Department of Transportation v. American Insurance

491 S.E.2d 328, 268 Ga. 505, 97 Fulton County D. Rep. 3498, 1997 Ga. LEXIS 601
CourtSupreme Court of Georgia
DecidedSeptember 22, 1997
DocketS97A0596
StatusPublished
Cited by11 cases

This text of 491 S.E.2d 328 (Department of Transportation v. American Insurance) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Department of Transportation v. American Insurance, 491 S.E.2d 328, 268 Ga. 505, 97 Fulton County D. Rep. 3498, 1997 Ga. LEXIS 601 (Ga. 1997).

Opinions

Sears, Justice.

The Georgia Department of Transportation (“DOT”) appeals from the trial court’s entry of summary judgment against it in this dispute concerning under what conditions a bidder on a DOT construction contract is obligated to forfeit its bid proposal guaranty. We find that under the circumstances of this case, both the relevant stat[506]*506utory scheme and basic principles of contract law dictate that the bidder was required to forfeit its bid proposal guaranty for refusing to execute a contract it had been awarded by DOT. Therefore, we reverse.

The relevant facts are stipulated to by both parties. DOT solicited bids for a bridge construction project. Mitchell Construction Company (“MCC”) submitted its bid along with a five percent bid proposal guaranty, or bid bond, as required by the Transportation Code (“the Code”).1 The bids were opened, and MCC’s bid was the lowest reliable one. MCC then realized that it had made a unilateral error of approximately $299,000 in calculating its bid, and asked DOT to release it from its bid bond obligation. DOT refused, and MCC then informed DOT by letter that it was withdrawing its bid. DOT refused to accept the withdrawal, formally accepted MCC’s bid, and publicly announced that MCC had been awarded the construction project. DOT forwarded a contract to MCC, which MCC refused to execute. DOT then awarded the contract to the next lowest reliable bidder, and filed against MCC’s surety, appellee American Insurance Company, to collect MCC’s bid bond of approximately $148,000. The insurance company refused to pay the bond. After negotiations, the parties agreed to file an action in the superior court to determine their respective rights and obligations concerning the bond. Pending resolution of that action, the insurance company paid the bid bond to DOT.

In the superior court, the insurance company filed for declaratory judgment, and both parties moved for summary judgment. The trial court granted summary judgment to the insurance company, and ruled that because MCC’s bid was based upon an unintentional unilateral clerical mistake, it would be relieved of its obligation to forfeit the bid bond under the principle of “equitable rescission.” DOT filed this appeal, challenging the propriety of equitable relief in this case.

1. The Code requires that, in order for a bid on a DOT construction project to be considered, it must be accompanied by a proposal guaranty, or bid bond.2 The bid bond requirement is intended to ensure that a successful bidder will execute a contract on which it [507]*507bid.3 The Code also states that a bid bond will be returned to a bidder, so long as DOT receives the bidder’s written withdrawal of the bid before bids are opened.4 Once bids are submitted, DOT is required to award the contract being bid upon to the lowest reliable bidder, provided that DOT also is authorized to reject all bids submitted.5 If the lowest reliable bidder refuses to accept or execute a contract it has been awarded, its bid bond becomes the property of DOT as liquidated damages.6 In that instance, DOT is authorized to award the contract to the next lowest reliable bidder.7

Thus, under the statutory scheme for the submission of bids to construct DOT projects, the common law principle that a bid, as an offer, may unconditionally be withdrawn at any time prior to acceptance8 is not altogether applicable. The Code permits the withdrawal of bids submitted for DOT projects without penalty only before the official opening of bids. Once bids are opened, if a bidder withdraws its bid, the Code dictates that its bid bond is forfeited, regardless of whether the lowest reliable bid has yet been formally accepted. In this regard, the contracting process dictated by the Transportation Code differs markedly from the common law and Georgia’s codification thereof.9

