DiMiceli v. Affordable Pool Maintenance, Inc.

110 S.W.3d 164, 2003 Tex. App. LEXIS 3903, 2003 WL 21010608
CourtCourt of Appeals of Texas
DecidedMay 7, 2003
Docket04-02-00497-CV
StatusPublished
Cited by12 cases

This text of 110 S.W.3d 164 (DiMiceli v. Affordable Pool Maintenance, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DiMiceli v. Affordable Pool Maintenance, Inc., 110 S.W.3d 164, 2003 Tex. App. LEXIS 3903, 2003 WL 21010608 (Tex. Ct. App. 2003).

Opinion

OPINION

Opinion by

CATHERINE STONE, Justice.

Appellant, Lawrence DiMiceli, appeals a judgment in favor of Affordable Pool Maintenance, Inc. (“APM”). A jury found that DiMiceli breached the parties’ agreement for the renovation and repair of DiM-iceli’s swimming pool and also found that APM had performed compensable work to the benefit of DiMiceli. DiMiceli asserts four issues on appeal, contending that: (1) the trial court erred in rendering judgment in favor of APM on its claim of quantum meruit; (2) the jury’s refusal to find APM liable for breach of contract and breach of the implied warranty of good and workmanlike performance is against the great weight and preponderance of the evidence; (3) the evidence is legally and factually insufficient to support the jury’s finding that DiMiceli breached the parties’ agreement and that DiMieeli’s breach was not excused; and (4) the jury’s award for attorney’s fees is based on factually insufficient evidence. We agree with DiMiceli that APM cannot recover on the theory of quantum meruit as a matter of law. We reverse that part of the judgment rendered in favor of APM on its claim for quantum meruit We conclude, however, that there is sufficient evidence to support the jury’s finding that DiMiceli breached the parties’ agreement. Therefore, we affirm the judgment as modified. See Tex. R.App. P. 43.2(b).

Factual and PROCEDURAL Background

A two-story cabana located in DiMiceli’s backyard was destroyed as a result of a fire. The heat from the fire also damaged DiMieeh’s swimming pool. After receiving estimates for the renovation and repair of the pool from various contractors, DiMiceli entered into a written service contract with APM on May 24, 1999. The service contract provided that APM would “drain [the] pool, light acid wash, remove old plaster, repair cracks as needed, repair gunite if required, reseal all skimmer faces, remove the old tile, install new tile, *167 hand trowel white marble plaster, replace 2 skimmers, install diving board brackets and diving board, stand and jig, [and] install [a] new light fixture.” For these services, DiMieeli agreed to pay APM the amount of $7,250. Under the contract, APM would begin work on June 9, 1999 and complete the project by July 1, 1999. DiMieeli would make one installment payment at signing, another payment when APM started work, and a final payment at the completion of the project. DiMieeli separately contracted with another company, Concrete Innovations, to install a new deck and sidewalk around the pool.

APM sued DiMieeli in January 2000 alleging claims for breach of contract and quantum, meruit. In support of its claims, APM alleged that DiMieeli failed to make a final installment payment of $3,580.47. APM also made a claim for attorney’s fees. By his sixth amended original answer, DiMieeli asserted various counterclaims, including claims for breach of contract and breaeh of the implied warranty of good and workmanlike manner. The case was tried before a jury.

Andre Montwill, president of APM, testified that problems arose shortly after APM started on the job. APM noticed that the pool’s beam was broken in certain areas. APM could not install decorative tile in areas where the beam was broken. It appeared to Montwill that the broken beam was a result of the removal of the deck and flagstones which surrounded the pool with a jackhammer. Montwill testified that he informed DiMieeli of the problem and the cost of repairing the broken beam. DiMieeli decided to have Concrete Innovations repair the beam when they poured the new deck. Montwill informed DiMieeli that this would make APM’s job more difficult because they could end up with an uneven tile line. DiMieeli was unconvinced, and APM was removed from the project to allow Concrete Innovations to work. Upon its return, APM noted that the beam had been repaired, but that the pool was missing coping. Coping is the lip that surrounds a pool to prevent water from running into the pool. The coping was subsequently added by Concrete Innovations. However, the end product appeared uneven in certain areas. These uneven areas affected APM’s placement of the decorative tile such that in some areas the tile fine was not level with the water line.

DiMieeli also testified. DiMieeli admitted that he had hired a third-party to remove the flagstones around the pool and even removed some of the flagstones himself. However, he denied that the beam was broken after the removal of these flagstones. DiMieeli also testified about specific complaints he had regarding APM’s work. According to DiMieeli, the decorative tile work was not level with the water line. DiMieeli also testified that the skimmers in the pool were “intolerable,” and the underwater light installed by APM did not work. Finally, DiMieeli testified that APM faded to install a diving board.

Lawrence Hans, engineer, testified as an expert witness on behalf of DiMieeli. Hans testified that it appeared that each of the sub-contractors conducted their work without supervision. He also testified about specific problems with the pool that he concluded were caused by APM’s failure to perform its work in a good and workmanlike manner. The underwater light did not work because it was not connected to the junction box which, in turn, was not in operation. The grab rails leading out of the pool were improperly placed, requiring a person to improperly exit the pool. In addition, the grab rails were not properly grounded. The decorative tile was not level with the water fine. The skimmers, responsible for circulating the *168 water both at the top and bottom of the pool, were not aligned with one another. As a result, water could not properly circulate. Hans also noted that the plaster in the pool was extremely rough. Finally, Hans testified that the bolts sticking out of the concrete to hold the diving board were unsafe.

The parties agree that the proper sequence of renovation was not followed in this case. According to Montwill, the proper sequence of events would have been to prepare the pool for plaster, install the decorative tile, pour the deck and install the coping, and plaster the pool. Hans similarly testified that the tile and coping should have been installed first. Once the coping was in place, the deck could be poured. Finally, the interior of the pool could be plastered. Here, it is undisputed that the deck was poured before the tile line was fixed. According to Montwill, the sequence was thrown off as a result of DiMiceli’s decision to remove the old deck himself and call on Concrete Innovations to pour the deck.

After deliberating, the jury returned a verdict in favor of APM. The jury specifically found that DiMiceli breached the parties’ agreement and that he was not excused for his breach. The jury also found that APM performed compensable work for DiMiceli. The jury refused to find that APM breached the parties’ agreement. The jury awarded damages in the amount of $2,030.47 on APM’s breach of contract claim and $6,380.47 on APM’s claim for quantum meruit. The jury also awarded APM attorney’s fees in the amount of $12,500 for trial and $4,000 for appeal. The trial court entered a judgment that provided that APM could elect the greater theory of recovery. DiMiceli filed a motion to modify the judgment and, in the alternative, a motion for new trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
110 S.W.3d 164, 2003 Tex. App. LEXIS 3903, 2003 WL 21010608, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dimiceli-v-affordable-pool-maintenance-inc-texapp-2003.