Double M Construction, Inc. v. State Corp. Commission

202 P.3d 7, 288 Kan. 268, 2009 Kan. LEXIS 24
CourtSupreme Court of Kansas
DecidedFebruary 6, 2009
Docket100,312
StatusPublished
Cited by105 cases

This text of 202 P.3d 7 (Double M Construction, Inc. v. State Corp. Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Double M Construction, Inc. v. State Corp. Commission, 202 P.3d 7, 288 Kan. 268, 2009 Kan. LEXIS 24 (kan 2009).

Opinion

The opinion of the court was delivered by

Rosen, J.:

On transfer from the Court of Appeals, Double M Construction, Inc. appeals from a district court decision upholding a Kansas Corporation Commission (Corporation Commission) order imposing liability for failure to properly investigate the location of a natural gas pipeline before excavating.

The parties submitted stipulated facts to the Corporation Commission. In its responsive brief, the appellee Corporation Commission refers to a number of facts outside the stipulations. Parties are bound to their stipulations, however, and a trial court or appellate court must render judgment based on those stipulated facts. Klein v. Oppenheimer & Co., 281 Kan. 330, 336, 130 P.3d 569 (2006); Shade v. Wheatcraft Industries, Inc., 248 Kan. 531, 541, 809 P.2d 538 (1991).

The stipulated facts are as follows:

Double M is an Oklahoma corporation. Double M was acting as a subcontractor for Double J Pipeline, LLC from September 26, 2006, through September 29,2006. Double M provided excavation *270 service to Double J Pipeline in an area south of Mound Valley, Kansas, in rural Labette County.

Under the terms of the contract, Double J was the contractor. The contract provided that Double J was “to excavate under and around existing utilities.” The contract also provided that Double J was to “spot and expose line crossing ahead of equipment.” In addition, the contract contained the following clause: “Double M Construction Company, Inc. is not responsible for damage to any existing underground utility lines that have not been located and uncovered prior to our trenching.”

On September 26, 2006, Double J Pipeline notified Kansas One Call that it would be excavating south of Mound City. Kansas One Call informed Double J Pipeline that all facilities would be marked by 12:01 A.M., September 29, 2006. Because of a mapping error in the Kansas One Call database, the facilities’ owner did not receive notification of the intent to excavate. The error was discovered before Double M began any excavation.

Double J Pipeline placed a second call to Kansas One Call noting the error and notifying Kansas One Call of the proper excavation area. The mapping error was corrected, and Kansas One Call informed Double J Pipeline that all facilities would be properly marked by Tuesday, October 3, 2006. On September 29, 2006, Double J Pipeline directed Double M to excavate along the planned gas-gathering route.

. Kansas One Call’s records indicated that Double M did not independently contact Kansas One Call to request utility locations or to provide notification of its intent to excavate. During the excavation, equipment owned and operated by Double M struck and ruptured a 20-inch high-pressure natural gas transmission line. Natural gas escaped through the rupture and ignited, resulting in the death of a Double M employee and property damage.

The Corporation Commission issued an order directing Double M to show cause why it should not institute punitive proceedings against Double M. Double M filed a response denying liability. The Corporation Commission entered an order finding Double M at fault and assessing a $25,000 penalty against Double M, which was half the statutory maximum for two violations. Double M filed *271 a timely petition for reconsideration under K.S.A. 66-118b and K.S.A. 77-529(a)(l), which the Corporation Commission denied. Double M then filed a timely petition for judicial review in Shawnee County District Court. The district court affirmed the Corporation Commission, and Double M took a timely appeal to the Court of Appeals. This court assumed jurisdiction on its own motion following Double M’s motion to transfer.

Double M essentially raises two arguments in its brief. First, it contends that it was not the statutory excavator because it contractually delegated its liability to Double J Pipeline. Second, it contends that it is unfair to impose sanctions on Double M without also imposing sanctions on Double J Pipeline. It frames these arguments under a variety of headings, but they condense down to repetitions of the same issues, which are governed by basic rules of statutory interpretation.

