Cesco Manufacturing Corp. v. Norcross, Inc.

391 N.E.2d 270, 7 Mass. App. Ct. 837, 27 U.C.C. Rep. Serv. (West) 126, 1979 Mass. App. LEXIS 1227
CourtMassachusetts Appeals Court
DecidedJune 28, 1979
StatusPublished
Cited by17 cases

This text of 391 N.E.2d 270 (Cesco Manufacturing Corp. v. Norcross, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cesco Manufacturing Corp. v. Norcross, Inc., 391 N.E.2d 270, 7 Mass. App. Ct. 837, 27 U.C.C. Rep. Serv. (West) 126, 1979 Mass. App. LEXIS 1227 (Mass. Ct. App. 1979).

Opinion

Dreben, J.

In this action alleging the breach of a contract for the manufacture of customized display racks for greeting cards, the trial judge found, relying on G. L. c. 106, § 2-709, that the plaintiff is entitled to recover an amount equal to the price as reduced by the net proceeds received from the sale of the undelivered fixtures and the expenses saved in consequence of the buyer’s breach, plus an award of incidental damages. We affirm, but under G. L. c. 106, § 2-708(2).

The case was originally a jury action and was referred to a master to make findings "which shall not be final.” After filing objections to the master’s report, the defendant waived its claim for a jury trial, and the plaintiff moved to confirm the report. The motion judge held that the order of reference controlled, that the master’s report was to be treated by the trier of facts as if it were a report under Mass.R.Civ.P. 53(e)(3), 365 Mass. 820 (1974), and that it was admissible as prima facie evidence of the matters found. The matter was tried without a jury, and the trial judge, after hearing testimony, found that the defendant had failed to rebut the findings of the master, and adopted most of the subsidiary findings of fact in the master’s original and supplemental 1 reports. He did not accept the ultimate findings of the master and, instead, issued his own.

The facts are derived from the findings of the master and the judge. The plaintiff and the defendant entered into a contract, evidenced by eight purchase orders, for the manufacture of 1,000 customized racks for greeting cards at a price of $114,319. The plaintiff was to ship the goods upon receipt of shipping orders from the defendant *839 and was to be paid within thirty days after receipt of the fixtures by the defendant. To handle the orders, the plaintiff bought the necessary materials and commenced production. Shipments were made in 1971 and 1972, but some time during the latter year the defendant decided that the fixtures, although manufactured in accordance with its specifications, were too heavy, and no further shipping orders were submitted to the plaintiff. At the end of 1972, 560 of the 1,000 fixtures remained undelivered. Of these, 483 had been manufactured, and sufficient raw materials to make the remaining seventy-seven units were on hand. The judge ruled that while the contract did not specify the time during which the shipping orders had to be placed, a reasonable time was to be inferred under G. L. c. 106, § 2-309(1), and found that such time expired on May 11, 1973. Despite.inquiries and correspondence, including a flurry of letters in the summer and fall of 1974, the parties did not resolve the matter, and this action was commenced by the plaintiff in October, 1974. The parties continued to negotiate until March 1, 1975.

The judge found that the plaintiff acted in a commercially reasonable manner and that it sought to minimize damages by ceasing production of the goods. He also found that, although there was a market for fixtures of the kind manufactured for the defendant, the plaintiff did not have reasonable access to this market, and that any efforts by the plaintiff to complete and sell the fixtures would have been unavailing. Prior to July, 1975, the plaintiff ceased doing business and the fixtures were sold in July at public auction for $2,000.

The defendant raises a number of issues on appeal. Since several concern either facts found by the trier of fact or mixed questions of law and fact, we first state briefly the standard to be applied by this court. Contrary to the defendant’s contention, we are not in the same position as was the judge with respect to the master’s report. We did not hear the testimony at the jury waived trial and are not the judges of the credibility of witnesses. *840 We cannot set aside the judge’s findings of fact unless clearly erroneous, and the findings of a master, to the extent that the judge adopts them, are considered the findings of the judge. Mass.R.Civ.P. 52(a), 365 Mass. 816 (1974). Findings cannot be reversed "unless the reviewing court on the entire evidence is left with the firm conviction that a mistake has been committed.” New England Canteen Serv. Inc. v. Ashley, 372 Mass. 671, 675 (1977). Building Inspector of Lancaster v. Sanderson, 372 Mass. 157, 160 (1977).

