FRIEDMAN, Judge.
This case concerns the Downingtown Area School District’s (Downingtown) attempt to recover monies from the International Fidelity Insurance Company (IFIC) under a performance bond that IFIC issued to Kern Structural Enterprises (Kern) in connection with a contract between Downingtown and Kern. Kern had defaulted on the contract resulting in damages to Downingtown.
This is the second time this case comes before this court. Previously, we considered, and denied, IFIC’s appeal from an amended order of the Court of Common Pleas of Chester County (trial court) denying IFIC’s Motion for Partial Summary Judgment.
See Downingtown Area School District v. International Fidelity Insurance Company,
671 A.2d 782 (Pa.Cmwlth.1996). The matter subsequently was tried in November 1998, and the trial court issued its verdict on March 18, 1999. Presently before us are Downingtown and IFIC’s cross appeals from the trial court’s June 30, 2000 order denying Downing-town’s post-trial motion and modifying the verdict.
The underlying facts of the case are largely undisputed. On February 8, 1989, Downingtown entered into a structural steel contract (Contract) with Kern for the construction of the Shamona Creek Elementary School Project (Project). Under the Contract, Kern agreed to provide labor, materials, equipment and services necessary for the Project, and Kern was required to substantially complete its work by August 15, 1989.
(Trial ct. Findings of Fact, Nos. 3-4, 22; R.R. at 322a.) In the event that the work was not completed by this date, the Contract provided that Kern would be hable for liquidated damages for delay in addition to any other consequential losses that Downingtown might incur because of the delay. (Contract section 1.07, Modification of Article 8, Time, subparagraph 8.4.2; R.R. at 330a.)
As contractor for the Project, Kern, pursuant to its obligation under the Contract and under the Public Works Contractors’ Bond Law of 1967 (Bond Law),
furnished
Downingtown with a Performance Bond provided by its surety, IFIC. In its first paragraph, the Performance Bond bound Kern and IFIC to Downingtown for the Contract amount of $513,929.00. The Performance Bond also contained a statement incorporating by reference the Contract between Kern and Downingtown.
(R.R. at 381a.) Directly following this statement, the Performance Bond provided:
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor shall promptly and faithfully perform said Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
The Surety hereby waives notice of any alteration or extension of time made by the Owner.
Whenever Contractor shall be, and declared by Owner to be in default under the Contract, the Owner having performed Owner’s obligations thereunder, the Surety may promptly remedy the default, or shall promptly
(1) Complete the Contract
in accordance with its terms and conditions,
or
(2) Obtain a bid or bids for completing the Contract
in accordance with its terms and conditions,
and ... arrange for a contract between [the lowest responsible] bidder and Owner, and make available as Work progresses ... sufficient funds to pay the cost of completion less the balance of the contract price; but not exceeding,
including other costs and damages for which the Surety may be liable hereunder, the amount set forth in the first paragraph hereof.
The term “balance of the contract price,” as used in this paragraph, shall mean the total amount payable by Owner to Contractor under the Contract and any amendments thereto, less the amount properly paid by Owner to Contractor.
(R.R. at 332a) (emphasis added).
On May 23, 1989, Kern stopped work on the Project and notified Downingtown by letter that Kern was terminating the Contract, creating an immediate delay in the progress of the work. (Trial ct. Findings of Fact, Nos. 10, 12; R.R. at 339a.) In response, Downingtown formally declared Kern in default and advised it that Down-ingtown would proceed against Kern’s bonds and pursue other available legal remedies against Kern. (Trial ct. Findings of Fact, No. 11; R.R. at 336a.) Downingtown immediately put IFIC on notice of Kern’s default and repeatedly requested IFIC to intervene and address the resulting delay. In addition, other prime contractors on the Project put Downingtown on notice that Kern’s default would delay the Project. (Trial ct. Findings of Fact, No. 13-14.) In November 1991, Downingtown filed an action in the trial court against IFIC as a result of Kern’s default. In its complaint, Downing-
town sought damages for the difference between the cost of the Contract with Kern and the eventual cost to complete the project with another contractor. In addition to these damages, Downingtown also sought delay damages, liquidated damages and attorney’s fees.
On February 28, 1994, IFIC filed a Motion for Partial Summary Judgment. "While IFIC did not dispute its liability for the difference in contract price between Kern and the replacement contractor, it did dispute its liability for the additional damages claimed by Downingtown, asserting that these items were neither covered by the express language of the Performance Bond nor required by Bond Law.
