Dillard & Sons Construction, Inc. v. Burnup & Sims Comtec, Inc.

51 F.3d 910
CourtCourt of Appeals for the Tenth Circuit
DecidedMay 12, 1995
Docket93-7090, 93-7101
StatusPublished
Cited by24 cases

This text of 51 F.3d 910 (Dillard & Sons Construction, Inc. v. Burnup & Sims Comtec, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dillard & Sons Construction, Inc. v. Burnup & Sims Comtec, Inc., 51 F.3d 910 (10th Cir. 1995).

Opinion

HENRY, Circuit Judge.

This Oklahoma diversity suit arises out of an 'independent subcontractor agreement between the plaintiff-appellee, Dillard & Sons Construction, Inc. (Dillard), and the defendant-appellant, Burnup & Sims Comtec, Inc. (Bumup). Burnup appeals from a jury verdict awarding Dillard $73,795.05 for its breach of contract claim and finding against Bumup on its counterclaim. We reverse the district court’s judgment and remand the case for a new trial.

BACKGROUND

In February of 1992, Dillard entered into' an independent contractor agreement with Burnup to install underground telephone cable for the benefit of Bumup’s customer, Contel of Missouri, Inc., d/b/a GTE. Four projects stemmed from this agreement, three in Oklahoma, and one in Annapolis, Missouri. Only the Missouri project is at issue in this appeal. 1

Pursuant to the Missouri contract, Dillard was to install 102,314 feet of cable. Dillard began work on the project in early July. Burnup’s superintendent was on-site and signed time and billing sheets, agreeing upon the units placed by Dillard on a daily basis. See Subcontractor Guidelines ¶ 6, Aplt.App. at 104; Letter of Authorization dated July 7, 1992, Aplt.App. at 106.

Although there was conflicting testimony at trial as to a specific date, -witnesses for both parties agreed that sometime during mid-to-late August the President of Dillard & Sons Constmction, Mike Dillard, approached Burnup’s Division Manager, Jim Bartlett, to request payment of past retainage due on two of the Oklahoma projects and payment for work-in-progress on the third Oklahoma project and the Missouri project. Mr. Bartlett indicated to Mr. Dillard that he would receive payment shortly, but then continued to withhold the money. Mr. Bartlett admitted at trial that Burnup’s payments were overdue at that time, and that Burnup never made any payments to Dillard for work on the Missouri project. Mr. Bartlett also testified that shortly after this meeting Burnup became aware that certain portions of the cable had been buried at a depth of less than twenty-four inches, which was allegedly not in compliance with the contract specifications, and that Dillard had begun taking steps to lower the cable. Mr. Bartlett then wrote a letter to Dillard confirming both that there was a problem with the depth of the cable and that Dillard would continue working to lower it.! The letter was dated August 31, 1992. On September 1, 1992, Mr. Dillard made a second oral demand for payment of money due. Upon Burnup’s refusal to pay, Dillard walked off the project.

Dillard then brought suit in the district court, arguing that Burnup breached the contract by refusing to make timely payments while Dillard was allegedly complying in good faith with Burnup’s request to lower the cable. Burnup counterclaimed, contending that Dillard faded to substantially perform the contract because it placed 28,000 to 34,-000 feet of the cable at less than a twenty-four inch depth. Additionally, Burnup argued that its delay in paying Dillard did not constitute a breach of the contract because payment was not due until Dillard substantially performed the installation pursuant to the contract’s terms. Bumup also sought damages for the expense it incurred by hiring a third party to lower the cable.

At trial, there was undisputed testimony that 28,000 to 34,000 feet of cable had been *913 buried at a depth of less than twenty-four inches. 2 However, the evidence indicated that the other 68,000 to 74,000 feet of cable had been buried at a twenty-four inch minimum depth. Bumup’s Executive Vice President also testified at trial that Burnup had received close to $50,000 from its customer, GTE, for work approved by GTE that was attributable to Dillard.

At the close of Dillard’s evidence and at the close of trial, Burnup moved for Judgment as a Matter of Law as to both Dillard’s breach of contract claim and its own counterclaim pursuant to Fed.R.Civ.P. 50. These motions were denied. Additionally, Burnup requested a jury instruction stating that interpretation of the contract was a matter of law for the court and that the court construed the contract to provide for a twenty-four inch minimum depth requirement. This request was denied. The jury then returned a verdict in favor of Dillard in the amount of $73,795.05.

Burnup raises several issues on appeal. First, Burnup argues that it is entitled to judgment as a matter of law as to Dillard’s claim and a new trial on Burnup’s counterclaim because the contract unambiguously required a twenty-four inch minimum depth for burial of the cable. In this regard, Burn-up argues that the trial court erred by refusing to construe the contract’s terms with regard to the depth requirement and by submitting to the jury a question that Burnup argues is an issue of law. Additionally, Burnup contends that the jury could not have reasonably found that Dillard substantially performed the contract or that the contract’s twenty-four inch depth requirement had been modified in any way. Burnup also argues that the district court should have granted its request for remittitur of the damages award to account for the cost of remedying the shallow cable depth. Lastly, Burnup appeals the attorney fees and costs awarded to Dillard by the district court.

DISCUSSION

Both parties agree that the Annapolis, Missouri contract consists of three documents: an Independent Contractor Agreement, Subcontractor Guidelines, and a Letter of Authorization, also known as the Unit Description. 3 These three documents do not contain specifications for burial of the cable. Rather, these documents refer to Burnup’s contract with GTE: The Subcontractor Guidelines provide that “[a]ll units placed must be placed per Burnup & Sims contract with their customer.” Subcontractor’s Guidelines ¶ 5, Aplt.App. at 104. Additionally, the Independent Contractor Agreement requires the “Independent Contractor [to] satisfy all applicable federal, state and local safety and electrical codes, and all applicable safety regulations_” Independent Contractor Agreement ¶ 5, Aplt.App. at 99.

The Letter of Authorization, addressed to Dillard and signed by Burnup’s Division Manager, describes the type of cable to bp buried, the price per unit, and the estimated quantity. The letter also provides:

All units must be completed per contract specifications and agreed upon daily with our superintendent....
After all units are agreed upon with our customer you will receive payment. Re-tainage that is held will be paid once we have received our retainage from our customer [and] all known claims against your company have been resolved....

*914 Letter of Authorization dated July 7, 1992, Aplt.App. at 106. 4

Twenty-Four Inch Depth Requirement

Burnup argues that the district court erred by not construing the contract’s specifications for cable depth as a matter of law and by submitting this issue to the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
51 F.3d 910, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dillard-sons-construction-inc-v-burnup-sims-comtec-inc-ca10-1995.