Dobie v. Sears, Roebuck & Co.

180 S.E. 289, 164 Va. 464, 107 A.L.R. 1026, 1935 Va. LEXIS 222
CourtSupreme Court of Virginia
DecidedJune 13, 1935
StatusPublished
Cited by30 cases

This text of 180 S.E. 289 (Dobie v. Sears, Roebuck & Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dobie v. Sears, Roebuck & Co., 180 S.E. 289, 164 Va. 464, 107 A.L.R. 1026, 1935 Va. LEXIS 222 (Va. 1935).

Opinion

Hudgins, J.,

delivered the opinion of the court.

Charles C. Dobie filed a bill in chancery, praying that a building contract executed by him and appellee be rescinded, on the ground of failure to erect a dwelling house in accordance with the plans and specifications. The answer filed denied the material allegations of the bill. Evidence was taken ore tenus, after which the chancellor made an inspection of the premises, and “being of the opinion that the rescission of the contract is not justified at this time but that certain things should be done by the defendant;” entered a decree on November 30, 1932, ordering appellee to make eight specific corrections in the building and report to court. To the entry of this decree appellant excepted.

After considerable delay, appellee reported the work done in accordance with the decree, to which report appellant filed exceptions. Evidence was introduced by both parties in support of the report and the objections. The chancellor finally determined that appellant was not entitled to rescission of the contract, but that he was entitled to $1,700 damages, for failure to erect the dwelling in accordance with the contract and for delay in the completion of the work, and on December 19, 1933, entered decree accordingly. From both decrees appellant sought and obtained this appeal.

The first error assigned is to the action of the court in refusing to rescind the contract.

The record discloses that appellant, a young man employed in Washington, District of Columbia, was engaged to marry a Miss Jean, and the date of the wedding was set [469]*469for February, 1932. For the purpose of having a home in readiness for his bride, he, in the summer of 1931, entered into negotiations with appellee to erect a dwelling house on a lot which he owned in the city of Alexandria, and paid appellee $50 to draft the plans and specifications for such a house as he desired. After studying the plans, he and his fiancee determined to make certain changes, which were submitted to and accepted by appellee. One of the changes in plan was the substitution of an open stairway for a closed or disappearing stairway leading to the second floor. Appellee stated that to make an attractive open stairway it would be necessary to enlarge the building from one to two feet, and for this change the additional cost would be approximately $1,000. This substitution in the plans was approved by all parties, and thereupon appellant paid appellee $1,450, less the $50 he had previously paid for the plans and specifications, and executed his notes for $9,600, payable in monthly installments, beginning January 15, 1932. The payment of this sum was secured by two deeds of trust on the lot and the proposed building. In these deeds of trust, it was stipulated that the owner should not sell or dispose of the property until the debt to appellee had been fully discharged.

Appellant contended that the house was not erected in accordance with the contract, and after the failure of the parties to reach a settlement the bill for rescission and cancellation was filed in February, 1932. The trial court, by its decree entered on November 30, 1932, found as a fact, on conflicting evidence, that the building failed to conform to the plans and specifications in eight particulars: (1) The cellar was not water proof; (2) the brick work on the whole building failed to have one-fourth inch white, stainless cement joints, the color of the cement joints was not uniform, and the brick window sills were not properly laid; (3) the carpenter’s work around the dormer windows was defective; (4) the electric wiring of the house was not in accordance with the specifications; (5) the door frames in the cellar did not fit; (6) the openings in the plaster around [470]*470the electric fixtures were too large; (7) the basement ceiling was not properly finished; (8) some of the slate on the roof was defective.

On these findings of fact, and evidence tending to prove other substantial deviations from the plans, on which the trial court did not express its conclusions except to assess $1,700 damages against appellee, appellant contends he is entitled to rescission of the building contract.

A suit for rescission is the counterpart of a suit for specific performance. Both are addressed to the sound discretion of the court, and in neither will relief be granted to one who has been guilty of inexcusable delay in asserting the right. Hagan v. Taylor, 110 Va. 9, 65 S. E. 487. An application to rescind a contract should be made with due diligence. What constitutes diligence must be determined from the facts of the particular case. It must be in proportion to the injury likely to ensue from delay. Simmons v. Palmer, 93 Va. 389, 25 S. E. 6. If after discovery or knowledge of facts which would entitle a party to rescind, he treats the contract as a subsisting obligation and leads the other party to believe that the contract is still in effect, he will have waived his right to rescind. Prompt action is essential when one believes himself entitled to such relief. Max Meadows Land and Imp. Co. v. Brady, 92 Va. 71, 22 S. E. 845; Campbell v. Eastern Building and Loan Association, 98 Va. 729, 37 S. E. 350; Finch v. Garrett, 109 Va. 114, 115, 63 S. E. 417; Barnett v. Barnett, 83 Va. 504, 2 S. E. 733.

