Detroit Power Screwdriver v. Ladney

181 N.W.2d 828, 25 Mich. App. 478, 8 U.C.C. Rep. Serv. (West) 504, 42 A.L.R. 3d 173, 1970 Mich. App. LEXIS 1598
CourtMichigan Court of Appeals
DecidedJuly 29, 1970
DocketDocket 7,869
StatusPublished
Cited by20 cases

This text of 181 N.W.2d 828 (Detroit Power Screwdriver v. Ladney) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Detroit Power Screwdriver v. Ladney, 181 N.W.2d 828, 25 Mich. App. 478, 8 U.C.C. Rep. Serv. (West) 504, 42 A.L.R. 3d 173, 1970 Mich. App. LEXIS 1598 (Mich. Ct. App. 1970).

Opinion

Lesinski, C. J.

Plaintiff Detroit Power Screwdriver Company filed suit for breach of contract against Michael Ladney, Jr., doing business as Detroit Plastic Molding Co. Following trial without jury, the court ruled that plaintiff had not carried *481 its burden of proof as to damages and dismissed the suit. Plaintiff appeals as of right.

On January 5, 1967, plaintiff sent defendant a quotation for a machine described as a:

“Double-spindle stud driver, designed to select, feed and drive two shoulder studs simultaneously into plastic air scoop, at the rate of 20-pieces per minute, per spindle, minimum.”

After further describing the equipment the quotation states the price of the machine ($11,750) and extra parts ($142). The quotation then provides:

“Delivery: 12 weeks from receipt of order and samples.

# * #

“Note: The above recommendation is made subject to receipt of actual samples of the studs, and parts into which studs are to be driven.

# # *

“Please submit approx. 1000 studs, and 100 components, for our engineering and testing purposes.”

On January 9, 1967, defendant sent its purchase order to plaintiff. The purchase order used the description quoted above and the same price as plaintiff’s quotation. The purchase order then provided:

“Delivery: 12 weeks from receipt of orderand [sic] samples.”

Defendant’s purchase order was acknowledged by letter from plaintiff on January 11, 1967 which stated inter alia:

“The order has been entered into production and delivery has been scheduled for March 31, 1967.

“This delivery is based on prompt receipt of 1000 of the studs involved, along with 100 components into which the studs will be driven.”

The record establishes that the samples referred to in the quotation, purchase order and acknowledge *482 ment were not delivered to plaintiff until approximately February 10,1967.

In mid-March plaintiff was notified that the studs to be used in the machine had been changed. The new studs were smaller than the original samples provided on February 10. At a meeting held March 20, it was established that the new studs could not be used in the machine as designed for the original samples. A number of changes in the machine’s design to accommodate the smaller studs were agreed upon. The changes were estimated as costing $600, and at trial the cost was established at $627.

At the March 20 meeting, defendant stated he needed the machine no later than March 31. There is, however, no evidence indicating that plaintiff made a binding acceptance of the proposed change.

On April 11, 1967, defendant notified plaintiff to stop work on the machine, apparently on the grounds that plaintiff had not delivered the machine by March 31. Negotiations between the parties failed to resolve their differences. The unfinished machine was crated and put in storage. On May 11, 1967, plaintiff invoiced defendant for work completed up to the April 11 work stoppage in the amount of $12,017 for the machine and $142 for extra parts. The invoice also stated: “Additional billing of $360 to be applicable when machine is completed”. 1 Upon defendant’s refusal to pay, plaintiff instituted this suit.

*483 At trial plaintiff’s price quotation, defendant’s purchase order, and plaintiff’s invoice, along with other exhibits, were admitted into evidence. There was also evidence that the scrap or salvage value of the machine wras $1,500.

Substantial evidence was also adduced at trial regarding the nature of the machine itself. While the record contains a highly detailed description, suffice it to say it is a very complex piece of equipment. Moreover, several important changes, requiring a good deal of redesign, differentiate this particular stud driver from the standard stud driver which plaintiff usually built.

