National Wildlife Refuge Association v. American Transmission Company LLC

Court of Appeals for the Seventh Circuit·Decided July 19, 2023·No. 22-1347·Published

Opinion

In the

United States Court of Appeals For the Seventh Circuit

Nos. 22-1347, 22-1709 & 22-1737 DRIFTLESS AREA LAND CONSERVANCY, et al., Plaintiffs-Appellees, Cross-Appellants,

v.

RURAL UTILITIES SERVICE, et al., Defendants-Appellants, Cross-Appellees,

and

AMERICAN TRANSMISSION COMPANY LLC, ITC MIDWEST LLC, and DAIRYLAND POWER COOPERATIVE, Intervening Defendants-Appellants, Cross-Appellees.

Appeals from the United States District Court for the Western District of Wisconsin.

Nos. 21-cv-096-wmc & 21-cv-306-wmc — William M. Conley, Judge.

ARGUED SEPTEMBER 28, 2022 — DECIDED JULY 19, 2023

Before EASTERBROOK, HAMILTON, and BRENNAN, Circuit Judges.

2 Nos. 22-1347, 22-1709 & 22-1737

EASTERBROOK, Circuit Judge. The Cardinal-Hickory Creek Project is a planned electric transmission line that would deliver wind energy from Iowa to Southern Wisconsin. The utility companies responsible for the line asked the Fish and Wildlife Service to allow construction across the Upper Mississippi River National Wildlife and Fish Refuge alongside a road and railroad that already cross the Refuge.

In October 2019 the Rural Utilities Service completed an environmental impact statement assessing this transmission line under the National Environmental Policy Act, 42 U.S.C. §4332(2)(C). The Fish and Wildlife Service and the Army Corps of Engineers adopted the statement for their own use in considering the project. In December 2019 the Fish and Wildlife Service determined that permi]ing the line to pass through the Refuge would be “compatible” with its “major purposes” under the Refuge Act. 16 U.S.C. §668dd(d)(1)(A). The agency issued a right-of-way permit in September 2020.

Several environmental advocacy groups sued, arguing that the permit violates the Refuge Act and that the environmental impact statement is deficient under the National Environmental Policy Act. While litigation was pending, the utility companies applied for an amended permit slightly altering the route, which still would largely parallel the road. They also asked the Fish and Wildlife Service to consider a land exchange under 16 U.S.C. §668dd(b)(3) as an alternative to the permit. While reviewing these new requests, the agency discovered that it had relied on incorrect easement documents in issuing its original compatibility determination. By a le]er dated August 27, 2021, it revoked the determination and permit . This le]er also promised to consider the proposed land

Nos. 22-1347, 22-1709 & 22-1737 3

exchange. Almost two years have passed, but the agency has not issued a new decision.

Despite the absence of an effective decision, the litigation continued. The district court entered a declaratory judgment that, under the Refuge Act, the agency’s compatibility determination could not support a crossing either by right of way (the rescinded decision) or land transfer (the pending proposal ). The court also vacated the Rural Utilities Service’s decision to adopt the environmental impact statement and remanded to the agency for further proceedings, although it declined to enjoin ongoing construction of the project on private land outside the Refuge. 580 F. Supp. 3d 588 (W.D. Wis. 2022). The agencies and utility companies appealed, and the advocacy groups cross-appealed from the denial of injunctive relief . (There were earlier appeals too, but the issues those decisions resolved do not affect the parties’ current disputes. See Driftless Area Land Conservancy v. Huebsch, 969 F.3d 742 (7th Cir. 2020); Driftless Area Land Conservancy v. Valcq, 16 F.4th 508 (7th Cir. 2021).)

We must first ensure that the district court had subjectma ]er jurisdiction. The utility company defendants maintain that the challenge to the revoked permit is moot.

A claim is moot “when the issues presented are no longer live or the parties lack a legally cognizable interest in the outcome . [This occurs] only when it is impossible for a court to grant any effectual relief whatever to the prevailing party.” Chafin v. Chafin, 568 U.S. 165, 172 (2013) (cleaned up). But a case does not inevitably become moot when a party chooses to stop the challenged conduct. Cessation implies mootness only when it is “absolutely clear” that the “allegedly wrongful behavior could not reasonably be expected to recur.” Friends 4 Nos. 22-1347, 22-1709 & 22-1737

of the Earth, Inc. v. Laidlaw Environmental Services (TOC), Inc., 528 U.S. 167, 190 (2000).

