Township of Indiana v. Acquisitions & Mergers, Inc.

770 A.2d 364, 2001 Pa. Commw. LEXIS 174
CourtCommonwealth Court of Pennsylvania
DecidedMarch 19, 2001
StatusPublished
Cited by13 cases

This text of 770 A.2d 364 (Township of Indiana v. Acquisitions & Mergers, Inc.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Township of Indiana v. Acquisitions & Mergers, Inc., 770 A.2d 364, 2001 Pa. Commw. LEXIS 174 (Pa. Ct. App. 2001).

Opinion

FLAHERTY, Judge.

ComServ, Inc. (ComServ) appeals from an order of the Court of Common Pleas of Allegheny County, (trial court) entering judgement against ComServ for breach of contract. In turn, the Township of Indiana (Township) cross-appeals from the trial court’s order limiting ComServ’s liability for its breach to $30,000. On November 6, 2000, this Court filed a previous opinion and order reversing the trial court’s order in the above captioned matter. Thereafter, the Township filed an application for reargument, which we denied but alternatively elected to grant reconsideration resulting in withdrawal of our prior opinion and order. On reconsideration, for the reasons set forth herein, we confirm our original determination to reverse.

Acquisitions and Mergers (A & M), a residential developer, sought and obtained approval from the Township to develop an up-scale residential community known as Hartwood Estates Garden Club (Hartwood Estates). A & M obtained financing agreements from Fayette Bank and Com-Serv to develop Hartwood Estates in three phases. A & M also entered into separate development agreements for Phases I, II, and III. The development agreements set forth the scale and nature of the development for each phase of Hartwood Estates including the road and infrastructure improvements, Township specifications, approval process and the requirement to obtain a performance bond or set-aside agreement with an approved financial institution. The performance bond or set-aside requirement is intended to assure the Township that the lender will provide the Township with sufficient funds to complete the infrastructure improvements in the event that the developer fails to timely complete the project. For its part, the Township agreed to assume control and maintenance responsibility for the roads and sewers system within Hartwood Estates after A & M completed construction in accordance with the approved specifications.

Fayette Bank handled the Phase I loan and set aside agreement and ComServ handled the Phase II and III loans and set aside agreements (Set Aside Agreements). The Phase I transactions are not at issue on appeal. 1 As required under the terms of the Phase II Development *368 Agreement, in February 1990, the Township, A & M and ComServ entered into the Phase II Set Aside Agreement. Com-Serv agreed to reserve $119,647.00 from A & M’s total development loan as “pledged funds” to ensure that these loan proceeds would be available for the Township to complete the infrastructure work should A & M fail to timely complete the work. The terms of the Phase II Set Aside Agreement specified that ComServ would incrementally disburse these pledged funds to A & M commensurate with the Township engineer’s approval of portions of the infrastructure work. ComServ was not to disburse any funds without documentation reflecting the Township’s approval of a completed portion of the improvements. Additionally, the agreement provided that if within one year of the signing of the agreement, A & M had not completed and obtained Township approval of the Phase II improvements, then “the Township will demand and receive payment of any balance remaining in the pledged funds and proceed to use the pledged funds [to complete the improvements] to the extent permitted by the funds so made available.” (Phase II Set Aside Agreement, paragraph 5, R.R. at 345a). In August 1991, these same parties entered into the Phase III Set Aside Agreement that contained virtually identical provisions but for the $95,018.11 figure representing the pledged funds reserved for the infrastructure improvements in Phase III of Hartwood Estates.

