redesign the new roof because the plans were not compatible with the existing roof. Mr. Arnold acknowledged that painting, plumbing and electrical work was not completed.

Plaintiffs relied upon the testimony of Mr. Troendle, the contractor who completed the job. He said the addition was "roughed in" when he started work and there were numerous defects[3] in the defendant's work. He stated the defendant had completed approximately two-thirds of the job, but the addition at that stage could not be lived in. Mr. Troendle said his contract to complete the job was for $9,350.00 which did not include plumbing, electrical, exterior painting, and flooring. It took slightly more than two months to complete the job, partly because of corrections that had to be made.

In a lawsuit of this sort conflicting testimony is the rule and conclusions of the Trial Judge must of necessity be given great weight. We feel it is reasonable to assume the lower court discounted the testimony of defendant's expert, Mr. Pope, because he never visited the work site and his familiarity with this dispute stems only from the testimony he heard during trial.

Under Louisiana law, a contractor who undertakes a construction project must perform the work in a skillful and workmanlike manner. LSA-C.C. Art. 2769. In a suit to impose liability on a contractor for poor workmanship or noncompliance with the contract, a plaintiff must prove his case by a preponderance of the evidence, either direct or circumstantial. A & M Pest Control Service, Inc. v. Fejta Construction Company, Inc., 338 So.2d 946 (La.App. 4th Cir. 1976).

In written reasons the Trial Judge concluded "... there is no doubt from the evidence that the job dragged and lagged on without fault on behalf of plaintiffs." Our review of the testimony, particularly the on-site experiences and unbiased statements of Mr. Troendle, leads us to conclude plaintiffs carried their burden of proof. We agree with the lower court's conclusion that the defendant failed to perform within a reasonable time and therefore is liable for appropriate damages. We are also satisfied defendant's efforts included faulty workmanship which required corrections that added to the completion cost.

BASIS TO COMPUTE DAMAGES

Whether or not the contract was substantially performed governs how the damages are to be calculated. If there was substantial performance, the contractor is entitled to recover the contract price reduced by the amount necessary to complete the work; if there has not been substantial performance the contractor's recovery is limited to quantum meruit with the owner entitled to costs incurred in completing the work in excess of the contract price.

Substantial performance exists when the construction may be used for the purpose intended regardless of defects or omissions. It is a question of fact which considers "the extent of the defect or non-performance, the degree to which the purpose of the contract is defeated, the ease of correction, and the use or benefit to the owner of the work performed ... Once substantial performance has been shown the burden of proof then shifts to the owner who must prove the existence and nature of the alleged defects, that they are due to faulty material and/or workmanship, and the cost of repairing the defects." Neel v. O'Quinn, 313 So.2d 286 at p. 290 (La.App. 3rd Cir.) writ denied, 319 So.2d 440 (La. 1975). (Citations omitted.)

*183 The reasons for judgment do not mention whether the contract was substantially performed, but did provide: "Plaintiffs were required to make these payments in order to have the work completed at some time during the year 1978 but the work was not actually completed until the first quarter of 1979 and then primarily by others." (Emphasis added.) By this statement and from the manner in which the damages were calculated, i.e., reimbursement for costs incurred to complete the work in excess of the contract price, we can only deduce the Trial Judge found there was not substantial performance. We agree that conclusion is appropriate.

COMPUTATION OF DAMAGES

In addition to the $33,862.50 paid to the defendant, the Trial Judge found plaintiffs paid $12,888.00 to complete the addition to their home, for: exterior paint—$900.00; flooring—$1,638.00; electrical—$300.00; plumbing—$700.00; Troendle, contractor— $9,350.00. He concluded: "Thus the plaintiffs had paid $46,750.50 to erect improvements for their convenience, that if property [sic] and timely performed, would not have cost them more than $40,650.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doucette v. Guient
208 So. 3d 444 (Louisiana Court of Appeal, 2016)
Superior Derrick Svcs, L.L.C. v. Lonestar 203, et
547 F. App'x 432 (Fifth Circuit, 2013)
Freeman & Mills, Inc. v. Belcher Oil Co.
900 P.2d 669 (California Supreme Court, 1995)
West v. Collins
648 So. 2d 500 (Louisiana Court of Appeal, 1994)
Leflore v. Anderson
537 So. 2d 215 (Louisiana Court of Appeal, 1988)
Perrodin v. SOUTHERN SIDING CO. INC.
524 So. 2d 885 (Louisiana Court of Appeal, 1988)
Robert v. Bayou Bernard Marine, Inc.
514 So. 2d 540 (Louisiana Court of Appeal, 1987)
LaFleur v. John Deere Co.
491 So. 2d 624 (Supreme Court of Louisiana, 1986)
Fontenot v. F. Hollier & Sons
478 So. 2d 1379 (Louisiana Court of Appeal, 1986)
Diodene v. Blueridge, Inc.
480 So. 2d 446 (Louisiana Court of Appeal, 1985)
Guitreau v. Juneau
479 So. 2d 431 (Louisiana Court of Appeal, 1985)
Gagliano v. Namias
479 So. 2d 23 (Louisiana Court of Appeal, 1985)
B & B Cut Stone Co., Inc. v. Resneck
465 So. 2d 851 (Louisiana Court of Appeal, 1985)
Richard v. Bourda
451 So. 2d 198 (Louisiana Court of Appeal, 1984)
Pike v. Stephens Imports, Inc.
448 So. 2d 738 (Louisiana Court of Appeal, 1984)
Brockhoeft v. McQueen
432 So. 2d 402 (Louisiana Court of Appeal, 1983)
Riche v. Juban Lumber Co., Inc.
421 So. 2d 318 (Louisiana Court of Appeal, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
416 So. 2d 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ducote-v-arnold-lactapp-1982.