Downingtown Area School District v. International Fidelity Insurance

671 A.2d 782, 1996 Pa. Commw. LEXIS 30
CourtCommonwealth Court of Pennsylvania
DecidedJanuary 30, 1996
StatusPublished
Cited by15 cases

This text of 671 A.2d 782 (Downingtown Area School District v. International Fidelity Insurance) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Downingtown Area School District v. International Fidelity Insurance, 671 A.2d 782, 1996 Pa. Commw. LEXIS 30 (Pa. Ct. App. 1996).

Opinion

FRIEDMAN, Judge.

The International Fidelity Insurance Company (IFIC) appeals from an amended order of the Court of Common Pleas of Chester County (trial court) denying IFIC’s Motion for Partial Summary Judgment.1

On February 8, 1989, the Downingtown Area School District (Downingtown) entered into a structural steel contract (Contract) with Kern Structural Enterprises (Kern) for the construction of the Shamona Creek Elementary School Project (Project). Under the Contract, Kern agreed to provide labor, materials, equipment and services necessary for the Project, and was required to substantially complete its work by August 15, 1989. (R.R. at 10.) In the event that the work was not completed by this date, the Contract provided that Kern would be liable for liquidated damages for delay in addition to any other consequential losses that Downingtown might incur because of the delay. (Contract section 1.07, Modification of Article 8, Time, subparagraph 8.4.2; R.R. at 38.)

As contractor for the Project, Kern, pursuant to its obligation under the Contract and under the Public Works Contractors’ Bond Law of 1967 (Bond Law),2 furnished Down-ingtown with a Performance Bond provided by its surety, IFIC. The Performance Bond contained a statement incorporating by reference the Contract between Kern and Down-ingtown, (R.R. at 17).3 Directly following this statement, the Performance Bond provided:

NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor shall promptly and faithfully perform said Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
[784]*784The Surety hereby waives notice of any alteration or extension of time made by the Owner.
Whenever Contractor shall be, and declared by Owner to be in default under the Contract, the Owner having performed Owner’s obligations thereunder, the Surety may promptly remedy the default, or shall promptly
(1) Complete the Contract in accordance with its terms and conditions, or
(2) Obtain a bid or bids for completing the Contract in accordance with its terms and conditions, and ... arrange for a contract between [the lowest responsible] bidder and Owner, and make available as Work progresses ... sufficient funds to pay the cost of completion less the balance of the contract price; but not exceeding, including other costs and damages for which the Surety may be liable hereunder, the amount set forth in the first paragraph hereof. The term “balance of the contract price,” as used in this paragraph, shall mean the total amount payable by Owner to Contractor under the Contract and any amendments thereto, less the amount properly paid by Owner to Contractor.

(R.R. at 18) (emphasis added).

On May 23, 1989, Kern stopped work on the Project and notified Downingtown by letter that Kern was terminating the Contract. (R.R. at 22.) In response, Downing-town formally declared Kern in default and advised it that Downingtown would proceed against Kerris bonds and pursue other available legal remedies against Kern. (R.R. at 26.) In November 1991, Downingtown filed an action in the trial court against IFIC as a result of Kern’s default. In its complaint, Downingtown sought damages for the difference between the cost of the Contract with Kern and the eventual cost to complete the project with another contractor. In addition to these damages, Downingtown also sought delay damages, liquidated damages and attorney’s fees.4

On February 28,1994, IFIC filed a Motion for Partial Summary Judgment. While IFIC did not dispute its liability for the difference in contract price between Kern and the replacement contractor, it did dispute its liability for the additional damages claimed by Downingtown, asserting that these items were neither covered by the express language of the Performance Bond nor required by Bond Law.

The trial court denied IFIC’s Motion for Partial Summary Judgment as well as a subsequent Motion for Reconsideration. The trial court agreed with IFIC that the only costs specified under the Performance Bond were for the completion of performance. However, while recognizing that the Performance Bond itself made no specific mention of delay damages, the trial court noted that the construction Contract, incorporated by reference into the Performance Bond, did contain provisions concerning responsibility for costs resulting from delay. The trial court then concluded that, because the law is not clear as to whether Downingtown may obtain delay damages from IFIC under these circumstances, IFIC was not entitled to summary judgment as a matter of law.

On appeal, we are again asked to consider whether Downingtown, as a matter of law, can recover delay damages, liquidated damages, and attorney’s fees against IFIC under a Performance Bond issued pursuant to sec[785]*785tion 3 of the Bond Law, 8 P.S. § 193(a)(1), where the Performance Bond does not provide specifically for such remedies, but does incorporate the terms and conditions of the Contract providing for those damages.

Initially, we note that our scope of review is limited to determining whether the trial court made an error of law or abused its discretion. Salerno v. LaBarr, 159 Pa.Cmwlth. 99, 632 A.2d 1002 (1993), appeal denied, 537 Pa. 655, 644 A.2d 740 (1994). Summary judgment should be granted only in those cases which are clear and free from doubt, and any doubt must be resolved in favor of the non-moving party. Pennsylvania Protection & Advocacy, Inc. v. Department of Education, 148 Pa.Cmwlth. 153, 609 A.2d 909 (1992). Moreover, summary judgment may be granted only where the moving party demonstrates that there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. Pa.R.C.P. No. 1035(b). Here, there are no disputed fact issues.

In support of its Motion for Partial Summary Judgment, IFIC maintains that in determining the extent of liability of a surety under a public construction surety bond, one must look to the language of the bond itself,

Salvino Steel and Iron Works, Inc. v. Fletcher & Sons, Inc., 398 Pa.Superior Ct. 86, 580 A.2d 853 (1990), appeal granted, 521 Pa. 625, 592 A.2d 45, appeal dismissed as improvidently granted, 529 Pa. 62, 601 A.2d 806 (1992), the general rule being that a surely assumes no obligations beyond those expressly enumerated in the bond. According to IFIC, because its Performance Bond does not specifically include provisions for IFIC to undertake the payment of delay damages, liquidated damages or attorney’s fees, but covers only those costs related to the completion of performance, IFIC’s liability under the Performance Bond extends only to the cost of Project completion. IFIC contends that caselaw supports this view.

First, IFIC cites several cases dealing with labor and material payment bonds issued pursuant to 8 P.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Govan v. Philadelphia Housing Authority
848 A.2d 193 (Commonwealth Court of Pennsylvania, 2004)
Hoke v. Elizabethtown Area School District
833 A.2d 304 (Commonwealth Court of Pennsylvania, 2003)
J.S. Ex Rel. H.S. v. Bethlehem Area School District
794 A.2d 936 (Commonwealth Court of Pennsylvania, 2002)
Bellefonte Area School District v. Deak
779 A.2d 1240 (Commonwealth Court of Pennsylvania, 2001)
North American Specialty Insurance v. Chichester School District
158 F. Supp. 2d 468 (E.D. Pennsylvania, 2001)
Downingtown Area School District v. International Fidelity Insurance
769 A.2d 560 (Commonwealth Court of Pennsylvania, 2001)
Township of Indiana v. Acquisitions & Mergers, Inc.
770 A.2d 364 (Commonwealth Court of Pennsylvania, 2001)
Cates Construction, Inc. v. Talbot Partners
980 P.2d 407 (California Supreme Court, 1999)
Wilson v. Philadelphia Housing Authority
735 A.2d 172 (Commonwealth Court of Pennsylvania, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
671 A.2d 782, 1996 Pa. Commw. LEXIS 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/downingtown-area-school-district-v-international-fidelity-insurance-pacommwct-1996.