Amwest Surety Insurance v. Ra-Lin & Associates, Inc.

455 S.E.2d 106, 216 Ga. App. 526, 95 Fulton County D. Rep. 942, 1995 Ga. App. LEXIS 226
CourtCourt of Appeals of Georgia
DecidedMarch 8, 1995
DocketA94A2004
StatusPublished
Cited by15 cases

This text of 455 S.E.2d 106 (Amwest Surety Insurance v. Ra-Lin & Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amwest Surety Insurance v. Ra-Lin & Associates, Inc., 455 S.E.2d 106, 216 Ga. App. 526, 95 Fulton County D. Rep. 942, 1995 Ga. App. LEXIS 226 (Ga. Ct. App. 1995).

Opinion

McMurray, Presiding Judge.

Plaintiff Amwest Surety Insurance Company (“Amwest”) brought this contract action against defendant RA-LIN & Associates, Inc. (“RA-LIN”) and RA-LIN’s insurer, St. Paul Fire & Marine In *527 surance Company (“St. Paul”), alleging that RA-LIN “refused to proceed with the completion . . .” of a construction project (hereafter “the Completion Contract”) for low-income housing owned by the Housing Authority of the City of Grantville, Georgia (“Housing Authority”). As a result of RA-LIN’s alleged breach of the Completion Contract, “Amwest was forced to contract with the next lowest bidder.” A separate count asserted a claim in the amount of five percent of RA-LIN’s total bid price against a bid bond issued by St. Paul. In its answer, RA-LIN admitted that it submitted a bid and that it “was chosen as the low bidder . . . ,” but denied all other material allegations and asserted, inter alia, that no enforceable contract was ever reached or else Amwest itself breached any agreement by rejecting RA-LIN’s tender of performance.

After discovery, RA-LIN moved for partial summary judgment and Amwest filed a cross-motion for partial summary judgment against both RA-LIN and St. Paul. The evidence adduced in support of these motions showed the following material facts: Amwest, as surety, issued a payment bond and performance bond to Dennis Welding Construction Company, Inc., the original contractor on a construction project for the renovation of certain low-income housing units owned by the Housing Authority. This original contractor was declared to be in default of its contractual obligations and the Housing Authority called on Amwest as surety to make good performance. Amwest determined to re-let the project for completion by another contractor. Alvin G. Rowe, a “Senior Consultant” with Surety & Construction Consultants, Inc., testified that “Amwest asked us [Surety & Construction Consultants, Inc.,] to . . . inspect the project, prepare our estimate of the cost to complete, and make recommendations on how to proceed to meet any obligations [Amwest] might have regarding the performance aspects of the bond.” Amwest undertook to procure a “Relet Contractor to perform all work remaining to be completed in accordance with the terms and conditions of the original contract. . . .”

Mr. Rowe “prepared the [re-bid] documents . . . [and submitted] them to Amwest for [its] approval. . . .” “[A]ll five potential bidders were mailed those documents [, which contain an invitation to attend a] pre-bid conference.” On Tuesday, May 28, 1991, Mr. Rowe held the pre-bid conference to go over the re-bid documents and to answer any questions for the potential bidders. Mr. Rowe “understood prior to the pre-bid conference that the Housing Authority would not accept a [completion] contract in which they were named as a party.” A representative of the Housing Authority informed Mr. Rowe “that per HUD regulations they [the Housing Authority] would not be in a position to accept — or to enter into a contract [directly] with the contractor. . . .” Hugh Palmer, a project manager for RA-LIN, attended *528 the pre-bid conference. There, he questioned Mr. Rowe as to the identity of the other contracting party to the Completion Contract. Specifically, he expressed concern on the part of RA-LIN about contracting with Amwest. Due to ongoing litigation between Amwest and RA-LIN over an unrelated contractual dispute, RA-LIN preferred to contract directly with the Housing Authority. By affidavit, Mr. Palmer deposed: “In response to my question, Mr. Rowe told me that the successful bidder would contract with the Grantville Housing Authority.” Mr. Rowe testified that he referred Mr. Palmer to the re-bid documents themselves, explaining “we can’t finish the completion contract until we get an agreement with the owner [Housing Authority] because ... it could go either way.”