The sale of property within Hartwood Estates was slower than anticipated causing A & M to delay completion of some infrastructure improvements. The parties do not dispute that A & M failed to com-píete its obligations under the Phase II and III Development Agreements. Although A & M constructed the Phase II and III roads to the extent of applying the initial base paving coat, the final paving coat was never applied to the roads. At a July 1993 public meeting, complaints from Hartwood Estate residents regarding the condition of their neighborhood roads prompted A & M to propose to the Township application of the final paving coat to the Phase II and III base roadways. However, the Township informally requested that A & M not complete the final paving work until 80% of the Phase II and III lots had been developed to minimize damage from construction traffic. After two further years of delay and complaints from residents, the Township requested that A & M apply the final paving coat in the Fall of 1995. A & M initially agreed but eventually refused to complete the work after receiving higher than expected estimates for the remaining paving work. In July 1996, the Township declared A & M in breach of the Phase II and III Development Agreements. The Township then turned to its guarantor, ComServ, for release of construction loan funds pledged for completion of the final Phase II and III paving. ComServ informed the Township that all pledged funds had been released when A & M paid off its construction loans in early 1992. When ComServ stated that it could not produce the pledged funds, the Township filed a complaint in equity with the trial court seeking ComServ’s specific performance of the Phase II and III Set Aside Agreements.

Following hearings the trial court issued a decree nisi dated December 29, 1997. 2 *369 The trial court reached the following conclusions of law: 1) A & M breached its obligation under the Phase II and III Development Agreements to perform the final road paving and construct the sewer and retention pond improvements; 2) although the 80% rule imposed by the Township did not appear in any Township ordinance and was not contained in the Phase II and III Development or Set Aside Agreements, A & M could not now excuse its failure to perform since it made no effort to enforce its right to go forward with the paving work; 8) ComServ breached the provisions of the Phase II and III Set Aside Agreements by releasing the pledged funds on a periodic basis without requesting written approval of the Township for any partial release of pledged funds; arid 4) nothing in the language of the Phase II and III Development or Set Aside Agreements states that the agreements automatically terminate after one year, or that the Township is mandated to call upon Fayette Bank or ComServ to obtain any remaining available pledged funds after one year from the date of execution of said contract in the event of A & M’s failure to perform. (Trial Court Decision and Decree Nisi, December 29, 1997, Conclusions of Law at 4). The trial court’s decree nisi directed the Township to accept as Township property the roads, sewers, retention ponds and common areas of Hartwood Estates, and to perform all remedial repairs and paving work for all phases of Hartwood Estates. 3 The decree nisi also directed ComServ to make all pledged funds available to the Township for the Phase II and III road and infrastructure improvements. 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keith A. Pierce
W.D. Pennsylvania, 2023
PA PUC v. Delaware Valley Regional Economic Dev. Fund
Commonwealth Court of Pennsylvania, 2021
Allegheny Intermediate Unit v. East Allegheny School District
203 A.3d 371 (Commonwealth Court of Pennsylvania, 2019)
Osprey Portfolio, LLC v. Izett
67 A.3d 749 (Supreme Court of Pennsylvania, 2013)
Osprey Portfolio, LLC v. Izett
32 A.3d 793 (Superior Court of Pennsylvania, 2011)
Selinsgrove Area School District v. Lobar, Inc.
29 A.3d 137 (Commonwealth Court of Pennsylvania, 2011)
Meadow Run/Mountain Lake Park Ass'n v. Bantell
985 A.2d 989 (Commonwealth Court of Pennsylvania, 2009)
Com. v. CITIZENS ALLIANCE
983 A.2d 1274 (Commonwealth Court of Pennsylvania, 2009)
Commonwealth v. Citizens Alliance for Better Neighborhoods, Inc.
983 A.2d 1274 (Commonwealth Court of Pennsylvania, 2009)
White Deer Township v. Napp
929 A.2d 671 (Commonwealth Court of Pennsylvania, 2007)
Hui v. City of Philadelphia Parking Authority
913 A.2d 994 (Commonwealth Court of Pennsylvania, 2006)
Wilson Area School District v. Skepton
71 Pa. D. & C.4th 142 (Northampton County Court of Common Pleas, 2005)
Polkowski v. Huskie Portfolio, LLC (In Re Polkowski)
303 B.R. 585 (M.D. Pennsylvania, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
770 A.2d 364, 2001 Pa. Commw. LEXIS 174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/township-of-indiana-v-acquisitions-mergers-inc-pacommwct-2001.