1. Modification of the Contract.

The defendant argues that the judge erred in failing to rule that the contract was modified or that a settlement was reached in June, 1974. It argues that the terms of payment were changed to provide that the defendant would pay for the fixtures after completion rather than after receipt. The letters relied on by the defendant do not compel a finding of modification as a matter of law. Nor can we say that the judge’s findings are clearly erroneous. The June 4,1974, letter of the defendant stated that the units would be billed upon "completionthe plaintiffs reply thanked the defendant for its letter "confirming our verbal agreement to bill you,” and enclosed a bill for the remaining 560 undelivered fixtures. The bill was not paid and, in response to inquiries by the plaintiff, the defendant in September wrote "as stated on our purchase orders, we will recognize and pay your invoices for fixtures as they are shipped.” A subsequent letter, written on behalf of the plaintiff, stated that the fixtures were completed and that, therefore, payment was due. It is apparent that even if the parties had agreed in June that payment was to be made on "completion,” they had (and still have on this appeal) totally different views as to what was meant by that term. There is thus no basis for setting aside findings which failed to conclude that a settlement was effected, but found only that the parties sought to resolve the problem.

*841 2. Applicability of c. 106, §2-708, to this Action.

Most of the remaining contentions of the defendant relate to the application of the Uniform Commercial Code, G. L. c. 106 2 (code), to the circumstances of this action. The complaint alleged a breach of contract and sought recovery for the amount set forth in the purchase orders and incidental expenses. No specific code section was cited in the complaint or in the master’s report, but the motion judge, the trial judge and the parties on appeal have treated the action as one under §2-709, an action for the price.

The defendant argues vigorously that an action for the price does not lie. However, even if the defendant is correct in this contention, it would not prevail in this action. The plaintiffs award is clearly proper under § 2-708, and we therefore affirm the judgment on that ground, leaving to another occasion the resolution of the questions posed by a recovery under § 2-709. 3 4 For the purposes of this appeal we assume, without deciding, that an action for the price is not available. In this event, § 2-709(3) allows recovery under § 2-708. See Comment 7 to § 2-703 of the *842 Uniform Commercial Code, 1A U.L.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SEC America, LLC v. Marine Electric Systems, Inc.
2011 VT 125 (Supreme Court of Vermont, 2011)
Auto Shine Car Wash Systems, Inc. v. Nice 'N Clean Car Wash, Inc.
792 N.E.2d 682 (Massachusetts Appeals Court, 2003)
Interstate Litho Corp. v. Brown
255 F.3d 19 (First Circuit, 2001)
Mexamerican Hides, S.A. v. Central International Co.
2000 Mass. App. Div. 327 (Mass. Dist. Ct., App. Div., 2000)
Dunkin' Donuts of America, Inc. v. Minerva, Inc.
956 F.2d 1566 (Eleventh Circuit, 1992)
Commonwealth Edison Co. v. Decker Coal Co.
653 F. Supp. 841 (N.D. Illinois, 1987)
Karen Construction Co. v. Lizotte
484 N.E.2d 1011 (Massachusetts Supreme Judicial Court, 1985)
Sterilite Corp. v. Continental Casualty Co.
479 N.E.2d 205 (Massachusetts Appeals Court, 1985)
Autonumerics, Inc. v. Bayer Industries, Inc.
696 P.2d 1330 (Court of Appeals of Arizona, 1984)
R. D. Matthews Construction Co. v. Planning Board
434 N.E.2d 684 (Massachusetts Appeals Court, 1982)
Roberts v. Grise
1982 Mass. App. Div. 17 (Mass. Dist. Ct., App. Div., 1982)
Ross v. Ross
430 N.E.2d 815 (Massachusetts Supreme Judicial Court, 1982)
Roblin Hope Industries, Inc. v. J. A. Sullivan Corp.
413 N.E.2d 1134 (Massachusetts Appeals Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
391 N.E.2d 270, 7 Mass. App. Ct. 837, 27 U.C.C. Rep. Serv. (West) 126, 1979 Mass. App. LEXIS 1227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cesco-manufacturing-corp-v-norcross-inc-massappct-1979.