The trial court held that a contract existed and that defendant breached the contract. The court also held, however, that plaintiff had failed to prove damages with sufficient certainty to permit a recovery. 2

On appeal plaintiff contends that the trial court erred in its conclusion that damages were not adequately proven. 3

*484 The disposition of the instant case is clearly governed by the Uniform Commercial Code.* * 4 5However, due to the differences between various sections providing remedies to sellers, it is necessary to make a preliminary determination of which sections of the code control the final outcome.

The code is, of course, a highly integrated statute, the sections of which must he read together. Accurate application of the code rarely involves reference to only one section.

Of the sections providing remedies for breach by the buyer, 5 plaintiff places principal reliance on MCLA § 440.2709(1) (Stat Ann 1964 Rev § 19.2709 [1]). The authority uncovered in our research, however, indicates that since the machine was not completed, § 2709(1) is inapplicable. As noted in E-Z Roll Hardware Mfg. Co. Inc. v. H & H Products & Finishing Corp. (1968), 4 UCC Rptr 1045, 1047, 1048 (NY Law J, Feb. 1, 1968, p 19):

“A seller who is in the process of manufacturing goods for the buyer which are not readily saleable when finished and who elects to cease manufacture on repudiation by the buyer does not have an action for the purchase price as such (Bender, Uniform Commercial Code Service, Yol 3, Sales & Bulk Transfers sec 13.07[4] p 13-85).”

See, also, Rowland Meledandi, Inc. v. Kohn (1969), 7 UCC Rptr 34 (NY Law J, Dec. 12, 1969, p 17).

Although the reasoning behind this conclusion is not set forth in either E-Z Roll or Rowland Meledandi, we are satisfied that it is correct for two reasons. First, the language of § 2709(1) which allows *485 a suit for the price “when the buyer fails to pay the price as it becomes due,” implies the completion of contractual conditions precedent to payment before the seller can sue for the price. Where, as here, the contract provides for “30 days net on approval,- FOB our plant,” the seller must complete the machine and tender performance consistent with the contract before it can sue for the price. 6

Second, § 2709(1) includes no provisions for expenses saved due to defendant’s breach. 7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Huron Tool and Engineering Co. v. Precision Consulting Services, Inc.
532 N.W.2d 541 (Michigan Court of Appeals, 1995)
Taft-Peirce Manufacturing Co. v. Seagate Technology, Inc.
789 F. Supp. 1220 (D. Rhode Island, 1992)
Young v. Frank's Nursery & Crafts, Inc.
569 N.E.2d 1034 (Ohio Supreme Court, 1991)
Yamaha Motor Corp., USA v. Tri-City Motors & Sports, Inc.
429 N.W.2d 871 (Michigan Court of Appeals, 1988)
Madsen v. Murrey & Sons Co., Inc.
743 P.2d 1212 (Utah Supreme Court, 1987)
Commonwealth Edison Co. v. Decker Coal Co.
653 F. Supp. 841 (N.D. Illinois, 1987)
Great Northern Packaging, Inc. v. General Tire & Rubber Co.
399 N.W.2d 408 (Michigan Court of Appeals, 1986)
Bennett v. Oakley
396 N.W.2d 451 (Michigan Court of Appeals, 1986)
Kelleher v. Kuchta
359 N.W.2d 224 (Michigan Court of Appeals, 1984)
Colonial Dodge, Inc v. Miller
322 N.W.2d 549 (Michigan Court of Appeals, 1982)
KLT Industries, Inc. v. Eaton Corp.
505 F. Supp. 1072 (E.D. Michigan, 1981)
Cesco Manufacturing Corp. v. Norcross, Inc.
391 N.E.2d 270 (Massachusetts Appeals Court, 1979)
Detroit Power Screwdriver Co. v. Ladney
197 N.W.2d 857 (Michigan Court of Appeals, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
181 N.W.2d 828, 25 Mich. App. 478, 8 U.C.C. Rep. Serv. (West) 504, 42 A.L.R. 3d 173, 1970 Mich. App. LEXIS 1598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/detroit-power-screwdriver-v-ladney-michctapp-1970.