DMA International, Inc. v. Qwest Communications International, Inc.

585 F.3d 1341, 48 Communications Reg. (P&F) 1122, 2009 U.S. App. LEXIS 24165
CourtCourt of Appeals for the Tenth Circuit
DecidedNovember 4, 2009
Docket19-3211
StatusPublished
Cited by17 cases

This text of 585 F.3d 1341 (DMA International, Inc. v. Qwest Communications International, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DMA International, Inc. v. Qwest Communications International, Inc., 585 F.3d 1341, 48 Communications Reg. (P&F) 1122, 2009 U.S. App. LEXIS 24165 (10th Cir. 2009).

Opinion

LUCERO, Circuit Judge.

In April 2004, appellant DMA International, Inc. (“DMA”) entered into a contract to provide database research services to appellee Qwest Communications International, Inc. (“Qwest”). When the contract expired eight months later, Qwest refused to pay DMA’s final invoice, contending it had already paid DMA in full for its services. DMA accused Qwest of breaching their contract and submitted a demand for arbitration. 1 After the arbitrator ruled in favor of Qwest, DMA filed a motion in the district court to vacate the award under the Federal Arbitration Act (“FAA”). 9 U.S.C. § 10. The district court concluded that it had no basis to vacate the arbitrator’s award and granted a counter motion to confirm the award under 9 U.S.C. § 9. DMA appeals that decision. Exercising jurisdiction under 9 U.S.C. § 16(a) and 28 U.S.C. § 1291, we affirm.

I

The parties’ dispute centers on the contract’s fees provision, Section 4. 1, which states:

[F]ees for Services rendered hereunder are as follows:

... Twenty-five dollars and twenty cents ($25.20) per circuit satisfactorily completed. (Fee is based on an hourly rate of forty-five dollars ($45) with 1.8 circuits completed per hour).

DMA argues that this provision unambiguously provides for payments to be based on the number of circuits completed. Using this interpretation, DMA submitted a final invoice to Qwest seeking approximately $5.4 million for roughly 285,000 completed circuits. This invoice included a $1.7 million deduction, representing fees that Qwest had already paid to DMA. Qwest argues that the parties intended for DMA to be paid on an hourly basis, as reflected in the parenthetical portion of Section 4.1. It also claims that DMA knew from the outset that Qwest’s budget for DMA’s work under the contract was $1.7 million. Based on an hourly rate of forty- *1344 five dollars, Qwest contends that the $1.7 million it had already paid DMA satisfied its payment obligations.

After extensive briefing and an eleven-day arbitration hearing in which sixteen witnesses testified and 140 exhibits were admitted, the arbitrator concluded that the contract’s fees provision was ambiguous:

I can not [sic] determine from a reading of ... section 4.1 at what rate the parties intended that DMA be paid for its work. Was it to be paid per circuit or per hour? Consideration of other relevant portions of the contract only underscore the ambiguity.... When is a circuit “completed” and how does that relate to the work DMA was to perform as described at section 1.2 of the [Statement of Work]?

Accordingly, the arbitrator turned to extrinsic evidence to determine the parties’ intent. He ultimately concluded that the parties intended for DMA to be paid at the rate of forty-five dollars per hour. Based on this finding, the arbitrator ruled that Qwest had paid DMA in full and dismissed DMA’s breach of contract claim.

In the district court, DMA argued that vacatur was warranted because: (1) the award manifestly disregarded the law; (2) the arbitrator was partial or corrupt; (3) the award violated public policy; (4) the arbitrator exceeded his powers; and (5) Qwest did not dispute the final invoice within forty-five days of receipt. In rejecting each of these arguments, the district court based its ruling largely on the highly deferential standard of review applicable to arbitration awards. See Hollern v. Wachovia Secs., Inc., 458 F.3d 1169, 1172 (10th Cir.2006) (describing that standard as “among the narrowest known to the law” (internal quotation marks omitted)). DMA now appeals.

II

In reviewing a district court’s confirmation of an arbitration award, we review factual findings for clear error and legal determinations de novo. Sheldon v. Vermonty, 269 F.3d 1202, 1206 (10th Cir.2001). We are required nevertheless to “give extreme deference to the determination of the [arbitrator].” Brown v. Coleman Co., 220 F.3d 1180, 1182 (10th Cir.2000). “Once an arbitration award is entered, the finality of arbitration weighs heavily in its favor and cannot be upset except under exceptional circumstances.” Ormsbee Dev. Co. v. Grace, 668 F.2d 1140, 1146-47 (10th Cir.1982). An arbitration award will only be vacated for the reasons enumerated in the FAA, 9 U.S.C. § 10, or for “a handful of judicially-created reasons.” Sheldon, 269 F.3d at 1206 (observing that a district court may set aside an arbitration award based on a violation of public policy, manifest disregard of the law, or denial of a fundamentally fair hearing).

DMA’s principal argument on appeal is that the arbitrator’s award should be vacated because the arbitrator acted in manifest disregard for the law. 2 We have characterized the “manifest disregard” standard, however, as “willful inattentiveness to the governing law.” Jenkins v. Prudential-Bache Sec. Inc., 847 F.2d 631, 634 (10th Cir.1988). Mere errors in *1345 an arbitrator’s factual findings, or in his interpretation and application of the law, do not justify vacatur. See Hollern, 458 F.3d at 1172. “[T]he record [must] show the arbitrator[ ] knew the law and explicitly disregarded it.” Dominion Video Satellite, Inc. v. Echostar Satellite LLC, 430 F.3d 1269, 1274 (10th Cir.2005) (quoting Bowen v. Amoco Pipeline Co., 254 F.3d 925, 932 (10th Cir.2001)).

As the district court noted in its order, the arbitrator in the present case correctly stated the law governing contract interpretation in Colorado and applied it to the fees provision. Once the arbitrator found Section 4.1 was ambiguous, he appropriately considered extrinsic evidence. See Fort Lyon Canal Co. v. High Plains A & M, LLC, 167 P.3d 726, 728-29 (Colo.2007). The arbitrator’s factual findings may not be overturned simply because the evidence was conflicting. See United Paperworkers Int’l Union v. Misco, Inc., 484 U.S. 29, 45, 108 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cox v. Dex Media, Inc.
D. Colorado, 2021
Mid Atlantic Capital v. Bien
956 F.3d 1182 (Tenth Circuit, 2020)
Wells Fargo Bank v. Apache Tribe of Oklahoma
2016 OK CIV APP 16 (Court of Civil Appeals of Oklahoma, 2015)
Bevan v. Davita, Inc.
557 F. App'x 706 (Tenth Circuit, 2014)
Cessna Aircraft Co. v. Avcorp Industries, Inc.
943 F. Supp. 2d 1191 (D. Kansas, 2013)
Countrywide Financial Corp. v. Bundy
187 Cal. App. 4th 234 (California Court of Appeal, 2010)
Legacy Trading Co., LTD v. Robert Hoffman
363 F. App'x 633 (Tenth Circuit, 2010)
Hicks v. Cadle Company
355 F. App'x 186 (Tenth Circuit, 2009)
Treadwell v. Village Homes of Colorado, Inc.
222 P.3d 398 (Colorado Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
585 F.3d 1341, 48 Communications Reg. (P&F) 1122, 2009 U.S. App. LEXIS 24165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dma-international-inc-v-qwest-communications-international-inc-ca10-2009.