North American Specialty Insurance v. Chichester School District

158 F. Supp. 2d 468, 2001 U.S. Dist. LEXIS 11626, 2001 WL 946589
CourtDistrict Court, E.D. Pennsylvania
DecidedMay 8, 2001
DocketCIV. A. 99-2394
StatusPublished
Cited by5 cases

This text of 158 F. Supp. 2d 468 (North American Specialty Insurance v. Chichester School District) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North American Specialty Insurance v. Chichester School District, 158 F. Supp. 2d 468, 2001 U.S. Dist. LEXIS 11626, 2001 WL 946589 (E.D. Pa. 2001).

Opinion

MEMORANDUM AND ORDER

SMITH, United States Magistrate Judge.

On February 9, 2001, following a bench trial in the above-referenced action, this Court entered judgment against Defendant and Counterclaim-Plaintiff Chiches-ter School District (the “School District”), in the amount of $407,801.44, and against Plaintiff and Counterclaim-Defendant North American Specialty Insurance Company (“NAS”), in the amount of $166,524.63. For judicial economy purposes, the Court bifurcated the School District’s claim for attorneys’ fees against NAS, and requested that both parties separately brief the issue. Having now considered both parties’ post-trial submissions on this issue, we find that the School District is entitled to an award of attorneys’ fees in an amount to be determined at a future evidentiary hearing.

I. FACTUAL AND PROCEDURAL BACKGROUND

Although the Court has already provided an extensive factual backdrop behind this litigation in the Findings of Fact and Conclusions of Law, an abridged version of the certain crucial events provides a useful framework for the issues presently before *470 us. This dispute arose out of defendant Chichester School District’s efforts to construct a new elementary school in Linwood Pennsylvania, 19601 (the “Linwood School”). According to the facts as found by this Court, the School District entered into a Construction Contract, on May 15, 1997, with Craft^Century Construction, Inc. (“CrafNCentury”) for the general construction work on the new school. In connection with that agreement, plaintiff North American Speciality Insurance Company, as surety for CrafL-Century, issued a Payment Bond and a Performance Bond in favor of the School District, as owner. By way of reference, the Performance Bond incorporated the terms of the Construction Contract.

Following several notices by the School District to both NAS and Craft-Century regarding Craffc-Century’s defaulted performance, the School District ultimately terminated the Contract by way of letter dated August 11, 1998. The letter requested immediate direction from NAS regarding the method by which the General Construction Contract for the New Linwood Elementary School would be fulfilled. In response, counsel for NAS, by letter dated August 18, 1998, indicated NAS’s election to proceed under paragraph 4.2 of the Performance Bond, which provided that the surety may undertake to perform and complete the construction contract itself, through its agents, or through independent contractors. The letter further noted that NAS’s election was subject to the School District and NAS entering into a Takeover Agreement, a proposed version of which NAS enclosed. The School District, however, declined to execute the Agreement as proposed by NAS.

Despite the School District’s refusal to sign the Takeover Agreement, NAS retained York Hunter, Inc. to complete the work under the Craft-Century Contract. NAS then provided funds, under the Performance Bond, to York Hunter, as well as to subcontractors, laborers, materialmen and consultants, in the amount of $375,365.90. In addition, it made payments totaling $896,856.73 under the Payment Bond to subcontractors, laborers and materialmen of CrafNCentury.

Notwithstanding numerous problems along the way, the project proceeded and was ultimately finished. Although the contractual date of substantial completion was set for July 28, 1998, the actual substantial completion date was not reached until September 7, 1998. On September 8, 1998, the new school opened, however, the School District complained that it was in deplorable condition and facilities were inadequate for the elementary school children. NAS, in turn, argued that it had properly performed its obligations and was thus entitled to appropriate compensation.

On May 10, 1999, with no resolution to the outstanding issues in sight, NAS commenced this action against the School District to recover various sums of money under the Contract. The School District responded to the Complaint on July 20, 1999, by way of Answer, Affirmative Defenses and Counterclaim, seeking, in part, damages for breach of contract arising from the default of CrafL-Century, including delay costs, incomplete work and/or damaged or improperly performed work and attorneys fees. Following a non-jury trial, this Court entered judgment on NAS’s complaint in the amount of $407,801.44, and on the School District’s counterclaim in the amount of $166,524.63. We bifurcated the School District’s claim for attorneys’ fees, to which we now turn.

II. DISCUSSION

The School District advances two theories for recovery of attorneys’ fees in this matter. First, it claims that, pursuant to *471 the underlying Contract between School District and Craft-Century Construction Company (“Craft-Century”), which is incorporated by reference into the Performance Bond, NAS is liable to the School District for attorneys’ fees. Second, it asserts that the Performance Bond itself provides for the School District to recover attorneys’ fees from NAS. The Court addresses each argument in turn.

A. Attorneys’ Fees Under the Crafh-Century/School District Contract.

The School District’s first argument focuses on the language of its Contract with CrafN-Century. It begins with the premise that, pursuant to the General and Supplementary Conditions, Crafk-Century bore responsibility for replacement of defective or nonconforming work. Paragraph 12.2 of those conditions addresses the contractor’s obligation to correct such work and lists attorneys’ fees among the recoverable expenses for a contractor who fails to meet such obligations. The School District then notes that paragraph 1 of NAS’s Performance Bond incorporates the Craft-Century Contract, thereby imposing the same degree of liability on NAS as borne by the School District. Relying on these various provisions, it goes on to conclude that NAS is accountable for attorneys’ fees incurred in the correction of nonconforming or defective work.

While, at first blush, this argument appears to follow a logical progression, closer examination of both the Contract language and the prevailing jurisprudence reveals that it is flawed. Under Pennsylvania law, “the liability of a surety is coextensive with that of the principal, and accordingly, a surety is bound to perform whatever may be legally required of its principal.” Diversified Utilities Sales, Inc. v. Monte Fusco Excavating Contracting Co., 71 F.R.D. 661, 664 (E.D.Pa.1976). However, it is equally well-established that a surety can be bound only to the extent and in the manner and under the circumstances set forth in his bond, and that he assumes no liability beyond those set forth in the suretyship agreement. See Tudor Development Group, Inc. v. U.S. Fidelity and Guar. Co., 692 F.Supp. 461, 463 (M.D.Pa.1988); Peter J. Mascara v. Milonas, 401 Pa. 632, 166 A.2d 15, 17 (1960); Nazareth Foundry and Machine Co. v. Marshall Machinery and Supply, 258 Pa. 558, 102 A. 268, 270 (1917); Downingtown Area Sch. Dist. v. International Fidelity Ins. Co., 769 A.2d 560

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
158 F. Supp. 2d 468, 2001 U.S. Dist. LEXIS 11626, 2001 WL 946589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-american-specialty-insurance-v-chichester-school-district-paed-2001.