The trial court denied IFIC’s Motion for Partial Summary Judgment as well as a subsequent Motion for Reconsideration,
and an appeal to this court followed. We were again asked to consider whether Downingtown, as a matter of law, can recover delay damages, liquidated damages, and attorney’s fees against IFIC under a Performance Bond issued pursuant to section 3 of the Bond Law, 8 P.S. § 193(a)(1), where the Performance Bond does not provide specifically for such remedies, but does incorporate the terms and conditions of the Contract providing for those damages. After examining the language of the applicable statute and the wording of the Performance Bond itself, we concluded that the terms of the Performance Bond may be sufficiently broad to extend coverage to damages beyond the price differential between Kerris Contract and the cost of completion with a different contractor. Because doubt remained as to whether such damages were unrecoverable under the Performance Bond, we held that IFIC was not entitled to judgment as a matter of law. Accordingly, we affirmed the trial court’s denial of IFIC’s Motion for Partial Summary Judgment and remanded the case for proceedings in accordance with our opinion.
See Downingtown.
Following remand, on March 18, 1999, the trial court found that IFIC was only
Free access — add to your briefcase to read the full text and ask questions with AI
FRIEDMAN, Judge.
This case concerns the Downingtown Area School District’s (Downingtown) attempt to recover monies from the International Fidelity Insurance Company (IFIC) under a performance bond that IFIC issued to Kern Structural Enterprises (Kern) in connection with a contract between Downingtown and Kern. Kern had defaulted on the contract resulting in damages to Downingtown.
This is the second time this case comes before this court. Previously, we considered, and denied, IFIC’s appeal from an amended order of the Court of Common Pleas of Chester County (trial court) denying IFIC’s Motion for Partial Summary Judgment.
See Downingtown Area School District v. International Fidelity Insurance Company,
671 A.2d 782 (Pa.Cmwlth.1996). The matter subsequently was tried in November 1998, and the trial court issued its verdict on March 18, 1999. Presently before us are Downingtown and IFIC’s cross appeals from the trial court’s June 30, 2000 order denying Downing-town’s post-trial motion and modifying the verdict.
The underlying facts of the case are largely undisputed. On February 8, 1989, Downingtown entered into a structural steel contract (Contract) with Kern for the construction of the Shamona Creek Elementary School Project (Project). Under the Contract, Kern agreed to provide labor, materials, equipment and services necessary for the Project, and Kern was required to substantially complete its work by August 15, 1989.
(Trial ct. Findings of Fact, Nos. 3-4, 22; R.R. at 322a.) In the event that the work was not completed by this date, the Contract provided that Kern would be hable for liquidated damages for delay in addition to any other consequential losses that Downingtown might incur because of the delay. (Contract section 1.07, Modification of Article 8, Time, subparagraph 8.4.2; R.R. at 330a.)
As contractor for the Project, Kern, pursuant to its obligation under the Contract and under the Public Works Contractors’ Bond Law of 1967 (Bond Law),
furnished
Downingtown with a Performance Bond provided by its surety, IFIC. In its first paragraph, the Performance Bond bound Kern and IFIC to Downingtown for the Contract amount of $513,929.00. The Performance Bond also contained a statement incorporating by reference the Contract between Kern and Downingtown.
(R.R. at 381a.) Directly following this statement, the Performance Bond provided:
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor shall promptly and faithfully perform said Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
The Surety hereby waives notice of any alteration or extension of time made by the Owner.
Whenever Contractor shall be, and declared by Owner to be in default under the Contract, the Owner having performed Owner’s obligations thereunder, the Surety may promptly remedy the default, or shall promptly
(1) Complete the Contract
in accordance with its terms and conditions,
or
(2) Obtain a bid or bids for completing the Contract
in accordance with its terms and conditions,
and ... arrange for a contract between [the lowest responsible] bidder and Owner, and make available as Work progresses ... sufficient funds to pay the cost of completion less the balance of the contract price; but not exceeding,
including other costs and damages for which the Surety may be liable hereunder, the amount set forth in the first paragraph hereof.
The term “balance of the contract price,” as used in this paragraph, shall mean the total amount payable by Owner to Contractor under the Contract and any amendments thereto, less the amount properly paid by Owner to Contractor.
(R.R. at 332a) (emphasis added).
On May 23, 1989, Kern stopped work on the Project and notified Downingtown by letter that Kern was terminating the Contract, creating an immediate delay in the progress of the work. (Trial ct. Findings of Fact, Nos. 10, 12; R.R. at 339a.) In response, Downingtown formally declared Kern in default and advised it that Down-ingtown would proceed against Kern’s bonds and pursue other available legal remedies against Kern. (Trial ct. Findings of Fact, No. 11; R.R. at 336a.) Downingtown immediately put IFIC on notice of Kern’s default and repeatedly requested IFIC to intervene and address the resulting delay. In addition, other prime contractors on the Project put Downingtown on notice that Kern’s default would delay the Project. (Trial ct. Findings of Fact, No. 13-14.) In November 1991, Downingtown filed an action in the trial court against IFIC as a result of Kern’s default. In its complaint, Downing-
town sought damages for the difference between the cost of the Contract with Kern and the eventual cost to complete the project with another contractor. In addition to these damages, Downingtown also sought delay damages, liquidated damages and attorney’s fees.
