Temp-Way Corp. v. R.M. Shoemaker Co. (In Re Temp-Way Corp.)

82 B.R. 747, 1988 Bankr. LEXIS 210, 1988 WL 11772
CourtUnited States Bankruptcy Court, E.D. Pennsylvania
DecidedFebruary 19, 1988
Docket18-17839
StatusPublished
Cited by16 cases

This text of 82 B.R. 747 (Temp-Way Corp. v. R.M. Shoemaker Co. (In Re Temp-Way Corp.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Temp-Way Corp. v. R.M. Shoemaker Co. (In Re Temp-Way Corp.), 82 B.R. 747, 1988 Bankr. LEXIS 210, 1988 WL 11772 (Pa. 1988).

Opinion

OPINION

DAVID A. SCHOLL, Bankruptcy Judge.

A. INTRODUCTION AND PROCEDURAL HISTORY

This is an adversarial proceeding in which a contracting firm operating as a Chapter 11 debtor-in-possession sought to collect five separate and apparently unrelated accounts receivable from five Defendants. All that remains before us for disposition is a dispute between the Debtor, a sub-contractor in the construction of a facility for the United Parcel Service (hereinafter referred to as “UPS”) in West Chester, Pennsylvania, and R.M. SHOEMAKER COMPANY, the general contractor on the project (hereinafter referred to as “the Defendant”). The specific dispute revolves around the meaning and enforci-bility of a particular clause in the sub-contract. The general contractor argues that this clause allows it to withhold payment from the Debtor unless and until the Debt- or pays the materialmen on the project. We believe that the clause does so provide and is enforcible against the Debtor. Therefore, we shall grant the general contractor’s request to pay most of the sums sought by the Debtor directly to the mate-rialmen.

The underlying Chapter 11 case was filed by the Debtor on April 1, 1987. The instant adversary proceeding, commenced on August 21, 1987, is one of several such proceedings filed by the Debtor to collect accounts receivable. The odd feature of these proceedings is that, in each, the defendants are named in clusters of five parties which appear to have no relationship to each other. Thus, in this proceeding, five defendants are named, and yet there is no apparent connection between the claims against the Defendant and the other parties named as defendants other than the fact that the Debtor has claims against them all. Rather remarkably, no party moved to sever the claims against it from the others. However, upon motion by two of the other defendants named herein, JOHN S. McQUADE CO. and NASON & CULLEN, INC., the District Court, on October 26, 1987, withdrew the reference to this court of the Debtor’s claims against them. A default judgment was entered against another, WALTERS MECHANICAL. The dispute with the final defendant, W.S. CUMLY & SONS, was reported settled. None of the dispositions of the Debtor’s claims against any of the co-defendants has had any perceptible impact on the Debtor’s claim against the Defendant.

There have, however, been other proceedings before us which do bear a relationship to the UPS project and these parties. On December 17, 1987, we issued a written Opinion in Adversary No. 87-0785S, 80 B.R. 699, a proceeding initiated against the Debtor and the Defendant by a materialman, in which we required the Debtor to forfeit the proceeds of a joint check agreement to the materialman. Another almost identical proceeding, instituted by another materialman in district court and transferred to this court as Adversary No. 88-0007S, constituted part of the sum in issue here. Given our disposition in Adversary No. 87-0785S, 80 B.R. 699, the Debtor has withdrawn its claim as to that *749 portion of the sum in question involving a joint-check agreement with that material-man, and those involving several similar much smaller joint-check agreements.

The relevant portion of the instant portion of the instant proceeding came before us for trial on January 7, 1988. At that time, per the parties’ agreement, we issued an Order directing them to prepare a Stipulation of Facts which would constitute a case stated and Briefs supporting their respective positions thereafter. Unfortunately, the parties could not agree on the wording of the entire Stipulation, and we were compelled to conduct a trial on January 27, 1988. At that time, the principals of each of the parties testified as to their particular understanding of the contract clause in issue. Thereafter, the parties submitted Briefs on February 5, 1988, and February 12, 1988.

Although most of the facts were indeed the subject matter of the written Stipulation, we are required by Bankruptcy Rule 7052 and Federal Rule of Civil Procedure 52(a) to submit our result in the form of Findings of Fact (much of what will incorporate the parties’ Stipulation), Conlusions of Law, and a Discussion.

B. FINDINGS OF FACT

1. The Defendant was the general contractor in the construction of a Parcel Distribution Center for UPS in West Chester, Pensylvania. The Debtor was a subcontractor on the UPS Project, furnishing and installing all heating, ventilation, air conditioning equipment, and gas piping to the facility constructed.

2. The original contract price for the Subcontract, dated May 28, 1986, was $398,000.00, but this figure was reduced by certain payments by the Defendant, including the joint checks in issue in Adversary No. 88-0007S. The amount presently at issue is agreed to be only $45,831.53.

3. The parties also agree that, since the Debtor has given a warranty on the work it performed which extends until May, 1988, it is reasonable for the Defendant to withhold $5,000.00 from any final payment until the expiration of the warranty period.

4. In issue are obligations of the Debtor to six materialmen on the UPS project, none of which had joint check arrangements with other parties hereto and which remain unpaid in amounts totalling $42,-820.59.

5. These six materialmen have put the Defendant on notice that they have not been paid by the Debtor, and they have sent it copies of their invoices or billing information.

6. The Defendant is withholding final payment to the Debtor because it claims that the Debtor failed to satisfy certain alleged requirements of Article VII of the subcontract, including the Debtor’s failures to supply a final invoice and to furnish a final Release of Liens, which the Debtor has stated it would supply; and the Debt- or’s failure to furnish certification that it has paid all materialmen in connection with the Subcontract, which the Debtor stated that it will not supply and contends that it need not supply as a condition for payment.

7. Article VII of the Subcontract provi-desd as follows:

ARTICLE VII Final Payment. Final payment hereunder is subject to the following conditions: (1) The Subcontractor shall have delivered to the Contractor a written certification of the full performance of all of the Subcontractor’s obligations, including a schedule of all outstanding vendors accounts, under such Subcontract, together with such guarantees of the Subcontractor as may be called for under such Subcontract; and (2) The Architect shall have delivered to the Contractor and Owner a certificate of completion approving the work done and/or materials furnished, the full performance of the terms the Subcontract by the Subcontractor and the payment in full of the Subcontract price; and (3) Owner shall have accepted the Project; and (4) Subcontractor shall have submitted a fully executed Release of Liens on a form furnished by the Contractor.

8. Dennis Spellman, the President of the Debtor, testified that, although the Subcontract was a form prepared by the *750 Defendant, he had read and was aware of this particular provision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
82 B.R. 747, 1988 Bankr. LEXIS 210, 1988 WL 11772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/temp-way-corp-v-rm-shoemaker-co-in-re-temp-way-corp-paeb-1988.