It is presumed that when it enacted the proposal guaranty statute in 1973, the General Assembly was aware that in common law, an offer may be withdrawn anytime before actual acceptance, and that the General Assembly intended to change that common law principle within the public bidding context.10 That being so, we do not believe that the General Assembly intended that a bid bond, once submitted, should be rendered a meaningless gesture in the event the bidder posting the bond declines the offered contract. To the contrary, the bid bond’s “purpose is to compel the bidder to enter into a contract if his bid is accepted, or to compensate the public body, at least to some extent, for losses incurred if the bidder defaults.”11

Accordingly, we find that under the statutory scheme delineated for DOT construction projects, MCC was not authorized to withdraw its bid without penalty once all of the bids submitted were opened. [508]*508Nor could MCC refuse to execute a contract awarded to it after its bid was determined to be the lowest reliable one, without being assessed a penalty. Because MCC first attempted to withdraw its bid, and then declined to execute the contract awarded to it, the Code dictates that its bid bond be forfeited.

2. Notwithstanding the prohibition against the withdrawal of bids after they are opened, the Code appears to authorize DOT to relieve a lowest reliable bidder of its duty to perform a contract awarded to it, due to “an obvious error” contained in a bid.12 In this case, the contractor, MCC, mistakenly calculated its bid by using the incorrect quantities of concrete required for the construction project, resulting in an omission of approximately $299,000 from its bid price. MCC claims that because the correct specifications for concrete were provided to all bidders by DOT, MCC’s clerical error in calculating its bid was “obvious,” entitling it to be relieved of its duty to perform. However, even if the bid contains an “obvious error,” the statute does not appear to require DOT to relieve a bidding contractor of its contractual duties. Rather, the statute simply states that, “if” DOT releases a bidding contractor due to an obvious error contained in a bid, the contract shall be awarded to the next lowest bidder. Accordingly, pretermitting whether MCC’s unilateral clerical mistake concerning the quantities of concrete was, in fact, “obvious,” we conclude that in this case, DOT was not obligated to release MCC from its contractual obligations.13

3. We also find that under the clear terms of MCC’s bid, it had no authority to withdraw it within the 50 days following the bids’ opening. MCC’s bid stated that:

It is understood and agreed that... in consideration of the sum of One Dollar cash in hand paid, receipt whereof is hereby acknowledged, [MCC] agrees that this proposal shall be an option, which is hereby given to [DOT] to accept or reject this proposal at any time within fifty (50) days from the date on which [it] is opened and read . . . it is expressly covenanted and agreed that this proposal is not subject to withdrawal by the bidder during the term of said option.

From this language, it is clear that MCC’s bid was made in the form of an option contract supported by adequate consideration, and MCC [509]*509could not withdraw DOT’s right to either accept or reject the bid during the 50-day option period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

INNOVATIVE IMAGES, LLC v. SUMMERVILLE
848 S.E.2d 75 (Supreme Court of Georgia, 2020)
Northlake Manor Condominium Association, Inc. v. Harvest Assests, LLC
812 S.E.2d 658 (Court of Appeals of Georgia, 2018)
Andrea Liu v. US Bank National Association
179 A.3d 871 (District of Columbia Court of Appeals, 2018)
Decision One Mortgage Co. v. Victor Warren Properties, Inc.
696 S.E.2d 145 (Court of Appeals of Georgia, 2010)
Morrell v. Wellstar Health System, Inc.
633 S.E.2d 68 (Court of Appeals of Georgia, 2006)
Coppler & Mannick, P.C. v. Wakeland
2005 NMSC 022 (New Mexico Supreme Court, 2005)
Security Life Insurance v. St. Paul Fire & Marine Insurance
588 S.E.2d 319 (Court of Appeals of Georgia, 2003)
In Re Estate of Miller
840 So. 2d 703 (Mississippi Supreme Court, 2003)
Jeanette Page v. Ann H. Miller
Mississippi Supreme Court, 2002
Department of Transportation v. American Insurance
491 S.E.2d 328 (Supreme Court of Georgia, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
491 S.E.2d 328, 268 Ga. 505, 97 Fulton County D. Rep. 3498, 1997 Ga. LEXIS 601, Counsel Stack Legal Research, https://law.counselstack.com/opinion/department-of-transportation-v-american-insurance-ga-1997.