We presume that an agency acts in good faith when it alters its course of action. Ozinga v. Price, 855 F.3d 730, 734 (7th Cir. 2017). This does not end our inquiry, however. An agency’s decision to change course does not moot a lawsuit when the change is “not implemented by statute or regulation and could be changed again.” Sefick v. Gardner, 164 F.3d 370, 372 (7th Cir. 1998). That is the case here. Although the Fish and Wildlife Service has revoked the original compatibility determination, it has not promised never to issue a new permit for the crossing. Tellingly, the agency itself does not argue that the litigation has become moot.

The district court therefore had jurisdiction to review both the revoked right-of-way permit and the proposed land exchange under the Refuge Act. But jurisdiction alone does not allow a court to reach the merits. Final agency action also is essential to judicial review. See 5 U.S.C. §704 (part of the Administrative Procedure Act or APA).

“[T]wo conditions … generally must be satisfied for agency action to be ‘final’ under the APA.” Army Corps of Engineers v. Hawkes Co., 578 U.S. 590, 597 (2016). The challenged action must represent the “consummation” of an agency’s decisionmaking process and must determine “rights or obligations ”. Ibid. (citing BenneP v. Spear, 520 U.S. 154, 177–78 (1997)). In other words, §704 asks whether a “terminal event” has occurred. Salinas v. Railroad Retirement Board, 141 S. Ct. 691, 697 (2021).

In Hawkes the Supreme Court found that the Army Corps of Engineers’ determination that waters on the plaintiffs’

Nos. 22-1347, 22-1709 & 22-1737 5

property were subject to the Clean Water Act was a final agency action. This determination was the end of the agency’s decisionmaking process: it was issued “after extensive fact- finding” and was to remain valid for five years. 578 U.S. at 597–98. It was also “definitive”: plaintiffs were denied a safe harbor from liability under the Clean Water Act, even though the determination did not itself impose monetary liability. Id. at 598–600.

By contrast, the Fish and Wildlife Service’s current stance regarding the proposed transmission line does not meet the Court’s criteria of finality. The compatibility determination is not a final action. Even before it was rescinded, the determination was just a prerequisite to a permit rather than the end of the agency’s process. And although the right-of-way permit may have “consummated” the agency’s decisionmaking process while it stood, the agency has revoked it. A revoked permit lacks legal consequence. It neither allows nor forbids the challenged crossing. Ma]ers are back where they were before the permit issued: under consideration at the agency.

Once an agency has made a final decision, a reviewing court evaluates whether that decision is supported by substantial evidence. 5 U.S.C. §706(2)(E). In Hawkes the agency’s decision was issued after “extensive factfinding”, which gave the Court a record to review. That’s impossible here: now that the Fish and Wildlife Service has rescinded the compatibility determination and permit, the court lacks an administrative record. To determine whether a permit allowing the transmission line to cross the Refuge would be “compatible” with the Refuge’s “major purposes”, 16 U.S.C. §668dd(d)(1)(A), a court needs to evaluate the agency’s factual findings about compatibility , as well as any findings about the “major purposes” of 6 Nos. 22-1347, 22-1709 & 22-1737

Free access — add to your briefcase to read the full text and ask questions with AI

National Wildlife Refuge Association v. American Transmission Company LLC, (7th Cir. 2023).

National Wildlife Refuge Association v. American Transmission Company LLC (National Wildlife Refuge Association v. American Transmission Company LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Abbott Laboratories v. Gardner
387 U.S. 136 (Supreme Court, 1967)
Bennett v. Spear
520 U.S. 154 (Supreme Court, 1997)
John Sefick v. Richard Gardner
164 F.3d 370 (Seventh Circuit, 1998)
Chafin v. Chafin
133 S. Ct. 1017 (Supreme Court, 2013)
Citizens for Appropriate Rural v. Anthony Foxx
815 F.3d 1068 (Seventh Circuit, 2016)
U.S. Army Corps of Eng'rs v. Hawkes Co.
578 U.S. 590 (Supreme Court, 2016)
Timothy Ozinga v. Thomas E. Price
855 F.3d 730 (Seventh Circuit, 2017)
San Francisco Herring Ass'n v. Usdoi
946 F.3d 564 (Ninth Circuit, 2019)
Driftless Area Land Conservanc v. Michael Huebsch
969 F.3d 742 (Seventh Circuit, 2020)
Salinas v. Railroad Retirement Bd.
592 U.S. 188 (Supreme Court, 2021)
Driftless Area Land Conservanc v. Rebecca Valcq
16 F.4th 508 (Seventh Circuit, 2021)
Friends of Alaska Nat'l v. Debra Haaland
29 F.4th 432 (Ninth Circuit, 2022)