Beco, Inc. v. Minnechaug Golf Course, Inc.

256 A.2d 522, 5 Conn. Cir. Ct. 444, 6 U.C.C. Rep. Serv. (West) 910, 1968 Conn. Cir. LEXIS 233
Connecticut Appellate Court·Decided August 30, 1968·No. File No. CV 14-668-24269·Published·Cited by 8 cases

Opinion

Dearington, J.

The plaintiff, in its complaint, alleges delivery of certain goods on June 24 and 27, 1966, and thereafter, on August 1, 1966, the defendant notified the plaintiff that it refused to accept the remaining goods. The goods refused, so it is alleged, were specially manufactured and could not be resold at reasonable prices, and the plaintiff was ready, able and willing to deliver the goods. The amount sought by the plaintiff was the balance remaining due for the goods delivered and the cost price of the goods refused. The defendant, in general, denied the allegations and by way of a special defense alleged that the goods delivered were of poor quality and design and as a result were reshipped to the plaintiff, which refused acceptance. By way of a counterclaim, the defendant alleged breach of warranty and claimed damages. Judgment having been rendered for the plaintiff, the defendant has appealed, assigning error in the denial of its motion to correct the finding and further that the subordinate facts do not support the court’s conclusions.

The court found that the plaintiff was engaged in the business of selling restaurant equipment and furnishings. It neither manufactured nor carried a large stock of such equipment. The defendant [446] owned and operated a golf course in Glastonbury. In the fall of 1965, the defendant contracted to construct a new clubhouse and as a part of the plans, prepared by an architect, it included the installation of a restaurant-coffee shop. Sometime in the latter part of February or early part of March, 1966, the plaintiff’s agent, Joseph Carcio, and the defendant’s agent, Graham Clark, began discussions relative to the furnishing of equipment for the restaurant. Many consultations were had between Carcio and Clark, and the former took measurements from the architect’s plans as well as the building, which was then under construction. The plaintiff prepared numerous sketches and layouts for the defendant. On April 21, 1966, the defendant executed an order for itemized equipment and paid the defendant $2950.15 on account. Some of the items were selected from catalogs, while others were carried in stock by the plaintiff. As a result, part of the material, of a value of $6952.62, was delivered at the clubhouse on June 24 and June 27, 1966. The plaintiff then engaged in setting up this equipment in a temporary position. Thereafter, the defendant refused to allow continuation of the work. On June 29, the defendant for the first time consulted his architect in regard to the equipment and then proceeded to rearrange the equipment without consulting the plaintiff. The defendant then advised the plaintiff that the counter as set up in the proposed plans extended twenty inches into a doorway entrance, that two stools along the counter interfered with the passage of customers through a proposed doorway and, further, that the overhang of a proposed shelf should be changed. The plaintiff agreed to eliminate or correct these minor defects. The defendant then discussed the possibility of converting the “wall” type equipment which had been purchased to an “island” type. The plaintiff agreed to [447] see what conversion could be made. The defendant, however, refused to deal any further with the plaintiff and on July 29 attempted to return all the equipment, but the plaintiff refused to accept it and it remained in the possession of the defendant. The finding also disclosed that during the course of the trial the plaintiff learned for the first time that the defendant complained of alleged defects which the plaintiff could have remedied within a reasonable time if given the opportunity.

The court concluded that the plaintiff was entitled to judgment on its complaint based on the contract price and also entitled to judgment on the defendant’s counterclaim. The court further concluded that the plaintiff was willing to cure seasonably any defect or nonconforming use, as provided for in § 42a-2-508 (2) of the General Statutes, that the defendant had waived any right to any implied warranty of suitability by failing to reject the goods within a reasonable time after delivery; § 42a-2-315; and, further, that the defendant had failed to allow the plaintiff to cure any alleged defect. § 42a-2-605 (1) (a), (b). The court then computed the damages to be the price of the goods delivered and the price of the goods especially fabricated and ready for delivery. The court allowed a credit for the payment made, the cost of correcting a counter, and the cost of two stools.

The defendant in its brief has reduced its assignment of errors to two questions, each relating to damages: (1) Was it proper to award damages measured by the contract price or should recovery be confined to damages for nonacceptance as provided for in § 42a-2-708 of the General Statutes? (2) Should damages be reduced by the expense saved by the plaintiff in consequence of the buyer’s breach as provided in § 42a-2-708 (1) ?

Free access — add to your briefcase to read the full text and ask questions with AI

Beco, Inc. v. Minnechaug Golf Course, Inc., 256 A.2d 522, 5 Conn. Cir. Ct. 444, 6 U.C.C. Rep. Serv. (West) 910, 1968 Conn. Cir. LEXIS 233 (Colo. Ct. App. 1968).

256 A.2d 522 (Beco, Inc. v. Minnechaug Golf Course, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Omega Engineering, Inc. v. Eastman Kodak Co.
30 F. Supp. 2d 226 (D. Connecticut, 1998)
G & H Land & Cattle Co. v. Heitzman & Nelson, Inc.
628 P.2d 1038 (Idaho Supreme Court, 1981)
Cesco Manufacturing Corp. v. Norcross, Inc.
391 N.E.2d 270 (Massachusetts Appeals Court, 1979)
La Villa Fair v. Lewis Carpet Mills, Inc.
548 P.2d 825 (Supreme Court of Kansas, 1976)
Cervitor Kitchens, Inc. v. Chapman
500 P.2d 783 (Court of Appeals of Washington, 1972)
Detroit Power Screwdriver v. Ladney
181 N.W.2d 828 (Michigan Court of Appeals, 1970)