The “Invitation to Bid” contained in part the following two provisions relating to time: “The successful bidder will be notified no later than five (5) days after the bid opening and will be expected to immediately enter into the construction contract. The successful bidder will only begin operations upon receipt of a notice to proceed. The notice to proceed will set the date at which the contract time will commence. ... All bids will be regarded as valid and in full force for 60 calendar days after receipt of bids.” This latter provision is restated in the form bid proposal immediately above the place for the bidder’s signature in the following language: This bid shall remain valid and “available for acceptance” for 60 calendar days from the bid date. (Emphasis supplied.) The “Scope of Work” provided that the successful bidder will be completing a “contract for Amwest Surety Insurance Company and the Housing Authority for the City of Grantville, Georgia. . . .” The re-bid documents further contained a proposed “Form of Agreement,” i.e., the form of that “agreement which Amwest and the Housing Authority are anticipating entering into with the successful bidder as the Completion Contractor.” The re-bid instructions stated that the successful bidder “may be required to enter into an agreement with Amwest only, or with the Housing Authority only.” However, in either case, the form of agreement “shall not be grounds for the Completion Contractor to . . . refuse to enter into a contract as long as the actual completion contract used . . . conforms in principle to the form agreement. . . .” This suggested form agreement named Amwest and the completion contractor as the only parties to the completion agreement.

Defendant RA-LIN was one of only two firms to submit bids. Hugh Palmer “came to the bid opening . . .” on June 4, 1991, where Mr. Rowe opened the bids and determined that RA-LIN’s bid was for the lowest dollar amount. Mr. Rowe told Mr. Palmer “as soon as I get an answer back from Amwest we’ll be sending you a proposed completion agreement to sign. . . . [T]hat’s our standard procedure. . . .” Mr. Rowe affirmed that he (or Amwest) “[was not] obli *529 gated to accept the low bidder. . . .” Nevertheless, Amwest “[decided] to accept RA-LIN as the successful bidder[.]” On June 7, 1991, Mr. Rowe “faxed a draft completion agreement to RA-LIN for review and consideration.” RA-LIN did not execute and return this completion agreement. When Mr. Rowe contacted James R. Fulford, president of RA-LIN, to inquire about execution of the contract, Mr. Fulford advised that RA-LIN was unwilling to contract directly with Amwest but would deal directly with the Housing Authority. Under cover of a letter dated June 26, 1991, Mr. Rowe forwarded “three more copies of the completion contracts to RA-LIN for its execution.” On July 24, 1991, Mr. Rowe received from James R. Fulford of RA-LIN a facsimile communication, advising as follows: “In response to your request for a signed agreement between RA-LIN & ASSOCIATES, INC. and Amwest Surety Insurance Company for the completion of the work on the [Grantville Housing Authority] project, RA-LIN believes that due to current ongoing litigation between RA-LIN and Amwest that it is not in the best interest of either RA-LIN or Amwest to enter into a completion agreement. However, RA-LIN is willing to sign a contract with the Grantville Housing Authority for the completion of all work remaining on the stated job. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pargar, LLC D/B/A Prudential Georgia Realty
Court of Appeals of Georgia, 2012
Pargar, LLC v. CP Summit Retail, LLC
730 S.E.2d 136 (Court of Appeals of Georgia, 2012)
Calhoun v. Cullum's Lumber Mill, Inc.
545 S.E.2d 41 (Court of Appeals of Georgia, 2001)
Yeazel v. Burger King Corp.
526 S.E.2d 112 (Court of Appeals of Georgia, 1999)
Destag of North America, Inc. v. LAN International, Inc.
512 S.E.2d 365 (Court of Appeals of Georgia, 1999)
Firstline Corp. v. Valdosta-Lowndes County Industrial Authority
511 S.E.2d 538 (Court of Appeals of Georgia, 1999)
Federal Paper Board Co. v. Harbert-Yeargin, Inc.
92 F. Supp. 2d 1342 (N.D. Georgia, 1998)
Sparks v. State
501 S.E.2d 562 (Court of Appeals of Georgia, 1998)
Tambone v. Indiana Insurance
493 S.E.2d 578 (Court of Appeals of Georgia, 1997)
Department of Transportation v. American Insurance
491 S.E.2d 328 (Supreme Court of Georgia, 1997)
Holbrook v. Executive Conference Center, Inc.
464 S.E.2d 398 (Court of Appeals of Georgia, 1995)
Hennessey v. Froehlich
464 S.E.2d 246 (Court of Appeals of Georgia, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
455 S.E.2d 106, 216 Ga. App. 526, 95 Fulton County D. Rep. 942, 1995 Ga. App. LEXIS 226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amwest-surety-insurance-v-ra-lin-associates-inc-gactapp-1995.