On February 28, 1994, IFIC filed a Motion for Partial Summary Judgment. "While IFIC did not dispute its liability for the difference in contract price between Kern and the replacement contractor, it did dispute its liability for the additional damages claimed by Downingtown, asserting that these items were neither covered by the express language of the Performance Bond nor required by Bond Law.
The trial court denied IFIC’s Motion for Partial Summary Judgment as well as a subsequent Motion for Reconsideration,
and an appeal to this court followed. We were again asked to consider whether Downingtown, as a matter of law, can recover delay damages, liquidated damages, and attorney’s fees against IFIC under a Performance Bond issued pursuant to section 3 of the Bond Law, 8 P.S. § 193(a)(1), where the Performance Bond does not provide specifically for such remedies, but does incorporate the terms and conditions of the Contract providing for those damages. After examining the language of the applicable statute and the wording of the Performance Bond itself, we concluded that the terms of the Performance Bond may be sufficiently broad to extend coverage to damages beyond the price differential between Kerris Contract and the cost of completion with a different contractor. Because doubt remained as to whether such damages were unrecoverable under the Performance Bond, we held that IFIC was not entitled to judgment as a matter of law. Accordingly, we affirmed the trial court’s denial of IFIC’s Motion for Partial Summary Judgment and remanded the case for proceedings in accordance with our opinion.
See Downingtown.
Following remand, on March 18, 1999, the trial court found that IFIC was only
liable for completion costs that exceeded the Kern Contract price and issued its verdict awarding Downingtown $38,081.47. Relying solely on its own reading and interpretation of the Performance Bond, the trial court ruled that, as specified in the Performance Bond, IFIC was obligated to pay only “the costs of completion less the balance of the contract price.” As to the language immediately following this phrase, i.e., “but not exceeding, including other costs and damages for which [IFIC] may be liable hereunder, the amount set forth in the first paragraph hereof,” the trial court concluded that this merely set a cap on IFIC’s obligation but did not require IFIC to pay for other costs and damages, such as delay damages, caused by Kern.
However, the trial court noted that in this court’s earlier decision in
Downing-town,
we construed the same language as indicating that IFIC
may
be liable for consequential damages, including delay damages, and the trial court conceded that this court’s opinion posed a stumbling block to his contrary interpretation and ruling.
(See
Trial ct. op. at 10.) Bearing in mind this apparent contradiction, the trial court, despite doubting Downing-town’s entitlement to any award of delay damages, went on to find that Kern’s default caused a delay which, in turn, caused damages to Downingtown, and the trial court determined the amount of these delay damages.
Subsequently, both Downingtown and IFIC filed motions for post-trial relief requesting the trial court to modify the verdict. Downingtown requested that the trial court find IFIC liable for delay damages resulting from Kern’s default and direct judgment for Downingtown in the amount of $809,392.00. IFIC contended that the trial court incorrectly held that the Project was delayed due to Kern’s default and, alternatively, failed to apportion the amount of delay caused by Kern. Upon consideration of the motions, the trial court issued its June 30, 2000 order, which provides:
AND NOW, June 30, 2000, upon consideration of Plaintiffs [Downingtown] post trial motions to amend the verdict in this matter, I HEREBY DENY said motion.
Upon consideration of Defendant’s [IFIC] post trial motions to amend the verdict in this matter, I HEREBY MODIFY the verdict to provide that, in the event that a reviewing court finds Defendant [IFIC] liable for “delay damages,” Defendant [IFIC] should be responsible for $191,121.37 in delay damages. This is roughly 59% of total delay damages, including the chánge orders and the arbitration claims, but excluding attorney’s fees. This percentage corresponds to the proportion of the total delay (62 of 104 days) attributable to the
default by Kern Structural Steel Company.
(Attachment to Downingtown’s brief.)
The parties now have filed cross-appeals from this order. Downingtown appeals from the denial of its motion for post-trial relief, asserting that this court, in our decision in
Downingtown,
interpreted the Performance Bond to hold IFIC hable for
all
damages due to Kern’s default on the Contract. IFIC appeals from the trial court’s modification of its March 18, 1999 order, contending that the record establishes that Kern caused no delay to the Project. The appeals have been consolidated for hearing before this court.
