DSC Industries, Inc. v. Robert Sagot, Inc. (In Re DSC Industries, Inc.)

79 B.R. 244, 1987 Bankr. LEXIS 1749
CourtUnited States Bankruptcy Court, E.D. Pennsylvania
DecidedNovember 3, 1987
Docket19-10102
StatusPublished
Cited by10 cases

This text of 79 B.R. 244 (DSC Industries, Inc. v. Robert Sagot, Inc. (In Re DSC Industries, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DSC Industries, Inc. v. Robert Sagot, Inc. (In Re DSC Industries, Inc.), 79 B.R. 244, 1987 Bankr. LEXIS 1749 (Pa. 1987).

Opinion

OPINION

DAVID A. SCHOLL, Bankruptcy Judge.

The instant Adversary proceeding is an accounts receivable action filed by a Debt- or-in-Possession which was a subcontractor on a building contract against the general contractor on the contract for amounts which the Plaintiff charged for alterations from its initial undertaking. We shall award the Plaintiff the entire sum requested because we believe that the alterations were reasonably communicated to and hence implicitly accepted by the Defendant; were caused by circumstances beyond the Plaintiff’s control; and, due to lack of privity of contract, would be unlikely to be recoverable by the Plaintiff from the building’s owner.

This action was commenced on August 6, 1987. The Defendant filed an Answer and Counterclaim, which was in turn answered, and the matter came to trial before us on September 29, 1987. At the close of the trial, we issued an Order, dated September 30, 1987, permitting the parties to file Proposed Findings of Fact and Conclusions of *246 Law and any supporting Briefs on or before October 16, 1987. Since this is an Adversary proceeding, we are obliged per Bankruptcy Rule 7062 and Federal Rule of Civil Procedure 52(a), to prepare our decision in the form of Findings of Fact and Conclusions of Law. We shall do so, setting forth a discussion of our legal analy-ses in the course of stating our Conclusions of Law.

FINDINGS OF FACT

1. In early 1986, Camden County, New Jersey, (hereinafter referred to as “the Owner”), desired to construct a new correctional facility.

2. The Plaintiff became aware of this project and obtained a copy of the specifications for the manufacture of the one hundred and five (105) dining-hall tables to be constructed in the facility, which were to be modeled on standard models used by Southern Steel Company, which items the Plaintiff regularly produced.

3. The Plaintiff submitted a bid to the Defendant, a general contractor bidding on the commercial furnishings aspect of the contract. Both parties’ bids were successful.

4. Although there was no formal written contract between the parties, the Plaintiffs undertaking was memoralized by a Quotation of February 19, 1986, and a totally-consistent written purchase order produced by the Defendant on May 5, 1986, on which the contract amount was designated as $72,661.00.

5. One condition of the agreement between the parties, which also was not reduced to writing, was that the Owner could test a sample table to determine whether it could be ripped out of the floor by inmates and used as a weapon within a certain time-frame. The initial sample table failed such a test conducted on May 30, 1986; the table was in fact ripped out of the floor and the table-top was bent within several minutes.

6. On June 20, 1986, the Plaintiff prepared and forwarded a Change Order form to the Defendant, which anticipated a change in floor anchors to attempt to correct the problems, at an additional cost of $2,650.00.

7. Another sample was prepared and another test was conducted by the Owner using the revised floor anchors in early July, 1986. Present at the site were, inter alia, Eric Berju, the Plaintiffs Vice-President in charge of sales, and Joseph Smirig-lio, the Defendant’s sales representative, both of whom testified at trial.

8. As before, the new sample table failed the test administered on it. Thereafter, the previous Change Order of June 20, 1986, was cancelled.

9. There is a dispute regarding discussions among the parties present at the facility — which included the Owner’s Under-sheriff and the Owner’s architectural firm — immediately after this second test. Mr. Berju stated that he took Mr. Smiriglio aside and suggested that legs be placed under each seat, indicating that there would be an additional cost of $40.00 per unit or $4,200.00, for the legs alone. Mr. Berju also stated that the Owner’s architect insisted that a certain other type of anchor bolt, utilized successfully in another facility, be utilized in this facility. Meanwhile, Mr. Smiriglio testified that Glen Kramer, the Plaintiff’s Executive Vice-President, was present on behalf of the Plaintiff at this meeting rather than Mr. Berju and that, without discussing same aside with him, blurted out to the group that additional legs would be necessary and that the total cost for affixing same would be $4,200.00, which figure was firmly agreed to by all parties on the spot.

10. We credit Mr. Berju’s version of this discussion. Mr. Smiriglio’s recollection appeared in all respects less detailed, and we believe that he identified the wrong agent of the Plaintiff present. We also believe that it was unlikely that any agent of the Plaintiff could have been expected to make an estimate on the spot, or that they would have done so, or that they would have agreed to have been bound by such an estimate.

11. On October 22, 1986, the Owner agreed with the Defendant to alter the *247 table-contract by adding $4,200.00 in costs. There was no evidence that this agreement was ever communicated to the Plaintiff.

12. On October 24, 1986, the subcontractor performing the installations of the tables sent a Message/Reply note to Mr, Kramer recapping a meeting of October 21, 1986 (concerning which meeting no testimony was adduced), that confirmed that the Plaintiff would move and enlarge the holes in the legs for additional anchors. No cost figures were set out in the note, however.

13. On December 16, 1986, the Plaintiff forwarded a Change Order to the Defendant which contemplated an additional structure to the table top plate, at a cost of $2,100.00; additional legs, at a cost of $4,200.00; and charges for changing the holes on the floor anchors, at a cost of $6,460.00, for a total additional sum of $12,-760.00, bringing the total contract charges to $85,421.00.

14. The Defendant, per Mr. Smiriglio, denied receipt of this Change Order. Mr. Smiriglio also contradicted testimony of Mr. Kramer that there were conversations relating to the Change Order with Mr. Smi-riglio in early 1987, which Mr. Kramer indicated that he understood as implicit acceptance of the figures on the Change Order. It is undisputed that the Change Order, like the June 20, 1986, Change Order, was not signed by the Defendant, nor was any written agreement of the Defendant to pay the additional $12,760.00 ever executed.

15. The testimony of Mr. Kramer that he sent the Change Order to the Defendant and later discussed the substance of the Change Order of December 16, 1986, with Mr. Smiriglio, was totally credible, as we think it likely that this dispatch and these discussions would have and therefore did take place. We do not credit the contrary testimony of Mr. Smiriglio.

16. The Plaintiff, assuming that approval had been given as to the December 16, 1986, Change Order, produced the tables as revised, and they were successfully installed in the Owner’s facility in spring, 1987.

17. Through May 14, 1987, the Defendant submitted at a total of $75,045.00 to the Plaintiff, on an alleged remaining balance of $83,967.00, leaving an alleged net balance of $8,922.00.

18.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re TM Carlton House Partners, Inc.
108 B.R. 512 (E.D. Pennsylvania, 1989)
In Re Franks
95 B.R. 346 (E.D. Pennsylvania, 1989)
Crossley v. Lieberman
90 B.R. 682 (E.D. Pennsylvania, 1988)
Fleet v. Rhode (In Re Fleet)
89 B.R. 420 (E.D. Pennsylvania, 1988)
Littles v. Lieberman (In Re Littles)
90 B.R. 669 (E.D. Pennsylvania, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
79 B.R. 244, 1987 Bankr. LEXIS 1749, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dsc-industries-inc-v-robert-sagot-inc-in-re-dsc-industries-inc-paeb-1987.