Driftless Area Land Conservanc v. Michael Huebsch

CourtCourt of Appeals for the Seventh Circuit
DecidedAugust 11, 2020
Docket20-1350
StatusPublished

This text of Driftless Area Land Conservanc v. Michael Huebsch (Driftless Area Land Conservanc v. Michael Huebsch) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Driftless Area Land Conservanc v. Michael Huebsch, (7th Cir. 2020).

Opinion

In the

United States Court of Appeals For the Seventh Circuit ____________________ No. 20-1350 DRIFTLESS AREA LAND CONSERVANCY and WISCONSIN WILDLIFE FEDERATION, Plaintiffs-Appellees,

v.

MICHAEL HUEBSCH, et al., Defendants-Appellees.

APPEAL OF: AMERICAN TRANSMISSION COMPANY LLC, et al., Intervenors-Defendants-Appellants. ____________________

Appeal from the United States District Court for the Western District of Wisconsin. No. 19-cv-1007-wmc — William M. Conley, Judge. ____________________

SUBMITTED JULY 2, 2020 — DECIDED AUGUST 11, 2020 ____________________

Before SYKES, Chief Judge, and FLAUM and ROVNER, Circuit Judges. SYKES, Chief Judge. The Wisconsin Public Service Com- mission issued a permit authorizing the construction of a $500 million electricity transmission line in southwestern 2 No. 20-1350

Wisconsin. Two environmental groups sued the Commis- sion to invalidate the permit. The permit holders moved to intervene to protect their interest in the permit; without it the power line cannot be built. The district court denied the motion, and the permit holders appealed. Briefing was completed at the end of June, and we set the case for oral argument on September 22, 2020. The permit holders moved for expedited review without oral argument; they want an earlier ruling because the case continues without them in the district court. The environmental groups responded in opposition, and the matter is ready for decision. We grant the motion. The briefs and record adequately address the single issue raised on appeal, and oral argument would not significantly assist the court. See FED. R. APP. P. 34(a)(2)(C). The case is submitted on the briefs, and we now reverse the district court. The permit holders are enti- tled to intervene under Rule 24(a)(2) of the Federal Rules of Civil Procedure. In many respects this is a paradigmatic case for intervention as of right. I. Background The plaintiffs are two Wisconsin environmental groups, Driftless Area Land Conservancy and Wisconsin Wildlife Federation. The defendants are the Wisconsin Public Service Commission of Wisconsin and its three commissioners (collectively, “the Commission”). The Commission regulates public utilities in the state. Two of the proposed interve- nors—American Transmission Company LLC and ITC Midwest LLC—are Wisconsin electric-power utilities. The No. 20-1350 3

third, Dairyland Power Cooperative, is a cooperative associ- ation that furnishes electricity to its members. In April 2018 the two utilities and the cooperative filed an application with the Commission for permission to construct a high-voltage transmission line running from Madison through the southwestern part of the state and ending in Dubuque County, Iowa. A project of this type is subject to heavy regulatory oversight and requires a special permit from the Commission known as a “certificate of public convenience and necessity.” WIS. STAT. § 196.491(3). The two utilities each own 45.5% of the project; the coopera- tive owns the remaining 9%. (We refer to the utilities and the cooperative collectively as “the transmission companies.”) The estimated cost of the project is $500 million. The permitting process requires a “class 1” contested case hearing. Id. § 227.01(3)(a). An exhaustive administrative proceeding ensued, spanning almost 18 months and draw- ing more than 50 intervenors. At the end of September 2019, the Commission approved the project and issued a permit authorizing the transmission companies to construct the proposed power line and acquire easements through emi- nent domain as necessary to complete construction. In December 2019 Driftless Area Land Conservancy and the Wisconsin Wildlife Federation filed this lawsuit against the Commission seeking to invalidate the permit. Both groups had participated in the permit proceedings as inter- venors in opposition, but their views obviously did not carry the day. The complaint raises three constitutional claims under 42 U.S.C. § 1983. The first alleges that the adjudicative process was tainted by the appearance of bias because two of the three commissioners had apparent conflicts of interest, 4 No. 20-1350

depriving the plaintiffs and their members of due process. The second and third claims challenge the authorization to use eminent domain as an unlawful taking of private prop- erty in violation of the Fifth Amendment’s takings clause. The Commission filed a motion to dismiss in January 2020. A week later the transmission companies moved to intervene, seeking intervention as of right under Rule 24(a)(2), or alternatively, permissive intervention under Rule 24(b). As required by Rule 24(c), they tendered pro- posed pleadings—answers and a motion to dismiss—with the intervention motion. The district judge rejected intervention as of right, con- cluding that the transmission companies and the Commis- sion have the same goal—dismissal of the lawsuit—and the Commission adequately represents that shared objective. The judge also declined to authorize permissive interven- tion, saying that adding the transmission companies as parties would “almost certainly and needlessly complicate and delay this case.” The judge denied the motion without prejudice and invited the transmission companies to renew their request if “a concrete, substantive conflict or actual divergence of interests should emerge” later in the litigation. Alternatively, he invited a “standby” application to inter- vene—essentially a placeholder motion that could be acti- vated if circumstances changed. See Solid Waste Agency of N. Cook Cty. v. U.S. Army Corps of Eng’rs (SWANCC), 101 F.3d 503, 509 (7th Cir. 1996). Not content to rely on governmental regulators to protect their $500 million private investment, the transmission companies appealed. No. 20-1350 5

II. Discussion A. Appellate Jurisdiction We begin by addressing a skirmish over appellate juris- diction. 1 It will not take long. It is well established that “from the perspective of a disappointed prospective intervenor, the denial of a motion to intervene is the end of the case, so an order denying intervention is a final, appealable decision under 28 U.S.C. § 1291.” CE Design, Ltd. v. Cy’s Crab House N., Inc., 731 F.3d 725, 730 (7th Cir. 2013). Notwithstanding this rule, the plaintiffs moved to dismiss for lack of appellate jurisdiction, arguing that the judge’s order is not final be- cause he left open the possibility of a new intervention motion if things change later in the litigation. The possibility of a new motion if circumstances change does not block an immediate appeal. The contingency that the judge has in mind might never arise, leaving the trans- mission companies on the sidelines of the litigation without appellate review of their intervention claim. Nor does the incantation of the words “without prejudice” automatically defeat finality; what matters is that the judge addressed the substantive merits of the intervention motion and conclu- sively denied it, freezing the transmission companies out of the case. See United States v. City of Milwaukee, 144 F.3d 524, 531 n.14 (7th Cir. 1998). Finally, the judge’s invitation to file a

1 There is also a minor debate about standing. We do not understand why.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Driftless Area Land Conservanc v. Michael Huebsch, Counsel Stack Legal Research, https://law.counselstack.com/opinion/driftless-area-land-conservanc-v-michael-huebsch-ca7-2020.