First, we consider Downingtown’s appeal, in which Downingtown argues that the trial court improperly interpreted the language of the Performance Bond to exclude payment of costs and damages by IFIC other than the costs of completion of the Contract. In support of this position, Downingtown contends that this court already has decided the primary legal issue in this case in its favor, specifically, that the award of delay damages, liquidated damages, attorney’s fees, interest and costs against IFIC is proper under the Performance Bond here. According to Downingtown, the plain meaning of the Performance Bond, as previously interpreted by this court, obligates IFIC to pay delay damages suffered by Downingtown as a result of Kern’s default. Referring to our holding in
Downingtown
that the “Performance Bond
may
be sufficiently broad to extend coverage to damages beyond the price differential between Kern’s Contract and the cost of completion with a different contractor,” Downingtown maintains that the trial court should have entered judgment for delay damages once it determined that (1) Kern caused the delay; (2) the Kern Contract obligated Kern to pay delay damages; and (3) IFIC bonded Kern.
Initially, we note our disagreement with Downingtown’s premise. In
Downing-town,
we held that summary judgment in favor of IFIC was inappropriate because doubt existed as to whether delay damages were unrecoverable under the Performance Bond. However, we did not hold that IFIC was obligated to pay delay damages under the Performance Bond; thus, Downingtown still had the burden of proving at trial that the delay damages alleged were both applicable
and
recoverable.
After reviewing the Performance Bond at issue here, the trial court determined that “as a matter of plain English, the [Performance Bond] does not make [IFIC] liable for delay damages caused by [Kern].” (Trial ct. op. at 9.) Upon careful consideration of the language in the Performance Bond, we agree with both the trial court’s result and its reasoning. Indeed, we adopt that reasoning with respect to the interpretation of IFIC’s obligations as set forth in the Performance Bond. To that end, we quote the following from the trial court opinion:
The underlying [C]ontract between Kern and Downingtown ... clearly makes Kern liable for “consequential losses and damages that [Downingtown] may incur by reason of such delay.” However, the contract with IFIC is not nearly so clear....
In the [Performance B]ond, [IFIC] has the obligation, in the event of a default
by [Kern], of either completing the [C]ontr"act itself, or obtaining bids for completion of the [Contract, either itself or jointly with [Downingtown], at [Downingtown’s] election.
If the latter option is chosen, [IFIC] then is responsible to “make available as work progresses ... sufficient funds to pay the
cost of completion
less the balance of the [C]ontract price.” That sentence then goes on to
limit[
]
the amount payable as “cost[ ] of completion” as follows: “but not
exceeding, including other costs and damages
for which [IFIC] may be hable hereunder, the amount set forth in the first paragraph hereof.[
] The term “balance of the contract price” is then defined as the price of the underlying contract less any amounts properly paid to the defaulting contractor.
The way I read this particular series of statements, [IFIC’s] underlying obligation is to pay the cost
of completion.
The clause beginning with “but not exceeding” simply places a cap on [IFIC’s] obligation. Granted, it does include as part of that cap “other costs and damages for which [IFIC] may be liable. However, I still think that as a matter of plain English, the [Performance Bond] does not make [IFIC] hable for delay damages caused by [Kern], I think it is significant that the [Performance B]ond says costs for which
[IFIC]
may be liable, and not for which
[Kern]
may be liable. [IFIC’s] obligation is to provide “sufficient funds to pay the cost of completion less the balance of the [C]on-tract.” I see no other way of interpreting the term “cost of completion” other than as the cost of obtaining a substitute contractor who will actually complete the job. This figure is apparently $21,070.00, the amount by which the Fisher Contract exceeded the Kern Contract.
The interpretation that I have adopted tends to bring the contract language into conformance with the statutory language set forth at 8 P.S. § 193(a)(1), which requires the posting of “[a] performance bond at 100% of the contract amount, conditioned upon the faithful performance of the contract in accordance with the plans, specifications and conditions of the contract.” The [Bond Law] doesn’t say anything about consequential damages or damages due to delay.[
]
(Trial ct. op. at 9-10) (emphasis in original). In other words, because the Performance Bond does not specifically obligate IFIC to cover claims that Downingtown may have against Kern under the Contract, IFIC’s liability is capped at the cost of Contract completion.
Accordingly, we affirm the trial court’s order.
LEADBETTER, J., did not participate in the decision in this case.
ORDER
AND NOW, this 21st day of March, 2001, the order of the Court of Common Pleas of Chester County, dated June 20, 2000, is hereby affirmed, and we deny the appeals filed by the Downingtown Area School District and the International Fidelity Insurance Company, respectively.