Applying these well established principles to the pertinent facts, the evidence clearly shows that shortly after the date of the contract, September 3, 1931, appellee commenced work on the building; that three or four times a week, sometimes oftener, appellant was on the premises, that he talked with the workmen and made numerous suggestions about the materials used; that he was in close contact with Mr. Nash, the salesman who had induced him to make the contract; and from time to time he registered various complaints; that Miss Jean, his fiancee, and other friends were [471]*471frequently on the premises and made suggestions to appellant on the subject.

The first written objection was made on November 27, 1931. In this letter he expressed his high opinion of appellee and stated that his complaint was based on the indifference and carelessness of some of the workmen engaged on the building, and asked that a man be sent down to correct some of the defects. Among other things, he said: “Undoubtedly much work and expense can be saved for you and by such an agreement I will surely derive more satisfaction, than by having things done wrongly and corrected later, which, of course, I shall insist upon.”

Soon after this letter was written, a representative of the company appeared, and on December 13, 1931, this representative, with the supervisor in charge of the construction, appellant, his fiancee, and several of his friends, went over the building together and a memorandum was made of the various objections raised. On this occasion several changes were suggested by appellant and his fiancee and the locations of several radiators were changed from the places designated in the original plans.

On this date the brick work and the plastering had been completed, except for finishing touches. It was therefore apparent that a closed stairway had been substituted for an open stairway, and even if appellee is mistaken in its contention that appellant had authorized the change, it was the duty of appellant, if he was going to insist upon an open stairway, to have then and there so informed appellee. This he did not do.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norfolk Aviation, LLC v. Rafamedia, LLC
Court of Appeals of Virginia, 2025
Phillips Avenue Holdings, LLC v. Rafamedia, LLC
Court of Appeals of Virginia, 2025
Squire v. VHDA
Supreme Court of Virginia, 2014
Waters v. CitiMortgage, Inc.
92 Va. Cir. 460 (Chesterfield County Circuit Court, 2013)
Banner Life Insurance v. Noel
861 F. Supp. 2d 701 (E.D. Virginia, 2012)
Jenkins v. Bay House Associates, L.P.
581 S.E.2d 510 (Supreme Court of Virginia, 2003)
Builders Floor Service, Inc. v. Kirby
60 Va. Cir. 171 (Virginia Circuit Court, 2002)
Cascades West Assocs. Ltd. Partnership v. PRC, Inc.
36 Va. Cir. 324 (Fairfax County Circuit Court, 1995)
McLeskey v. Ocean Park Investors, Ltd.
405 S.E.2d 846 (Supreme Court of Virginia, 1991)
Sowers v. Hamilton Dev. Co.
14 Va. Cir. 311 (Chesterfield County Circuit Court, 1989)
Adelman v. Conotti Corporation
213 S.E.2d 774 (Supreme Court of Virginia, 1975)
Pillis v. Nash
2 Va. Cir. 377 (Richmond City Circuit Court, 1973)
Moore v. Farm & Ranch Life Insurance
505 P.2d 666 (Supreme Court of Kansas, 1973)
J. C. Nichols Co. v. Meredith
391 P.2d 136 (Supreme Court of Kansas, 1964)
Cut Price Super Markets v. Kingpin Foods, Inc.
98 N.W.2d 257 (Supreme Court of Minnesota, 1959)
Local 1142 v. United Electrical, Radio & MacHine Workers
76 N.W.2d 481 (Supreme Court of Minnesota, 1956)
Alabama Vermiculite Corporation v. Patterson
124 F. Supp. 441 (W.D. South Carolina, 1954)
Tennessee Gas Transmission Co. v. Fox
58 S.E.2d 584 (West Virginia Supreme Court, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
180 S.E. 289, 164 Va. 464, 107 A.L.R. 1026, 1935 Va. LEXIS 222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dobie-v-sears-roebuck-co-va-1935.