Downingtown Area School District v. International Fidelity Insurance

769 A.2d 560, 2001 Pa. Commw. LEXIS 175
CourtCommonwealth Court of Pennsylvania
DecidedMarch 21, 2001
StatusPublished
Cited by5 cases

This text of 769 A.2d 560 (Downingtown Area School District v. International Fidelity Insurance) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Downingtown Area School District v. International Fidelity Insurance, 769 A.2d 560, 2001 Pa. Commw. LEXIS 175 (Pa. Ct. App. 2001).

Opinion

FRIEDMAN, Judge.

This case concerns the Downingtown Area School District’s (Downingtown) attempt to recover monies from the International Fidelity Insurance Company (IFIC) under a performance bond that IFIC issued to Kern Structural Enterprises (Kern) in connection with a contract between Downingtown and Kern. Kern had defaulted on the contract resulting in damages to Downingtown.

*561 This is the second time this case comes before this court. Previously, we considered, and denied, IFIC’s appeal from an amended order of the Court of Common Pleas of Chester County (trial court) denying IFIC’s Motion for Partial Summary Judgment. See Downingtown Area School District v. International Fidelity Insurance Company, 671 A.2d 782 (Pa.Cmwlth.1996). The matter subsequently was tried in November 1998, and the trial court issued its verdict on March 18, 1999. Presently before us are Downingtown and IFIC’s cross appeals from the trial court’s June 30, 2000 order denying Downing-town’s post-trial motion and modifying the verdict.

The underlying facts of the case are largely undisputed. On February 8, 1989, Downingtown entered into a structural steel contract (Contract) with Kern for the construction of the Shamona Creek Elementary School Project (Project). Under the Contract, Kern agreed to provide labor, materials, equipment and services necessary for the Project, and Kern was required to substantially complete its work by August 15, 1989. 1 (Trial ct. Findings of Fact, Nos. 3-4, 22; R.R. at 322a.) In the event that the work was not completed by this date, the Contract provided that Kern would be hable for liquidated damages for delay in addition to any other consequential losses that Downingtown might incur because of the delay. (Contract section 1.07, Modification of Article 8, Time, subparagraph 8.4.2; R.R. at 330a.) 2

As contractor for the Project, Kern, pursuant to its obligation under the Contract and under the Public Works Contractors’ Bond Law of 1967 (Bond Law), 3 furnished *562 Downingtown with a Performance Bond provided by its surety, IFIC. In its first paragraph, the Performance Bond bound Kern and IFIC to Downingtown for the Contract amount of $513,929.00. The Performance Bond also contained a statement incorporating by reference the Contract between Kern and Downingtown. 4 (R.R. at 381a.) Directly following this statement, the Performance Bond provided:

NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor shall promptly and faithfully perform said Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
The Surety hereby waives notice of any alteration or extension of time made by the Owner.
Whenever Contractor shall be, and declared by Owner to be in default under the Contract, the Owner having performed Owner’s obligations thereunder, the Surety may promptly remedy the default, or shall promptly
(1) Complete the Contract in accordance with its terms and conditions, or
(2) Obtain a bid or bids for completing the Contract in accordance with its terms and conditions, and ... arrange for a contract between [the lowest responsible] bidder and Owner, and make available as Work progresses ... sufficient funds to pay the cost of completion less the balance of the contract price; but not exceeding, including other costs and damages for which the Surety may be liable hereunder, the amount set forth in the first paragraph hereof. The term “balance of the contract price,” as used in this paragraph, shall mean the total amount payable by Owner to Contractor under the Contract and any amendments thereto, less the amount properly paid by Owner to Contractor.

(R.R. at 332a) (emphasis added).

On May 23, 1989, Kern stopped work on the Project and notified Downingtown by letter that Kern was terminating the Contract, creating an immediate delay in the progress of the work. (Trial ct. Findings of Fact, Nos. 10, 12; R.R. at 339a.) In response, Downingtown formally declared Kern in default and advised it that Down-ingtown would proceed against Kern’s bonds and pursue other available legal remedies against Kern. (Trial ct. Findings of Fact, No. 11; R.R. at 336a.) Downingtown immediately put IFIC on notice of Kern’s default and repeatedly requested IFIC to intervene and address the resulting delay. In addition, other prime contractors on the Project put Downingtown on notice that Kern’s default would delay the Project. (Trial ct. Findings of Fact, No. 13-14.) In November 1991, Downingtown filed an action in the trial court against IFIC as a result of Kern’s default. In its complaint, Downing- *563 town sought damages for the difference between the cost of the Contract with Kern and the eventual cost to complete the project with another contractor. In addition to these damages, Downingtown also sought delay damages, liquidated damages and attorney’s fees. 5

On February 28, 1994, IFIC filed a Motion for Partial Summary Judgment. "While IFIC did not dispute its liability for the difference in contract price between Kern and the replacement contractor, it did dispute its liability for the additional damages claimed by Downingtown, asserting that these items were neither covered by the express language of the Performance Bond nor required by Bond Law.

The trial court denied IFIC’s Motion for Partial Summary Judgment as well as a subsequent Motion for Reconsideration, 6 and an appeal to this court followed. We were again asked to consider whether Downingtown, as a matter of law, can recover delay damages, liquidated damages, and attorney’s fees against IFIC under a Performance Bond issued pursuant to section 3 of the Bond Law, 8 P.S. § 193(a)(1), where the Performance Bond does not provide specifically for such remedies, but does incorporate the terms and conditions of the Contract providing for those damages. After examining the language of the applicable statute and the wording of the Performance Bond itself, we concluded that the terms of the Performance Bond may be sufficiently broad to extend coverage to damages beyond the price differential between Kerris Contract and the cost of completion with a different contractor. Because doubt remained as to whether such damages were unrecoverable under the Performance Bond, we held that IFIC was not entitled to judgment as a matter of law. Accordingly, we affirmed the trial court’s denial of IFIC’s Motion for Partial Summary Judgment and remanded the case for proceedings in accordance with our opinion. See Downingtown.

Following remand, on March 18, 1999, the trial court found that IFIC was only *564

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Devereux Foundation v. Chester County IU No. 24
Commonwealth Court of Pennsylvania, 2015
Dexereux Foundation v. Chester County IU No. 24
Commonwealth Court of Pennsylvania, 2015
Wise Investments, Inc. v. Bracy Contracting, Inc.
232 F. Supp. 2d 390 (E.D. Pennsylvania, 2002)
Mattiola Construction Corp. v. Commercial Union Insurance
60 Pa. D. & C.4th 412 (Philadelphia County Court of Common Pleas, 2002)
North American Specialty Insurance v. Chichester School District
158 F. Supp. 2d 468 (E.D. Pennsylvania, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
769 A.2d 560, 2001 Pa. Commw. LEXIS 175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/downingtown-area-school-district-v-international-fidelity-insurance-pacommwct-2001.