Double M initially contends that the Corporation Commission and the district court erred in imposing statutory punitive measures against Double M after it had contractually assigned to Double J Pipeline responsibility for locating utilities and liability for any damages resulting from excavations.

This appeal asks the court to construe a statutory scheme in light of the stipulated facts. The standard of appellate review is de novo for cases decided by the district court based upon documents and stipulated facts. In re Harris Testamentary Trust, 275 Kan. 946, 951, 69 P.3d 1109 (2003). Interpretation of a statute is a question of law over which this court has unlimited review. Genesis Health Club, Inc. v. City of Wichita, 285 Kan. 1021, 1031, 181 P.3d 549 (2008). An appellate court’s first task is to “ascertain the legislature’s intent through the statutory language it employs, giving ordinary words their ordinary meaning.” State v. Stallings, 284 Kan. 741, 742, 163 P.3d 1232 (2007). *272 statute to effect the legislature’s intent.” In re K.M.H., 285 Kan. 53, 79, 169 P.3d 1025 (2007), cert. denied 555 U.S. 937 (2008).

*271 “When a statute is plain and unambiguous, we do not speculate as to the legislative intent behind it and will not read the statute to add something not readily found in it. We need not resort to statutory construction. It is only if the statute’s language or text is unclear or ambiguous that we move to the next analytical step, applying canons of construction or relying on legislative history construing the

*272 An administrative agency’s interpretation of a statute is not binding, and the final construction of a statute always rests with the courts. Denning v. KPERS, 285 Kan. 1045, 1048, 180 P.3d 564 (2008).

As a general rule, a punitive statute should be strictly construed in favor of the accused, which simply means that words are given their ordinary meaning. Any reasonable doubt about their meaning is decided in favor of the accused. State v. Kleypas, 282 Kan. 560, 564, 147 P.3d 1058 (2006).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Gachelin
Court of Appeals of Kansas, 2024
In re N.E.
516 P.3d 586 (Supreme Court of Kansas, 2022)
State v. West
Court of Appeals of Kansas, 2020
State v. Braun
470 P.3d 1286 (Supreme Court of Kansas, 2020)
In re Hodge - (
Supreme Court of Kansas, 2017
McMullin v. Bravo
New Mexico Court of Appeals, 2016
Hale v. CDR Operations, Inc.
474 S.W.3d 129 (Kentucky Supreme Court, 2015)
Manzano v. Kansas Department of Revenue
324 P.3d 321 (Court of Appeals of Kansas, 2014)
Bussman v. Safeco Insurance Co. of America
317 P.3d 70 (Supreme Court of Kansas, 2014)
State v. Allen
305 P.3d 702 (Court of Appeals of Kansas, 2013)
In re TransCanada Keystone Pipeline, L.P.
301 P.3d 355 (Court of Appeals of Kansas, 2013)
Davis v. Winning Streak Sports, LLC
301 P.3d 709 (Court of Appeals of Kansas, 2013)
Markovich v. Green
297 P.3d 1176 (Court of Appeals of Kansas, 2013)
In re the Adoption of I. M.
288 P.3d 864 (Court of Appeals of Kansas, 2012)
In re the Marriage of Merrill
281 P.3d 559 (Court of Appeals of Kansas, 2012)
CoreFirst Bank & Trust v. JHawker Capital, LLC
282 P.3d 618 (Court of Appeals of Kansas, 2012)
Barnes v. BD. OF COUNTY COM'RS OF COWLEY
274 P.3d 697 (Court of Appeals of Kansas, 2012)
Barnes v. Board of County Commissioners
274 P.3d 697 (Court of Appeals of Kansas, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
202 P.3d 7, 288 Kan. 268, 2009 Kan. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/double-m-construction-inc-v-state-corp-commission-kan-2009.